The document outlines a flowchart for determining the applicability of 40 CFR Part 60, Subpart Da to electric utility steam generating units based on various criteria such as heat input capacity, construction dates, and fuel types. It details the steps and conditions under which the facility must comply with specific standards and regulations. The flowchart serves as a guide for facilities subject to the Federal Operating Permits Program.

Uploaded by

loriannemadrid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
37 views73 pages

NSPS Subpart Da Flowchart

The document outlines a flowchart for determining the applicability of 40 CFR Part 60, Subpart Da to electric utility steam generating units based on various criteria such as heat input capacity, construction dates, and fuel types. It details the steps and conditions under which the facility must comply with specific standards and regulations. The flowchart serves as a guide for facilities subject to the Federal Operating Permits Program.

Uploaded by

loriannemadrid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Below is a flowchart describing 40 CFR Part 60, Subpart Da.

For the text of the


statute/rule, please go to 40 CFR Part 60, Subpart Da
(1 of 73)

Start

Is the electric
utility steam generating
unit capable of combusting
more than 250 MMBtu/hr heat input No
of fossil fuel (alone or in
combination with any
other fuel)?
§60.40Da(a)
§60.40Da(a)(1)
Yes

Was construction,
modification, or reconstruction
No
of the facility commenced after
September 18, 1978?

§60.40Da(a)(2)

Yes

Have there
been any changes
at the existing facility (not
40 CFR Part 60,
currently subject to NSPS, Subpart
Yes Subpart Da does
Da) to accommodate the use of
not apply.
combustible materials,
other than fossil
fuels?
§60.40Da(c)

No

1 End

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(2 of 73)

1 End

Has there
been any changes
at the existing facility (not
40 CFR Part 60,
currently subject to NSPS, Subpart Da)
Yes Subpart Da does
originally designed to fire gaseous or liquid
not apply.
fossil fuels, to accommodate the
use of any other
fuel?
§60.40Da(d)

No

Is the
affected facility
Yes
subject to NSPS Eb
or CCCC?
§60.40Da(e)(3)
No

No

Was construction,
Is the facility
modification, or reconstruction
an IGCC electric utility steam Yes
of the facility commenced after
generating unit?
February 28, 2005?

§60.40Da(b)
§60.40Da(b)(2)
No Yes

2 2a

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(3 of 73)

Is the facility an
electric utility combined
Is the
cycle gas turbine other than an IGCC
Yes facility subject to NSPS
electric utility steam generating unit
KKKK?
or unit that is NOT subject to
NSPS Eb or CCCC?
§60.40Da(e)(1)
Yes
§60.40Da(e)
§60.40Da(e)(1)

40 CFR Part 60,


Subpart Da does not
apply.
No
2a
No
End

Is the facility
operated under a PM
commercial demonstration permit Yes 13
in accordance with
§60.47Da?
§60.42Da(f)(2)

No

Does the
facility combust
only gaseous or liquid
fossil fuel (excluding residual oil)
with potential SO2 emissions rates of 26 ng/J No 2b
or less and does not use post-
combustion technology
to reduce SO2
or PM?
§60.42Da(f)(1)

Yes 13

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(4 of 73)

2b PM

Comply with the following:


Standard
§60.42Da(a)
Was construction,
§60.48Da(a)
modification, or reconstruction
No Monitoring/Testing
of the facility commenced after
§60.48Da(f)
February 28, 2005?
§60.50Da(a), [G](b), [G](e)
Reporting
§60.42Da(a) §60.51Da(a), [G](h), (j)

Yes

3a

Is the facility
Yes using a PM CEMS per No
§60.49Da(v)?

§60.49Da(v)
Comply with the following:
Monitoring/Testing
§60.49Da(g), [G](s), (t)
[G]§60.49Da(v)-(w)
Recordkeeping
[G]§60.49Da(s), [G](v)-(w)
Reporting
[G]§60.49Da(s), [G](v)-(w)

12 8

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(5 of 73)

3a

Was the facility


constructed or reconstructed
Yes 3
after 02/28/2005 and on or
before 05/03/2011?

§60.42Da(d)

No

Was the facility


constructed or reconstructed
No 4a
(as opposed to modified)
after 05/03/2011?

§60.42Da(e)(1)(i)

Yes 4c

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(6 of 73)

Has the owner


or operator elected §60.42Da(d)
as an alternative to §60.42Da(c)
for PM?
Yes No
§60.42Da(d)

Is the
facility complying with
the input based emission
No limit? Yes

§60.42Da(c)(2)
Comply with the following:
Standard
§60.42Da(d)(1) 4 5
§60.48Da(a)
Monitoring/Testing
§60.48Da(f), (o)(5)
§60.50Da(a), [G](b), [G](e)
Reporting
§60.51Da(a), [G](h), (j)

Was the facility


constructed or reconstructed
Yes (as opposed to modified) after No
02/28/2005 and on or before
05/03/2011?

§60.42Da(d)(2)

Comply with the following: Comply with the following:


Standard 5e Standard
§60.42Da(d)(2) §60.42Da(d)(3)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(7 of 73)

4a

Has the owner


or operator elected §60.42Da(d)
as an alternative to §60.42Da(c)
for PM?
Yes
No
§60.42Da(d)

Comply with the following:


Standard
§60.42Da(d)(1)
§60.48Da(a)
Is the
Monitoring/Testing
facility complying with
§60.48Da(f), (o)(5)
the input based emission
§60.50Da(a), (b), [G](e)
limit?
Reporting No
§60.51Da(a), [G](h), (j) Yes
§60.42Da(c)(2)

Comply with the following:


Standard 5a 5b
§60.42Da(d)(3), (e)(1)(ii)

Is the Comply with the following:


facility subject to 40 Standard
CFR Part 63, Subpart Yes
§60.42Da(e)(2)
DDDDD? §63.7500(a)(1)-Table 3
§60.42Da(e)(2)

No

Is the Comply with the following:


facility subject to 40 Standard
CFR Part 63, Subpart Yes
§60.42Da(e)(2)
UUUUU? §63.9991(a)(1)-Table 3
§60.42Da(e)(2)

No 5e

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(8 of 73)

4c

Is the
facility complying with
the gross output based
emission limit?
Yes §60.42Da(e)(1)(i) No

Comply with the following: Comply with the following:


Standard Standard
§60.42Da(e)(1)(i)(A) §60.42Da(e)(1)(i)(B)
§60.48Da(a) §60.48Da(a)
Monitoring/Testing Monitoring/Testing
§60.48Da(f), (n) §60.48Da(f), (n)
[G]§60.49Da(k), (t) [G]§60.49Da(k), (t)
§60.50Da(a), [G](b), [G](e) §60.50Da(a), [G](b), [G](e)
Recordkeeping Recordkeeping
[G]§60.49Da(k) [G]§60.49Da(k)
Reporting Reporting
§60.51Da(a), (b), (b)(1), (b)(2) §60.51Da(a), (b), (b)(1), (b)(2)
§60.51Da(b)(4), (b)(5), (b)(6) §60.51Da(b)(4), (b)(5), (b)(6)
§60.51Da(b)(7), (b)(8), (b)(9) §60.51Da(b)(7), (b)(8), (b)(9)
[G]§60.51Da(c), (f), [G](h) [G]§60.51Da(c), (f), [G](h)
§60.51Da(j), (k) §60.51Da(j), (k)

Is the Comply with the following:


facility subject to 40 Standard
CFR Part 63, Subpart Yes
§60.42Da(e)(2)
DDDDD? §63.7500(a)(1)-Table 3
§60.42Da(e)(2)
No

Is the Comply with the following:


facility subject to 40 Standard
CFR Part 63, Subpart Yes
§60.42Da(e)(2)
UUUUU? §63.9991(a)(1)-Table 3
§60.42Da(e)(2)

No 5f

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(9 of 73)

4 5

Comply with the following: Comply with the following:


Standard Standard
§60.42Da(c)(1) §60.42Da(c)(2)
§60.48Da(a) §60.48Da(a)
Monitoring/Testing Monitoring/Testing
§60.48Da(f), (n) §60.48Da(f)
[G]§60.49Da(k), (t) §60.50Da(a), [G](b), [G](e)
§60.50Da(a), [G](b), [G](e) Reporting
Recordkeeping §60.51Da(a), [G](h), (j)
[G]§60.49Da(k)
Reporting
§60.51Da(a), [G](h), (j)

5f 5e

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(10 of 73)

5a 5b

Comply with the following: Comply with the following:


Standard Standard
§60.42Da(c)(1) §60.42Da(c)(2)
§60.48Da(a) §60.48Da(a)
Monitoring/Testing Monitoring/Testing
§60.48Da(f), (n) §60.48Da(f)
[G]§60.49Da(k), (t) §60.50Da(a), (b), [G](e)
§60.50Da(a), (b), [G](e) Reporting
Recordkeeping §60.51Da(a), [G](h), (j)
[G]§60.49Da(k)
Reporting
§60.51Da(a), [G](h), (j)

Comply with the following: Comply with the following:


Standard Standard
§60.42Da(e)(1)(ii) §60.42Da(e)(1)(ii)

5c 5d

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(11 of 73)

5c

Is the Is the
facility subject to 40 facility subject to 40
CFR Part 63, Subpart No CFR Part 63, Subpart
DDDDD? UUUUUD?

