Professional Documents
Culture Documents
Recommended
Practices for the
Prevention of
Water Damage to
A N A M E R I C A N N AT I O N A L STA N DA R D
ASME TDP-1–2006
(Revision of ASME TDP-1–1998)
Recommended
Practices for the
Prevention of
Water Damage to
A N A M E R I C A N N AT I O N A L S TA N D A R D
The 2006 edition of this Standard is being issued with an automatic addenda subscription service.
The use of addenda allows revisions made in response to public review comments or committee
actions to be published as necessary. This Standard will be revised when the Society approves the
issuance of a new edition.
ASME issues written replies to inquiries concerning interpretations of technical aspects of this
Standard. The interpretations will be included with the above addenda service.
This code or standard was developed under procedures accredited as meeting the criteria for American National
Standards. The Standards Committee that approved the code or standard was balanced to assure that individuals from
competent and concerned interests have had an opportunity to participate. The proposed code or standard was made
available for public review and comment that provides an opportunity for additional public input from industry, academia,
regulatory agencies, and the public-at-large.
ASME does not “approve,” “rate,” or “endorse” any item, construction, proprietary device, or activity.
ASME does not take any position with respect to the validity of any patent rights asserted in connection with any
items mentioned in this document, and does not undertake to