§60.42Da(e)(2) No
Yes §60.42Da(e)(2) Yes

Comply with the following: Comply with the following:


Standard Standard
§60.42Da(e)(2) §60.42Da(e)(2)
§63.7500(a)(1)-Table 3 §63.9991(a)(1)-Table 3

5f

5d

Is the Is the
facility subject to 40 facility subject to 40
CFR Part 63, Subpart No CFR Part 63, Subpart
DDDDD? UUUUU?

§60.42Da(e)(2)
§60.42Da(e)(2)
No
Yes Yes

Comply with the following: Comply with the following:


Standard Standard
§60.42Da(e)(2) §60.42Da(e)(2)
§63.7500(a)(1)-Table 3 §63.9991(a)(1)-Table 3

5e

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(12 of 73)

5e

Is the facility
using a PM CEMS per
§60.48Da(p) as an alternative
Yes to §60.48Da(o)?

§60.48Da(p) No

Comply with the following:


Monitoring/Testing
[G]§60.48Da(p)
§60.49Da(g), [G](s) Comply with the following:
§60.49Da(t), [G](v)-(w) Monitoring/Testing
Recordkeeping §60.48Da(o)(1)
[G]§60.49Da(s), [G](v)-(w)
Reporting
[G]§60.49Da(s), [G](v)-(w)

12 6

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(13 of 73)

5f

Is the facility
using a PM CEMS per
§60.49Da(v)?
Yes
No
§60.49Da(t)

Comply with the following:


Monitoring/Testing
[G]§60.49Da(g), (s) Is the facility
[G]§60.49Da(v)-(w) using a CPMS per
Recordkeeping §63.10021(c)?
[G]§60.49Da(s), [G](v)-(w)
Yes
Reporting §60.49Da(t)
[G]§60.49Da(s), [G](v)-(w)

Comply with the following:


Monitoring/Testing No
[G]§60.49Da(s)
[G]§63.10021(c)
Recordkeeping
[G]§60.49Da(s)
[G]§63.10021(c)
Reporting
[G]§60.49Da(s)

12 8! 7

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(14 of 73)

Is the facility
Does the facility
using a predictive model per
use an electrostatic precipitator Yes
§60.48Da(o)(3) in place of a
for PM control?
COMS?

§60.48Da(o)(2) §60.48Da(o)(3)
Yes

No Comply with the following:


8! Monitoring/Testing
[G]§60.48Da(o)(3)

Is the facility
Does the facility No
using a leak detection system
use a fabric filter (baghouse) Yes No
per §60.48Da(o)(4)in place
for PM control?
of a COMS?

§60.48Da(o)(2) §60.48Da(o)(4)
No Yes

Comply with the following:


8! Monitoring/Testing
§60.48Da(o)(4)

Comply with the following:


Monitoring/Testing
[G]§60.48Da(o)(2)
[G]§60.49Da(s)
Recordkeeping
[G]§60.49Da(s)
Reporting
[G]§60.49Da(s)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(15 of 73)

Is the
facility a gas-fired or oil-
Comply with the following:
fired unit AND using an appendix D,
Yes Monitoring/Testing
part 75 fuel flow monitoring system as
§60.49Da(n)
an alternative to §60.49Da(l)
or (m)?

§60.49Da(n)

No 12

Is the facility
using an appendix A, Comply with the following:
part 75 continuous flow monitoring Yes Monitoring/Testing
system as an alternative §60.49Da(m)
to §60.49Da(l)?
§60.49Da(m)

No

Comply with the following:


Monitoring/Testing
§60.49Da(l) 12
Recordkeeping
§60.49Da(l)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(16 of 73)

8!

Is the facility an
electric utility combined cycle gas
No
turbine that does NOT meet the
definition of an IGCC?

§60.50Da(f)
Yes

Comply with the following:


Monitoring/Testing PM(Opacity)
§60.50Da(f)

12
Comply with the following:
Standard
§60.42Da(b)
§60.48Da(a)
Is the facility an Monitoring/Testing
electric utility combined cycle gas §60.48Da(q)
No §60.50Da(a), [G](b), [G](e)
turbine that does NOT meet the
definition of an IGCC? Recordkeeping
[G]§60.51Da(d)(1)
Reporting
§60.51Da(a), (d), (f)
§60.50Da(f) [G]§60.51Da(h), (i), (j), (k)
Yes

Comply with the following:


Monitoring/Testing 13 9
§60.50Da(f)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(17 of 73)

Does the facility


use a fabric filter to meet
§60.42Da standards and is a leak
detection system installed and operated per Yes
§60.48Da(o); and the facility elects
to monitor opacity per
§60.49Da(a)(3)

§60.49Da(a)(2)(i)
No

Does the facility


burn only gaseous or liquid
fossil fuel (excluding residual oil)
with potential SO2 emissions rates of 26 ng/J or
Yes 10
less and not use post combustion technology for
SO2 or PM; and the facility elects
to monitor opacity per
§60.49Da(a)(3)?

§60.49Da(a)(2)(ii)
Comply with the following:
No Monitoring/Testing
[G]§60.49Da(u)
Recordkeeping
[G]§60.49Da(u)
Does the facility not
use post combustion technology
(except a wet scrubber) for PM, SO2, or
CO; burn only gaseous fuels or fuel oils that contain
< 0.30 weight percent sulfur, operated such that emissions Yes
of CO are maintained at levels < to 1.4 lb/MWh on
a boiler operating day average basis; and
the facility elects to monitor opacity
per §60.49Da(a)(3)?

§60.49Da(a)(2)(iii)(A)-(C)

No 9a

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(18 of 73)

9a

Does the facility use an


ESP and ESP predictive model to
monitor the performance of the ESP developed in
Yes 10
accordance and operated according to the most
current requirements in section
§60.48Da of this part?

§60.49Da(a)(2)(iv)
No

Does the facility combust


only gas and/or liquid fuels (excluding
residual oil) with potential SO2 emissions rate
of each fuel is less than 26 ng/J (0.060 lb/MMBtu), and Yes 11a
the unit operates according to a written site-
specific monitoring plan approved by
the permitting authority?

§60.49Da(a)(4)
No

Does the facility


maintain a particulate matter continuous
parametric monitoring system (PM CPMS) according Yes 11c
to the requirements specified in subpart
UUUUU of part 63?

§60.49Da(a)(4)

No 11

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(19 of 73)

Comply with the following:


Monitoring/Testing
10 [G]§60.49Da(a)(3)
Recordkeeping
[G]§60.52Da(b)

Comply with the following:


Monitoring/Testing
§60.49Da(a)(1), (i), (i)(3)
[G]§60.49Da(s)
11
Recordkeeping
[G]§60.49Da(s)
Reporting
[G]§60.49Da(s)
13
Comply with the following:
Standard
§60.49Da(a)(4)(i)
Monitoring/Testing
11a §60.49Da(a)(4)(i), [G](s)
Recordkeeping
[G]§60.49Da(s)
Reporting
[G]§60.49Da(s)

Comply with the following:


Standard
§60.49Da(a)(4)(ii)
[G]§63.10010(a), (h)
11c Monitoring/Testing
§60.49Da(a)(4)(ii)
[G]§63.10010(a), (h)
Recordkeeping
[G]§63.10010(h)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(20 of 73)

13

Is the facility
operated under an SO2
commercial demonstration permit Yes 34
in accordance with
§60.47Da?
§60.43Da(f)

No

SO2

Was construction,
modification, or reconstruction
Yes 14
of the facility commenced before
March 1, 2005?

§60.43Da(a), (b)
No

Does the facility


burn 75% or more coal
No 20
refuse on a 12-month rolling
average basis?

§60.43Da(j)

Yes 26

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(21 of 73)

14 Comply with the following:


Standard
§60.43Da(c)
§60.48Da(a)
Monitoring/Testing
§60.48Da(b), (c), (d), (e), (h)
§60.49Da(b), (d), (e), (f)(1)
Is the §60.49Da(h), (h)(1), (h)(3)-(4)
affected facility combusting §60.49Da(j)(1), (j)(3), (j)(4)
solid solvent refined coal [G]§60.49Da(2), [G](w)
(SRC-I)? §60.50Da(a), [G](c), [G](e)
Recordkeeping
§60.43Da(c) §60.49Da(b), (d)-(e), [G](s), [G](w)
Reporting
No §60.49Da(c), [G](s), [G](w)
§60.51Da(a), (b), (b)(1)-(9)
[G]§60.51Da(c), [G](e), (f), [G](h)
§60.51Da(j)-(k)
Is the affected
facility combusting 100% Yes
anthracite?

31
§60.43Da(d)(1)
No

Is the
affected facility classified
Yes
as a resource recovery
unit?
Comply with the following:
§60.43Da(d)(2) Standard
§60.43Da(d)
No §60.43Da(g)
§60.48Da(a)
Monitoring/Testing
§60.48Da(b), (c), (d)
15 §60.49Da(j)(1), (j)(3)-(4), [G](w)
§60.50Da(a), [G](c), [G](e) 17f
Recordkeeping
[G]§60.49Da(w)
Reporting
§60.48Da(c)
[G]§60.49Da(w)
§60.51Da(a), (b), (b)(1)-(2)
§60.51Da(b)(4)-(9), [G](c), [G](e)
§60.51Da(f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(22 of 73)

15

Is the affected
facility simultaneously combusting No 16
different fuels?

§60.43Da(h)
Comply with the following:
Yes Standard
§60.43Da(h)(2)
§60.43Da(g)
§60.48Da(a)
Monitoring/Testing
Are emissions
§60.48Da(b), (c), (d)
< 0.60 lb/MMBtu Yes
§60.49Da(j)(1), (j)(3)-(4)
heat input?
§60.50Da(a), [G](c), [G](e)
Reporting
§60.43Da(h)(2) §60.48Da(c)
§60.51Da(a), (b), (b)(1)-(2)
No §60.51Da(b)(4)-(9), [G](c), [G](e)
§60.51Da(f), [G](h), (j)-(k)

Comply with the following:


Standard
§60.43Da(h)(1)
§60.43Da(g)
§60.48Da(a)
Monitoring/Testing
§60.48Da(b), (c), (d), (h)
18c
§60.49Da(j)(1), (j)(3)-(4)
§60.50Da(a), [G](c), [G](e)
Reporting
§60.48Da(c)
§60.51Da(a), (b), (b)(1)-(2)
§60.51Da(b)(4)-(9), [G](c), [G](e)
§60.51Da(f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(23 of 73)

16

Is
the affected
facility combusting solid or No 17
solid-derived
fuel?
§60.43Da(a)

Yes

Are SO2
emissions < 1.4 lb/MWh
Yes 16b
gross energy
output?
§60.43Da(a)(3)

No

Are SO2
emissions < 0.15 lb/MMBtu Yes 16c
heat input?

§60.43Da(a)(4)

No

Are
emissions < 0.60 lb/MMBtu Yes 16a
heat input?

§60.43Da(a)(2)

No 16d

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(24 of 73)

Comply with the following:


Standard
§60.43Da(a)(2)
§60.43Da(g)
§60.48Da(a)
Monitoring/Testing
§60.48Da(b), (c), (d), (e)
16a 17c
§60.49Da(j)(1), (j)(3)-(4)
§60.50Da(a), [G](c), [G](e)
Reporting
§60.48Da(c)
§60.51Da(a), (b), (b)(1)-(9)
[G]§60.51Da(c), [G](e), (f), [G](h)
§60.51Da(j)-(k)

Comply with the following:


Standard
§60.43Da(a)(3)
§60.43Da(g)
§60.48Da(a)
Monitoring/Testing
§60.48Da(b), (c), (d)
§60.49Da(j)(1), (j)(3)-(4), [G](k)
16b 17a
§60.50Da(a), [G](c), [G](e)
Recordkeeping
[G]§60.49Da(k)
Reporting
§60.48Da(c)
§60.51Da(a), (b), (b)(1)-(2)
§60.51Da(b)(4)-(9), [G](c), [G](e)
§60.51Da(f), [G](h), (j)-(k)

Comply with the following:


Standard
§60.43Da(a)(4)
§60.43Da(g)
§60.48Da(a)
Monitoring/Testing
§60.48Da(b), (c), (d)
16c 18c
§60.49Da(j)(1), (j)(3)-(4)
§60.50Da(a), [G](c), [G](e)
Reporting
§60.48Da(c)
§60.51Da(a), (b), (b)(1)-(2)
§60.51Da(b)(4)-(9), [G](c), [G](e)
§60.51Da(f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(25 of 73)

16d
Comply with the following:
Standard
§60.43Da(a)(1)
§60.43Da(g)
§60.48Da(a)
Monitoring/Testing
§60.48Da(b), (c), (d), (e), (h)
§60.49Da(b), (d)-(e), (f)(1)
§60.49Da(g), (h), (h)(1), (h)(3)-(4)
§60.49Da(i), (i)(1), (j)(1), (j)(3)-(4)
[G]§60.49Da(s), [G](w) 19b
§60.50Da(a), [G](c), [G](e)
Recordkeeping
§60.49Da(b), (d)-(e)
[G]§60.49Da(s), [G](w)
Reporting
§60.48Da(c)
[G]§60.49Da(s), [G](w)
§60.51Da(a), (b), (b)(1)-(9)
[G]§60.51Da(c), [G](e), (f), [G](h)
§60.51Da(j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(26 of 73)

These requirements are


for facilities combusting liquid or
17
gaseous fuels [except the fuels
under §60.43Da(a) or (h)]
Comply with the following:
Standard
§60.43Da(b)(2)
§60.43Da(g)
§60.48Da(a)
Are Monitoring/Testing
emissions less than §60.48Da(b), (c), (d), (e)
No Yes
0.20 lb/MMBtu heat §60.49Da(j)(1), (j)(3)-(4)
input? §60.50Da(a), [G](c), [G](e)
Reporting
§60.43Da(b)(2)
§60.48Da(c)
17d §60.51Da(a), (b), (b)(1)-(9)
[G]§60.51Da(c), [G](e), (f), [G](h)
§60.51Da(j)-(k)

17b

17f
Does the
facility combust
only gaseous or liquid fuels
(excluding residual oil) with potential
Yes
SO2 emissions rates of 26 ng/J
(0.060 lb/MMBtu) or less
as specified in
60.49Da(b)?

§60.49Da(b)

No 18b 33

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(27 of 73)

17a
Does the
facility combust
only gaseous or liquid fuels
(excluding residual oil) with potential
Yes
SO2 emissions rates of 26 ng/J
(0.060 lb/MMBtu) or less
as specified in
60.49Da(b)?
§60.49Da(b)

No 18
32a

17b
Does the
facility combust
only gaseous or liquid fuels
(excluding residual oil) with potential
Yes
SO2 emissions rates of 26 ng/J
(0.060 lb/MMBtu) or less
as specified in
60.49Da(b)?
§60.49Da(b)

No 19 33

17c Does the


facility combust
only gaseous or liquid fuels
(excluding residual oil) with potential
Yes
SO2 emissions rates of 26 ng/J
(0.060 lb/MMBtu) or less
as specified in
60.49Da(b)?
§60.49Da(b)

No 19a

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(28 of 73)

17d Comply with the following:


Standard
§60.43Da(b)(1)
§60.43Da(g)
§60.48Da(a)
Monitoring/Testing
§60.48Da(b), (c), (d), (e), (h)
§60.49Da(b), (d)-(e), (f)(1)
§60.49Da(g), (h), (h)(1), (h)(3)-(4)
§60.49Da(i), (i)(1), (j)(1), (j)(3)-(4)
19b
[G]§60.49Da(s), [G](w)
§60.50Da(a), [G](c), [G](e)
Recordkeeping
§60.49Da(b), (d)-(e), [G](s), [G](w)
Reporting
§60.48Da(c)
[G]§60.49Da(s), [G](w)
§60.51Da(a), (b), (b)(1)-(9)
[G]§60.51Da(c), [G](e), (f), [G](h)
§60.51Da(j)-(k)

18c Comply with the following:


Monitoring/Testing
§60.48Da(h)
§60.49Da(b), (e), (f)(1)
§60.49Da(h), (h)(1), (h)(3)-(4)
[G]§60.49Da(s), [G](w)
Recordkeeping
§60.49Da(b), (e), [G](s), [G](w)
Reporting
[G]§60.49Da(s), [G](w)

Does the owner


or operator use a SO2
No CEMS installed according to appendix Yes
A of part 75 to monitor
SO2 emissions?
§60.49Da(b)(4)

Comply with the following: Comply with the following:


Monitoring/Testing 33 Monitoring/Testing
§60.49Da(b)(2), (g), (i), (i)(1)-(2), (i)(5) [G]§60.49Da(b)(4)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(29 of 73)

18 Comply with the following:


Monitoring/Testing
§60.48Da(h)
§60.49Da(b), (e), (f)(1)
§60.49Da(h), (h)(1), (h)(4), [G](s), [G](w)
Recordkeeping
§60.49Da(b), (e), [G](s), [G](w)
Reporting
[G]§60.49Da(s), [G](w)

18a
Does the owner
or operator use a SO2 Comply with the following:
CEMS installed according to appendix A Yes Monitoring/Testing
of part 75 to monitor [G]§60.49Da(b)(4)
SO2 emissions?

§60.49Da(b)(4)
No

Comply with the following:


Monitoring/Testing 32a
§60.49Da(b)(2), (g), (i), (i)(1)-(2), (i)(5)

Comply with the following:


18b Monitoring/Testing
§60.48Da(h)
§60.49Da(b), (e), (f)(1)
§60.49Da(h), (h)(1), (h)(4), [G](s)
Recordkeeping
§60.49Da(b), (e), [G](s)
Reporting
[G]§60.49Da(s)

Does the owner


or operator use a SO2
No CEMS installed according to appendix Yes
A of part 75 to monitor
SO2 emissions?
§60.49Da(b)(4)

Comply with the following: Comply with the following:


Monitoring/Testing 33 Monitoring/Testing
§60.49Da(b)(2), (g), (i), (i)(1)-(2), (i)(5) [G]§60.49Da(b)(4)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(30 of 73)

19 Comply with the following:


Monitoring/Testing
§60.48Da(h)
§60.49Da(b), (e), (f)(1)
§60.49Da(h), (h)(1), (h)(3)-(4)
[G]§60.49Da(s), [G](w)
Recordkeeping
§60.49Da(b), (e)
[G]§60.49Da(s), [G](w)
Reporting
[G]§60.49Da(s), [G](w)

Is an as-fired
Comply with the following:
fuel monitoring system
Yes Monitoring/Testing
used at the inlet to the
§60.49Da(b)(3)
control device?
§60.49Da(b)(3)

No

Does the owner


or operator use a SO2 Comply with the following:
CEMS installed according to appendix A Yes Monitoring/Testing
of part 75 to monitor [G]§60.49Da(b)(4)
SO2 emissions?

§60.49Da(b)(4)
No

Comply with the following:


Monitoring/Testing 33
§60.49Da(b)(1), (g), (i), (i)(1)-(2), (i)(5)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(31 of 73)

19a Comply with the following:


Monitoring/Testing
§60.48Da(h)
§60.49Da(b), (e), (f)(1)
§60.49Da(h), (h)(1), (h)(3)-(4)
[G]§60.49Da(s), [G](w)
Recordkeeping
§60.49Da(b), (e)
[G]§60.49Da(s), [G](w)
Reporting
[G]§60.49Da(s), [G](w)

Is an as-fired
Comply with the following:
fuel monitoring system
Yes Monitoring/Testing
used at the inlet to the
§60.49Da(b)(3)
control device?
§60.49Da(b)(3)

No

Does the owner


or operator use a SO2 Comply with the following:
CEMS installed according to appendix A Yes Monitoring/Testing
of part 75 to monitor [G]§60.49Da(b)(4)
SO2 emissions?

§60.49Da(b)(4)
No

Comply with the following:


Monitoring/Testing 33
§60.49Da(b)(1), (g), (i), (i)(1)-(2), (i)(5)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(32 of 73)

19b

Is an as-fired
Comply with the following:
fuel monitoring system
Yes Monitoring/Testing
used at the inlet to the
§60.49Da(b)(3)
control device?

§60.49Da(b)(3)

No

Does the owner


or operator use a SO2 Comply with the following:
CEMS installed according to appendix A Yes Monitoring/Testing
of part 75 to monitor [G]§60.49Da(b)(4)
SO2 emissions?

§60.49Da(b)(4)

No

Comply with the following:


Monitoring/Testing 33a
§60.49Da(b)(1), (i)(2), (i)(5)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(33 of 73)

20 Yes 28a

Was the facility Was the facility


constructed, reconstructed, constructed or reconstructed
Yes
or modified after (as opposed to modified) after
May 3, 2011? May 3, 2011?

§60.43Da(l) §60.43Da(l)(1)

No 28b
No

Yes 21

Was the facility


Was the facility
constructed (as opposed to
reconstructed (as opposed to
reconstructed or modified) after No
modified) after February 28, 2005,
February 28, 2005, but before
but before May 4, 2011?
May 4, 2011?
§60.43Da(i)(1)
§60.43Da(i)(2)

No 22

Yes 20a

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(34 of 73)

SO2 requirements
for facilities constructed
20a
after February 25, 2005,
but before May 4, 2011.
Comply with the following:
Standard
§60.43Da(i)(1)(ii)
§60.43Da(g)
§60.48Da(a)
Monitoring/Testing
Is the facility
§60.48Da(b), (c), (d), (e)
meeting the output based
§60.49Da(j)(1), (j)(3), (j)(4)
emission limit?
§60.50Da(a), [G](c), [G](e)
Reporting
§60.43Da(i)(1)(i) §60.48Da(c)
§60.51Da(a), (b), (b)(1)-(9)
[G]§60.51Da(c), [G](e)
Yes
§60.51Da(f), [G](h), (j)-(k)

Comply with the following:


Standard
§60.43Da(i)(1)(i)
§60.43Da(g) 25
§60.48Da(a)
Monitoring/Testing
§60.48Da(b), (c), (d), (m)
§60.49Da(j)(1), (j)(3), (j)(4), [G](k)
23
§60.50Da(a), [G](c), [G](e)
Recordkeeping
[G]§60.49Da(k)
Reporting
§60.48Da(c)
§60.51Da(a), (b), (b)(1)-(2)
§60.51Da(b)(4)-(9), [G](c), [G](e)
§60.51Da(f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(35 of 73)

Comply with the following:


21
Standard
§60.43Da(i)(2)(ii)
§60.43Da(g)
§60.48Da(a)
These requirements are Monitoring/Testing
for facilities reconstructed §60.48Da(b), (c), (d)
24
after February 28, 2005, §60.49Da(j)(1), (j)(3), (j)(4)
but before May 4, 2011. §60.50Da(a), [G](c), [G](e)
Reporting
§60.48Da(c)
§60.51Da(a), (b), (b)(1)-(2)
§60.51Da(b)(4)-(9), [G](c), [G](e)
§60.51Da(f), [G](h), (j)-(k)

Is the facility
meeting the output based
emission limit? Yes

No
§60.43Da(i)(2)(i)

Yes Is the facility


meeting the input based
emission limit?

Comply with the following:


Standard §60.43Da(i)(2)(ii)
§60.43Da(i)(2)(i) No
§60.43Da(g)
§60.48Da(a)
Monitoring/Testing Comply with the following:
§60.48Da(b), (c), (d), (m) Standard
§60.49Da(j)(1), (j)(3), (j)(4), [G](k) §60.43Da(i)(2)(iii)
23
§60.50Da(a), [G](c), [G](e) §60.43Da(g)
Recordkeeping §60.48Da(a)
[G]§60.49Da(k) Monitoring/Testing
Reporting §60.48Da(b), (c), (d), (e)
§60.48Da(c) 25
§60.49Da(j)(1), (j)(3), (j)(4)
§60.51Da(a), (b), (b)(1)-(2) §60.50Da(a), [G](c), [G](e)
§60.51Da(b)(4)-(9), [G](c), [G](e) Reporting
§60.51Da(f), [G](h), (j)-(k) §60.48Da(c)
§60.51Da(a), (b), (b)(1)-(9)
[G]§60.51Da(c), [G](e)
§60.51Da(f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(36 of 73)

22 Comply with the following:


Standard
§60.43Da(i)(3)(ii)
§60.43Da(g)
§60.48Da(a)
These requirements are Monitoring/Testing
for facilities modified after §60.48Da(b), (c), (d)
February 28, 2005, but 24
§60.49Da(j)(1), (j)(3), (j)(4)
before May 4, 2011. §60.50Da(a), [G](c), [G](e)
Reporting
§60.48Da(c)
§60.51Da(a), (b), (b)(1)-(2)
§60.51Da(b)(4)-(9), [G](c), [G](e)
§60.51Da(f), [G](h), (j)-(k)

Is the facility
meeting the output based
emission limit? Yes

§60.43Da(i)(3)(i) No

Yes Is the facility


meeting the input based
emission limit?

Comply with the following:


§60.43Da(i)(3)(ii)
Standard
§60.43Da(i)(3)(i) No
§60.43Da(g)
§60.48Da(a)
Monitoring/Testing
Comply with the following:
§60.48Da(b), (c), (d), (m)
Standard
§60.49Da(j)(1), (j)(3), (j)(4), [G](k)
23 §60.43Da(i)(3)(iii)
§60.50Da(a), [G](c), [G](e)
§60.43Da(g)
Recordkeeping
§60.48Da(a)
[G]§60.49Da(k)
Monitoring/Testing
Reporting
§60.48Da(b), (c), (d), (e)
§60.48Da(c) 25
§60.49Da(j)(1), (j)(3), (j)(4)
§60.51Da(a), (b), (b)(1)-(2)
§60.50Da(a), [G](c), [G](e)
§60.51Da(b)(4)-(9), [G](c), [G](e)
Reporting
§60.51Da(f), [G](h), (j)-(k)
§60.48Da(c)
§60.51Da(a), (b), (b)(1)-(9)
[G]§60.51Da(c), [G](e)
§60.51Da(f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(37 of 73)

23
Does the
facility combust
only gaseous or liquid fuels
(excluding residual oil) with potential
Yes
SO2 emissions rates of 26 ng/J
(0.060 lb/MMBtu) or less
as specified in
60.49Da(b)?
§60.49Da(b)

No 29 32a

24

Does the
facility combust
only gaseous or liquid fuels
(excluding residual oil) with potential
Yes
SO2 emissions rates of 26 ng/J
(0.060 lb/MMBtu) or less
as specified in
60.49Da(b)?
§60.49Da(b)

No 30
33

25
Does the
facility combust
only gaseous or liquid fuels
(excluding residual oil) with potential
Yes
SO2 emissions rates of 26 ng/J
(0.060 lb/MMBtu) or less
as specified in
60.49Da(b)?
§60.49Da(b)

No 30a

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(38 of 73)

26
Was the facility
constructed (as opposed to
Yes 26a
reconstructed or modified)
after 02/28/2005?

§60.43Da(j)(1)

No

Was the facility


reconstructed (as opposed to modified) Yes 27
after 02/28/2005?

§60.43Da(j)(2)

No 28

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(39 of 73)

26a

These requirements are for


facilities constructed after Comply with the following:
February 28, 2005 that burn Standard
75% or more coal refuse. §60.43Da(j)(1)(ii)
§60.48Da(a)
Monitoring/Testing
§60.48Da(b), (c), (d), (e), (h)
§60.49Da(b), (d), (e), (f)(2)
§60.49Da(h), (h)(1), (h)(3), (h)(4)
§60.49Da(j)(1), (j)(3), (j)(4)
Is the facility
[G]§60.49Da(s), [G](w)
meeting the output based No
§60.50Da(a), [G](c), [G](e)
emission limit?
Recordkeeping
§60.49Da(b), (d), (e)
§60.43Da(j)(1)(i) [G]§60.49Da(s), [G](w)
Yes Reporting
§60.48Da(c)
[G]§60.49Da(s), [G](w)
§60.51Da(a), (b), (b)(1)-(9)
Comply with the following:
[G]§60.51Da(c), [G](e)
Standard
§60.51Da(f), [G](h), (j)-(k)
§60.43Da(j)(1)(i)
§60.48Da(a)
Monitoring/Testing
§60.48Da(b), (c), (d), (h), (m)
§60.49Da(b), (e), (f)(2), (h), (h)(1)
§60.49Da(h)(4), (j)(1), (j)(3), (j)(4)
[G]§60.49Da(k), [G](s), [G](w)
§60.50Da(a), [G](c), [G](e) 18a 31
Recordkeeping
§60.49Da(b), (e)
[G]§60.49Da(k), [G](s), [G](w)
Reporting
§60.48Da(c)
[G]§60.49Da(s), [G](w)
§60.51Da(a), (b), (b)(1)-(2)
§60.51Da(b)(4)-(9), [G](c), [G](e)
§60.51Da(f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(40 of 73)

27 Comply with the following:


Standard
§60.43Da(j)(2)(ii)
§60.48Da(a)
Monitoring/Testing
These requirements are for §60.48Da(b), (c), (d), (h)
facilities reconstructed after §60.49Da(b), (d), (e), (f)(2)
February 28, 2005 that burn §60.49Da(h), (h)(1), (h)(3), (h)(4)
75% or more coal refuse. §60.49Da(j)(1), (j)(3), (j)(4)
[G]§60.49Da(s), [G](w)
§60.50Da(a), [G](c), [G](e)
30b Recordkeeping
§60.49Da(b), (d), (e), [G](s), [G](w)
Reporting
§60.48Da(c)
Is the facility [G]§60.49Da(s), [G](w)
meeting the output based §60.51Da(a), (b), (b)(1)-(2), (b)(4)-(9)
emission limit? [G]§60.51Da(c), [G](e), (f), [G](h), (j)-(k)

Yes
No
§60.43Da(j)(2)(i)
Yes Is the facility
meeting the input based
emission limit?
Comply with the following:
Standard §60.43Da(j)(2)(ii)
§60.43Da(j)(2)(i) No
§60.48Da(a)
Monitoring/Testing Comply with the following:
§60.48Da(b), (c), (d), (h), (m) Standard
§60.49Da(b), (e), (f)(2), (h), (h)(1) §60.43Da(j)(2)(iii)
§60.49Da(h)(4), (j)(1), (j)(3), (j)(4) §60.48Da(a)
[G]§60.49Da(k), [G](s), [G](w) Monitoring/Testing
§60.50Da(a), [G](c), [G](e) 18a §60.48Da(b), (c), (d), (e), (h)
Recordkeeping §60.49Da(b), (d), (e), (f)(2)
§60.49Da(b), (e) §60.49Da(h), (h)(1), (h)(3), (h)(4)
[G]§60.49Da(k), [G](s), [G](w) §60.49Da(j)(1), (j)(3), (j)(4)
Reporting 31 [G]§60.49Da(s), [G](w)
§60.48Da(c) §60.50Da(a), [G](c), [G](e)
[G]§60.49Da(s), [G](w) Recordkeeping
§60.51Da(a), (b), (b)(1)-(2) §60.49Da(b), (d), (e), [G](s), [G](w)
§60.51Da(b)(4)-(9), [G](c), [G](e) Reporting
§60.51Da(f), [G](h), (j)-(k) §60.48Da(c)
[G]§60.49Da(s), [G](w)
§60.51Da(a), (b), (b)(1)-(9)
[G]§60.51Da(c), [G](e)
§60.51Da(f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(41 of 73)

Comply with the following:


28
Standard
§60.43Da(j)(3)(ii)
§60.48Da(a)
These requirements are for Monitoring/Testing
facilities modified after §60.48Da(b), (c), (d), (h)
February 28, 2005 that burn §60.49Da(b), (d), (e), (f)(2)
75% or more coal refuse. §60.49Da(h), (h)(1), (h)(3), (h)(4)
30b §60.49Da(j)(1), (j)(3)-(4), [G](s), [G](w)
§60.50Da(a), [G](c), [G](e)
Recordkeeping
§60.49Da(b), (d), (e), [G](s), [G](w)
Reporting
Is the facility §60.48Da(c)
meeting the output based [G]§60.49Da(s), [G](w)
emission limit? §60.51Da(a), (b), (b)(1)-(2), (b)(4)-(9)
§60.43Da(j)(3)(i) [G]§60.51Da(c), [G](e), (f), [G](h), (j)-(k)

No
Yes
Yes

Is the facility
meeting the input based
Comply with the following:
emission limit?
Standard
§60.43Da(j)(3)(i)
§60.48Da(a) §60.43Da(j)(3)(ii)
No
Monitoring/Testing
§60.48Da(b), (c), (d), (h), (m)
§60.49Da(b), (e), (f)(2), (h), (h)(1) Comply with the following:
§60.49Da(h)(4), (j)(1), (j)(3), (j)(4) Standard
[G]§60.49Da(k), [G](s), [G](w) §60.43Da(j)(3)(iii)
§60.50Da(a), [G](c), [G](e) 18a §60.48Da(a)
Recordkeeping Monitoring/Testing
§60.49Da(b), (e) §60.48Da(b), (c), (d), (e), (h)
[G]§60.49Da(k), [G](s), [G](w) §60.49Da(b), (d), (e), (f)(2)
Reporting §60.49Da(h), (h)(1), (h)(3), (h)(4)
§60.48Da(c) §60.49Da(j)(1), (j)(3)-(4), [G](s), [G](w)
31
[G]§60.49Da(s), [G](w) §60.50Da(a), [G](c), [G](e)
§60.51Da(a), (b), (b)(1)-(2) Recordkeeping
§60.51Da(b)(4)-(9), [G](c), [G](e) §60.49Da(b), (d), (e), [G](s), [G](w)
§60.51Da(f), [G](h), (j)-(k) Reporting
§60.48Da(c)
[G]§60.49Da(s), [G](w)
§60.51Da(a), (b), (b)(1)-(9)
[G]§60.51Da(c), [G](e)
§60.51Da(f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(42 of 73)

Comply with the following:


28a
Standard
§60.43Da(l)(1)(ii)
§60.43Da(g)
SO2 requirements for §60.48Da(a)
facilities constructed or reconstructed Monitoring/Testing
after May 3, 2011. §60.48Da(b), (c), (d), (m)
§60.49Da(j)(1), (j)(3)-(4)
23 [G]§60.49Da(k)
§60.50Da(a), [G](c), [G](e)
Recordkeeping
[G]§60.49Da(k)
Reporting
§60.48Da(c)
Is the facility
§60.51Da(a), (b), (b)(1)-(2)
meeting the output based
§60.51Da(b)(4)-(9), [G](c), [G](e)
emission limit?
§60.51Da(f), [G](h), (j)-(k)
§60.43Da(j)(3)(i)
Yes Yes

No Is the
facility meeting the net
output based emission
limit?

Comply with the following: §60.43Da(j)(3)(ii)


Standard No
§60.43Da(l)(1)(iii)
§60.43Da(g)
§60.48Da(a) Comply with the following:
Monitoring/Testing Standard
§60.48Da(b), (c), (d), (e) §60.43Da(l)(1)(i)
25
§60.49Da(j)(1), (j)(3)-(4) §60.43Da(g)
§60.50Da(a), [G](c), [G](e) §60.48Da(a)
Reporting Monitoring/Testing
§60.48Da(c) §60.48Da(b), (c), (d), (m)
§60.51Da(a), (b), (b)(1)-(9) §60.49Da(j)(1), (j)(3)-(4)
[G]§60.51Da(c), [G](e) 23 [G]§60.49Da(k)
§60.51Da(f), [G](h), (j)-(k) §60.50Da(a), [G](c), [G](e)
Recordkeeping
[G]§60.49Da(k)
Reporting
§60.48Da(c)
§60.51Da(a), (b), (b)(1)-(2)
§60.51Da(b)(4)-(9), [G](c), [G](e)
§60.51Da(f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(43 of 73)

SO2 requirements
28b for facilities modified
after May 3, 2011.
Comply with the following:
Standard
§60.43Da(l)(2)(ii)
§60.43Da(g)
§60.48Da(a)
Monitoring/Testing
Is the facility
§60.48Da(b), (c), (d), (e), (m)
meeting the output based No
§60.49Da(j)(1), (j)(3)-(4)
emission limit?
§60.50Da(a), [G](c), [G](e)
Reporting
§60.43Da(j)(1)(i) §60.48Da(c)
§60.51Da(a), (b), (b)(1)-(9)
[G]§60.51Da(c), [G](e)
Yes §60.51Da(f), [G](h), (j)-(k)

Comply with the following:


Standard
§60.43Da(l)(2)(i)
§60.43Da(g)
§60.48Da(a)
Monitoring/Testing
§60.48Da(b), (c), (d), (m)
§60.49Da(j)(1), (j)(3)-(4)
[G]§60.49Da(k) 23 25
§60.50Da(a), [G](c), [G](e)
Recordkeeping
[G]§60.49Da(k)
Reporting
§60.48Da(c)
§60.51Da(a), (b), (b)(1)-(2)
§60.51Da(b)(4)-(9), [G](c), [G](e)
§60.51Da(f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(44 of 73)

29 Comply with the following:


Monitoring/Testing
§60.48Da(h)
§60.49Da(b), (e), (f)(2)
§60.49Da(h), (h)(1), (h)(4)
[G]§60.49Da(s), [G](w)
Recordkeeping
§60.49Da(b), (e), [G](s), [G](w)
Reporting
[G]§60.49Da(s), [G](w)

Does the owner


or operator use a SO2 Comply with the following:
CEMS installed according to appendix A Yes Monitoring/Testing
of part 75 to monitor [G]§60.49Da(b)(4)
SO2 emissions?

§60.49Da(b)(4)

No

Comply with the following:


Monitoring/Testing 32a
§60.49Da(b)(2), (g), (i), (i)(1)-(2), (i)(5)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(45 of 73)

30 Comply with the following:


Monitoring/Testing
§60.48Da(h)
§60.49Da(b), (e), (f)(2)
§60.49Da(h), (h)(1), (h)(3)-(4)
[G]§60.49Da(s), [G](w)
Recordkeeping
§60.49Da(b), (e), [G](s), [G](w)
Reporting
[G]§60.49Da(s), [G](w)
30b

Does the owner


or operator use a SO2 Comply with the following:
CEMS installed according to appendix A Yes Monitoring/Testing
of part 75 to monitor [G]§60.49Da(b)(4)
SO2 emissions?

§60.49Da(b)(4)

No

Comply with the following:


Monitoring/Testing 33
§60.49Da(b)(2), (g), (i), (i)(1)-(2), (i)(5)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(46 of 73)

30a Comply with the following:


Monitoring/Testing
§60.48Da(h)
§60.49Da(b), (e), (f)(2)
§60.49Da(h), (h)(1), (h)(3)-(4)
[G]§60.49Da(s), [G](w)
Recordkeeping
§60.49Da(b), (e), [G](s), [G](w)
Reporting
[G]§60.49Da(s), [G](w)

Is an as-fired
Comply with the following:
fuel monitoring system
Yes Monitoring/Testing
used at the inlet to the
§60.49Da(b)(3)
control device?

§60.49Da(b)(3)

No

Does the owner


or operator use a SO2 Comply with the following:
CEMS installed according to appendix A Yes Monitoring/Testing
of part 75 to monitor [G]§60.49Da(b)(4)
SO2 emissions?

§60.49Da(b)(4)
No

Comply with the following:


Monitoring/Testing 33
§60.49Da(b)(2), (g), (i), (i)(1)-(2), (i)(5)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(47 of 73)

31

Is an as-fired
Comply with the following:
fuel monitoring system
Yes Monitoring/Testing
used at the inlet to the
§60.49Da(b)(3)
control device?

§60.49Da(b)(3)

No

Does the owner


Comply with the following:
or operator use a SO2
Monitoring/Testing
CEMS installed according to appendix A Yes
[G]§60.49Da(b)(4), (g)
of part 75 to monitor
§60.49Da(i), (i)(1), (m)
SO2 emissions?

No §60.49Da(b)(4)

Comply with the following:


Monitoring/Testing
§60.49Da(b)(1), (g), (i)
33a
§60.49Da(i)(1)-(2), (i)(5), (l)
Recordkeeping
§60.49Da(l)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(48 of 73)

32a

Is the facility a
gas-fired or oil-fired unit
Comply with the following:
AND using an appendix D, part 75
Yes Monitoring/Testing
fuel flow monitoring system as an
§60.49Da(n)
alternative to §60.49Da(l)
or (m)?

§60.49Da(n)
No 33a

Is the facility Comply with the following:


using an appendix A, Monitoring/Testing
part 75 continuous flow monitoring No §60.49Da(l)
system as an alternative Recordkeeping
to §60.49Da(l)? §60.49Da(l)

Yes §60.49Da(m)

Comply with the following:


Monitoring/Testing 33a
§60.49Da(m)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(49 of 73)

33
Does the
affected facility have a
Yes
flue gas desulfurization
system?

§60.49Da(d)
33a

No

Comply with the following:


Is the facility an
Monitoring/Testing
electric utility combined cycle gas
No §60.49Da(d)
turbine that does NOT meet the
Recordkeeping
definition of an IGCC?
§60.49Da(d)

§60.50Da(f)
Yes

Comply with the following:


34 Monitoring/Testing
§60.50Da(f)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(50 of 73)

Is the facility
operated under a
34 commercial demonstration permit Yes End
in accordance with
§60.47Da?
§60.44Da(h)

No

Was the facility


constructed, reconstructed, or modified No 34a
after May 3, 2011?

§60.45Da(a)
Yes

Is the facility
electing to comply
with the alternative standards No
for combined Yes 44f
NOx + CO?

§60.45Da(a)

Does the facility


burn 75% or more coal
Yes
refuse on a 12-month rolling
average basis?

§60.45Da(b)(2)

No 44c

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(51 of 73)

34a NOx
No 35

Was construction, Is the affected


modification, or reconstruction facility simultaneously
Yes
of the facility commenced before combusting different
July 10, 1997? fuels?

§60.44Da(a) §60.44Da(a)(2)

Yes 36
No

No 37

Was construction,
Did reconstruction
reconstruction, or Modification of the
Yes commence after July 9, 1997 but
facility commenced after July 9, 1997
before March 1, 2005?
but before 03/01/2005?

§60.44Da(d)
§60.44Da(d)
Yes 38

No 34b

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(52 of 73)

34b

Was construction,
modification, or reconstruction
of the facility commenced after Yes 41
February 28, 2005 but before
May 4, 2011?

§60.44Da(e)

No

Does the facility


burn 75% or more coal
Yes 44e
refuse on a 12-month rolling
average basis?
§60.44Da(g)(2)

No 44a

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(53 of 73)

35 36

Comply with the following: Comply with the following:


Standard Standard
§60.44Da(a)(1) §60.44Da(a)(2)
§60.48Da(a) §60.48Da(a)
Monitoring/Testing Monitoring/Testing
§60.48Da(b), (c), (d) §60.48Da(b), (c), (d), (h)
§60.49Da(j)(2)-(4) §60.49Da(d), (e), (f)(1), (h), (h)(2)-(4)
§60.50Da(a), [G](d)-(e) §60.49Da(j)(2)-(4), [G](s), [G](w)
Reporting §60.50Da(a), [G](d)-(e)
§60.48Da(c) Recordkeeping
§60.51Da(a), (b), (b)(1)-(2) §60.49Da(d), (e), [G](s), [G](w)
§60.51Da(b)(4)-(9), [G](c) Reporting
§60.51Da(f), [G](h), (j)-(k) §60.48Da(c)
[G]§60.49Da(s), [G](w)
§60.51Da(a), (b), (b)(1)-(2), (b)(4)-(9)
[G]§60.51Da(c), (f), [G](h), (j)-(k)

Is the steam
generating unit a No 39 39a
duct burner?

§60.48Da(j)

Yes

Is the specified Comply with the following:


CEMS used to determine Yes Monitoring/Testing
compliance? §60.48Da(j)(2)

§60.48Da(j)(2)
No

Comply with the following:


Monitoring/Testing
51!
§60.48Da(j)(1)
§60.49Da(o)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(54 of 73)

37 38

Comply with the following: Comply with the following:


Standard Standard
§60.44Da(d)(1) §60.44Da(d)(2)
§60.44Da(d) §60.44Da(d)
§60.48Da(a) §60.48Da(a)
Monitoring/Testing Monitoring/Testing
§60.48Da(b), (c), (d), (i) §60.48Da(b), (c), (d), (h)
§60.49Da(j)(2)-(4), [G](k), [G](s) §60.49Da(d), (e), (f)(1)
§60.50Da(a), [G](d)-(e) §60.49Da(h), (h)(2)-(4)
Recordkeeping §60.49Da(j)(2)-(4),[G](s), [G](w)
[G]§60.49Da(k), [G](s) §60.50Da(a), [G](d)-(e)
Reporting Recordkeeping
§60.48Da(c) §60.49Da(d), (e), [G](s), [G](w)
[G]§60.49Da(s) Reporting
§60.51Da(a), (b), (b)(1)-(2) §60.48Da(c)
§60.51Da(b)(4)-(9), [G](c) [G]§60.49Da(s), [G](w)
§60.51Da(f), [G](h), (j)-(k) §60.51Da(a), (b), (b)(1)-(2)
§60.51Da(b)(4)-(9), [G](c)
§60.51Da(f), [G](h), (j)-(k)

Is the
steam generating unit a duct No 40 48
burner?
§60.48Da(k)

Yes
Comply with the following:
Monitoring/Testing
[G]§60.48Da(k)(2), [G](k)(3)
Is the specified
CEMS and exhaust flow
monitor (or the CEMS and a fuel flow Yes
meter) used to determine
compliance?

§60.48Da(k)(2)
No

Comply with the following:


Monitoring/Testing
50!
[G]§60.48Da(k)(1), [G](k)(3)
§60.49Da(o)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(55 of 73)

Comply with the following:


Monitoring/Testing
§60.48Da(h)
§60.49Da(d)-(e), (f)(1)
§60.49Da(h), (h)(2)-(4)
39 [G]§60.49Da(s), [G](w)
Recordkeeping
§60.49Da(d), (e)
[G]§60.49Da(s), [G](w)
Reporting
[G]§60.49Da(s), [G](w)

Does the owner


or operator use a NOx
39a CEMS installed according to appendix A Yes
of part 75 to monitor
NOx emissions?
§60.49Da(c)(2)

Comply with the following:


No Monitoring/Testing
§60.49Da(c)(2)

Comply with the following:


Monitoring/Testing
§60.49Da(c)(1), (g), (i)
§60.49Da(i)(1)-(3) 51!
§60.49Da(i)(3)(i)-(ii), (i)(4)
Recordkeeping
§60.49Da(c)(1)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(56 of 73)

Comply with the following:


Monitoring/Testing
§60.48Da(h)
§60.49Da(e), (f)(1)
§60.49Da(h), (h)(2), (h)(4)
40
[G]§60.49Da(w)
Recordkeeping
§60.49Da(e), [G](w)
Reporting
[G]§60.49Da(w)

Does the owner


or operator use a NOx
CEMS installed according to appendix A Yes
of part 75 to monitor
NOx emissions?

§60.49Da(c)(2)
Comply with the following:
No Monitoring/Testing
§60.49Da(c)(2)

Comply with the following:


Monitoring/Testing
§60.49Da(c)(1), (g), (i)
§60.49Da(i)(1)-(3) 50!
§60.49Da(i)(3)(i)-(ii), (i)(4)
Recordkeeping
§60.49Da(c)(1)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(57 of 73)

Is the facility
41 an IGCC electric utility steam Yes
generating unit?

§60.44Da(f)

No

42
Does
the facility, during a
30-day rolling average compliance
period, burn liquid fuel such that the liquid fuel
No
contributes 50% or more of the total heat input
for only a portion of the clock
hours in the 30-day
period?
§60.44Da(f)(3)

Yes

47

Does
the facility burn
liquid fuel exclusively or in
combination with solid-derived fuel such that No
the liquid fuel contributes 50% or
more of the total heat
input?

§60.44Da(f)(2)
Yes

46 45

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(58 of 73)

Was the facility


constructed (as opposed to
42 Yes 42a
reconstructed or modified) after
February 28, 2005?

§60.44Da(e)(1)

No

Was the facility


reconstructed (as opposed to
Yes 43
modified) after February 28,
2005?

§60.44Da(e)(2)

No 44

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(59 of 73)

Comply with the following:


42a
Standard
§60.44Da(e)(1)
§60.48Da(a)
Monitoring/Testing
§60.48Da(b), (c), (d), (i)
§60.49Da(j)(2)-(4), [G](k)
§60.50Da(a), [G](d)-(e)
Recordkeeping
[G]§60.49Da(k)
Reporting
§60.48Da(c)
§60.51Da(a), (b), (b)(1)-(2)
§60.51Da(b)(4)-(9), [G](c)
§60.51Da(f), [G](h), (j)-(k)

Is the
steam generating unit a duct No 49
burner?
§60.48Da(k)

Yes

Is the specified
CEMS and exhaust flow Comply with the following:
monitor (or the CEMS and a fuel flow Yes Monitoring/Testing
meter) used to determine [G]§60.48Da(k)(2), [G](k)(3)
compliance?

§60.48Da(k)(2)

Comply with the following:


Monitoring/Testing
No 50!
[G]§60.48Da(k)(1), [G](k)(3)
§60.49Da(o)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(60 of 73)

43

Is the facility
Yes meeting the output based No
emission limit?

§60.44Da(e)(2)(i)
Comply with the following:
Standard
§60.44Da(e)(2)(i)
§60.48Da(a)
Monitoring/Testing
§60.48Da(b), (c), (d), (h), (i) Comply with the following:
§60.49Da(e), (f)(2), (h), (h)(2) Standard
§60.49Da(h)(4), (j)(2)-(4) §60.44Da(e)(2)(ii)
[G]§60.49Da(k), [G](s), [G](w) §60.48Da(a)
49a Monitoring/Testing
§60.50Da(a), [G](d)-(e)
Recordkeeping §60.48Da(b), (c), (d), (h)
§60.49Da(e), [G](k), [G](s), [G](w) §60.49Da(d), (e), (f)(2), (h)
Reporting §60.49Da(h)(2)-(4), (j)(2)-(4)
§60.48Da(c) [G]§60.49Da(s), [G](w)
48!
[G]§60.49Da(s), [G](w) §60.50Da(a), [G](d)-(e)
§60.51Da(a), (b), (b)(1)-(2) Recordkeeping
§60.51Da(b)(4)-(9), [G](c) §60.49Da(d), (e), [G](s), [G](w)
§60.51Da(f), [G](h), (j)-(k) Reporting
§60.48Da(c)
[G]§60.49Da(s), [G](w)
§60.51Da(a), (b), (b)(1)-(2)
§60.51Da(b)(4)-(9), [G](c)
§60.51Da(f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(61 of 73)

44

Is the facility
Yes meeting the output based No
emission limit?
§60.44Da(e)(3)(i)
Comply with the following:
Standard
§60.44Da(e)(3)(i)
§60.48Da(a)
Monitoring/Testing Comply with the following:
§60.48Da(b), (c), (d), (h), (i) Standard
§60.49Da(e), (f)(2), (h), (h)(2) §60.44Da(e)(3)(ii)
§60.49Da(h)(4), (j)(2)-(4) §60.48Da(a)
[G]§60.49Da(k), [G](s), [G](w) Monitoring/Testing
49a
§60.50Da(a), [G](d)-(e) §60.48Da(b), (c), (d), (h)
Recordkeeping §60.49Da(d), (e), (f)(2), (h)
§60.49Da(e), [G](k), [G](s), [G](w) §60.49Da(h)(2)-(4), (j)(2)-(4)
Reporting [G]§60.49Da(s), [G](w)
§60.48Da(c) 48!
§60.50Da(a), [G](d)-(e)
[G]§60.49Da(s), [G](w) Recordkeeping
§60.51Da(a), (b), (b)(1)-(2) §60.49Da(d), (e), [G](s), [G](w)
§60.51Da(b)(4)-(9), [G](c) Reporting
§60.51Da(f), [G](h), (j)-(k) §60.48Da(c)
[G]§60.49Da(s), [G](w)
§60.51Da(a), (b), (b)(1)-(2)
§60.51Da(b)(4)-(9), [G](c)
§60.51Da(f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(62 of 73)

45 46

Comply with the following: Comply with the following:


Standard Standard
§60.44Da(f)(1) §60.44Da(f)(2)
§60.44Da(e) §60.44Da(e)
§60.48Da(a) §60.48Da(a)
Monitoring/Testing Monitoring/Testing
§60.48Da(b), (c), (d), (h), (i) §60.48Da(b), (c), (d), (h), (i)
§60.49Da(e), (f)(2), (h), (h)(2) §60.49Da(e), (f)(2), (h), (h)(2)
§60.49Da(h)(4), (j)(2)-(4) §60.49Da(h)(4), (j)(2)-(4)
[G]§60.49Da(k), [G](s), [G](w) 49a [G]§60.49Da(k), [G](s), [G](w)
§60.50Da(a), [G](d)-(e) §60.50Da(a), [G](d)-(e)
Recordkeeping Recordkeeping
§60.49Da(e), [G](k), [G](s), [G](w) §60.49Da(e), [G](k), [G](s), [G](w)
Reporting Reporting
§60.48Da(c) §60.48Da(c)
[G]§60.49Da(s), [G](w) [G]§60.49Da(s), [G](w)
§60.51Da(a), (b), (b)(1)-(2) §60.51Da(a), (b), (b)(1)-(2)
§60.51Da(b)(4)-(9), [G](c) §60.51Da(b)(4)-(9), [G](c)
§60.51Da(f), [G](h), (j)-(k) §60.51Da(f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(63 of 73)

Comply with the following:


Standard
§60.44Da(f)(3)
§60.44Da(e)
47 §60.48Da(a)
Monitoring/Testing
§60.48Da(b), (c), (d), (h), (i)
§60.49Da(e), (f)(2), (h), (h)(2)
§60.49Da(h)(4), (j)(2)-(4)
[G]§60.49Da(k), [G](s), [G](w) 49a
§60.50Da(a), [G](d)-(e)
Recordkeeping
§60.49Da(e), [G](k), [G](s), [G](w)
Reporting
§60.48Da(c)
[G]§60.49Da(s), [G](w)
§60.51Da(a), (b), (b)(1)-(2)
§60.51Da(b)(4)-(9), [G](c)
§60.51Da(f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(64 of 73)

Did the facility


44a commence modification Yes 44b
after May 3, 2011?

§60.44Da(g)(3)

No

Is the facility
Yes meeting the output based No
emission limit?

§60.44Da(g)(1)

Comply with the following: Comply with the following:


Standard Standard
§60.44Da(g)(1)(i) §60.44Da(g)(1)(ii)
§60.44Da(e) §60.44Da(e)
§60.48Da(a) §60.48Da(a)
Monitoring/Testing Monitoring/Testing
§60.48Da(b), (c), (d), (h), (i) §60.48Da(b), (c), (d), (h), (i)
§60.49Da(e), (f)(2) §60.49Da(e), (f)(2)
§60.49Da(h), (h)(4), (j)(2)-(4) §60.49Da(h), (h)(4), (j)(2)-(4)
[G]§60.49Da(k), [G](s), [G](w) 49a [G]§60.49Da(k), [G](s), [G](w)
§60.50Da(a), [G](d)-(e) §60.50Da(a), [G](d)-(e)
Recordkeeping Recordkeeping
§60.49Da(e), [G](k), [G](s), [G](w) §60.49Da(e), [G](k), [G](s), [G](w)
Reporting Reporting
§60.48Da(c) §60.48Da(c)
[G]§60.49Da(s), [G](w) [G]§60.49Da(s), [G](w)
§60.51Da(a), (b), (b)(1)-(2) §60.51Da(a), (b), (b)(1)-(2)
§60.51Da(b)(4)-(9), [G](c) §60.51Da(b)(4)-(9), [G](c)
§60.51Da(f), [G](h), (j)-(k) §60.51Da(f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(65 of 73)

Comply with the following:


Standard
§60.44Da(g)(3)
§60.44Da(e)
§60.48Da(a)
Monitoring/Testing
§60.48Da(b), (c), (d), (h), (i)
§60.49Da(e), (f)(2), (h), (h)(4), (j)(2)-(4)
[G]§60.49Da(k), [G](s), [G](w)
44b 49a
§60.50Da(a), [G](d), [G](e)
Recordkeeping
§60.49Da(e), [G](k), [G](s), [G](w)
Reporting
§60.48Da(c)
[G]§60.49Da(s), [G](w)
§60.51Da(a), (b), (b)(1)-(2)
§60.51Da(b)(4)-(9), [G](c), [G](e)
§60.51Da(f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(66 of 73)

Did the facility


NOx +
44c commence modification Yes 44d
CO
after May 3, 2011?

§60.44Da(g)(3)

No

Is the facility
Yes meeting the gross output based No
emission limit?
§60.44Da(e)(3)(i)

Comply with the following: Comply with the following:


Standard Standard
§60.45Da(b)(1)(i) §60.45Da(b)(1)(ii)
§60.45Da(b) §60.45Da(b)
§60.48Da(a) §60.48Da(a)
Monitoring/Testing Monitoring/Testing
§60.48Da(b), (c), (g), [G](r) §60.48Da(b), (c), (g), [G](r)
§60.49Da(e), (f)(2), (h) §60.49Da(e), (f)(2), (h)
§60.49Da(h)(2), (h)(4), (j)(2)-(4) §60.49Da(h)(2), (h)(4), (j)(2)-(4)
[G]§60.49Da(k), [G](s) [G]§60.49Da(k), [G](s)
[G]§60.49Da(u), [G](w) 49a [G]§60.49Da(u), [G](w)
§60.50Da(a), [G](e) §60.50Da(a), [G](e)
Recordkeeping Recordkeeping
§60.49Da(e), [G](k) §60.49Da(e), [G](k)
[G]§60.49Da(s), [G](u), [G](w) [G]§60.49Da(s), [G](u), [G](w)
Reporting Reporting
§60.48Da(c) §60.48Da(c)
[G]§60.49Da(s), [G](w) [G]§60.49Da(s), [G](w)
§60.51Da(a), (b), (b)(1)-(2) §60.51Da(a), (b), (b)(1)-(2)
§60.51Da(b)(4)-(9), [G](c), [G](e) §60.51Da(b)(4)-(9), [G](c), [G](e)
§60.51Da(f), [G](h), (j)-(k) §60.51Da(f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(67 of 73)

Comply with the following:


Standard
§60.45Da(b)(3)
§60.45Da(b)
§60.48Da(a)
Monitoring/Testing
§60.48Da(b), (c), (g), [G](r)
§60.49Da(e), (f)(2), (h), (h)(2)
§60.49Da(h)(4), (j)(2)-(4), [G](k)
44d [G]§60.49Da(s), [G](u), [G](w) 49a
§60.50Da(a), [G](e)
Recordkeeping
§60.49Da(e), [G](k),
[G]§60.49Da(s), [G](u), [G](w)
Reporting
§60.48Da(c)
[G]§60.49Da(s), [G](w)
§60.51Da(a), (b), (b)(1)-(2), (b)(4)-(9)
[G]§60.51Da(c), [G](e), (f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(68 of 73)

NOx requirements for facilities


constructed or reconstructed
44e
after May 3, 2011 that burn
75% or more coal refuse.

Did the facility


commence modification after Yes 44b
May 3, 2011?

§60.44Da(g)(3)

No

Is the
facility meeting the gross
Yes No
output based emission
limit?
§60.44Da(g)(2)

Comply with the following: Comply with the following:


Standard Standard
§60.44Da(g)(2)(i) §60.44Da(g)(2)(ii)
§60.44Da(e) §60.44Da(e)
§60.48Da(a) §60.48Da(a)
Monitoring/Testing Monitoring/Testing
§60.48Da(b), (c), (d), (h), (i) §60.48Da(b), (c), (d), (h), (i)
§60.49Da(e), (f)(2), (h), (h)(4), (j)(2)-(4) §60.49Da(e), (f)(2), (h), (h)(4), (j)(2)-(4)
[G]§60.49Da(k), [G](s), [G](w) [G]§60.49Da(k), [G](s), [G](w)
49a
§60.50Da(a), [G](d), [G](e) §60.50Da(a), [G](d), [G](e)
Recordkeeping Recordkeeping
§60.49Da(e), [G](k), [G](s), [G](w) §60.49Da(e), [G](k), [G](s), [G](w)
Reporting Reporting
§60.48Da(c) §60.48Da(c)
[G]§60.49Da(s), [G](w) [G]§60.49Da(s), [G](w)
§60.51Da(a), (b), (b)(1)-(2) §60.51Da(a), (b), (b)(1)-(2)
§60.51Da(b)(4)-(9), [G](c), [G](e) §60.51Da(b)(4)-(9), [G](c), [G](e)
§60.51Da(f), [G](h), (j)-(k) §60.51Da(f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(69 of 73)

NOx plus CO requirements


NOx + for facilities CR after
44f
CO May 3, 2011 that burn 75%
or more coal refuse.

Did the facility


commence modification after Yes 44d
May 3, 2011?

§60.44Da(g)(3)
No

Is the facility
Yes meeting the gross output based No
emission limit?
§60.45Da(b)(2)

Comply with the following: Comply with the following:


Standard Standard
§60.45Da(b)(2)(i) §60.45Da(b)(2)(ii)
§60.45Da(b) §60.45Da(b)
§60.48Da(a) §60.48Da(a)
Monitoring/Testing Monitoring/Testing
§60.48Da(b), (c), (g), [G](r) §60.48Da(b), (c), (g), [G](r)
§60.49Da(e), (f)(2), (h), (h)(2) §60.49Da(e), (f)(2), (h), (h)(2)
§60.49Da(h)(4), (j)(2)-(4), [G](k) §60.49Da(h)(4), (j)(2)-(4), [G](k)
[G]§60.49Da(s), [G](u), [G](w) 49a [G]§60.49Da(s), [G](u), [G](w)
§60.50Da(a), [G](e) §60.50Da(a), [G](e)
Recordkeeping Recordkeeping
§60.49Da(e), [G](k), §60.49Da(e), [G](k)
[G]§60.49Da(s), [G](u), [G](w) [G]§60.49Da(s), [G](u), [G](w)
Reporting Reporting
§60.48Da(c) §60.48Da(c)
[G]§60.49Da(s), [G](w) [G]§60.49Da(s), [G](w)
§60.51Da(a), (b), (b)(1)-(2), (b)(4)-(9) §60.51Da(a), (b), (b)(1)-(2), (b)(4)-(9)
[G]§60.51Da(c), [G](e), (f), [G](h), (j)-(k) [G]§60.51Da(c), [G](e), (f), [G](h), (j)-(k)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(70 of 73)

48!

Does the owner


or operator use a NOx Comply with the following:
CEMS installed according to appendix A Yes Monitoring/Testing
of part 75 to monitor §60.49Da(c)(2)
NOx emissions?

§60.49Da(c)(2)

No

Comply with the following:


Monitoring/Testing
§60.49Da(c)(1), (g), (i)
§60.49Da(i)(1)-(3) 51!
§60.49Da(i)(3)(i)-(ii), (i)(4)
Recordkeeping
§60.49Da(c)(1)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(71 of 73)

49 Comply with the following:


Monitoring/Testing
§60.48Da(h)
§60.49Da(e), (f)(2)
§60.49Da(h), (h)(2), (h)(4)
[G]§60.49Da(s), [G](w)
Recordkeeping
§60.49Da(e), [G](s), [G](w)
Reporting
[G]§60.49Da(s), [G](w)

Does the owner


or operator use a NOx
49a CEMS installed according to appendix A Yes
of part 75 to monitor
NOx emissions?

§60.49Da(c)(2) Comply with the following:


No Monitoring/Testing
§60.49Da(c)(2)

Comply with the following:


Monitoring/Testing
§60.49Da(c)(1), (g), (i)
§60.49Da(i)(1)-(3) 50
§60.49Da(i)(3)(i)-(ii), (i)(4)
Recordkeeping
§60.49Da(c)(1)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(72 of 73)

50!

Is the
facility a gas-fired or oil-
Comply with the following:
fired unit AND using an appendix D,
Yes Monitoring/Testing
part 75 fuel flow monitoring system as
§60.49Da(n)
an alternative to §60.49Da(l)
or (m)?

§60.49Da(n)

No 51!

Is the facility
using an appendix A, Comply with the following:
part 75 continuous flow monitoring Yes Monitoring/Testing
system as an alternative §60.49Da(m)
to §60.49Da(l)?
§60.49Da(m)

No

Comply with the following:


Monitoring/Testing
§60.49Da(l) 51!
Recordkeeping
§60.49Da(l)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***
40 CFR Part 60, Subpart Da
(73 of 73)

51!

Is the facility an
electric utility combined cycle gas
No
turbine that does NOT meet the
definition of an IGCC?

§60.50Da(f)
Yes

Comply with the following:


Monitoring/Testing End
§60.50Da(f)

Last Modified: March 14, 2023 From 40 CFR Part 60, Subpart Da, Amended 04/06/2016
These flowcharts are for use by sources subject to the Federal Operating Permits Program only and are subject to change. ***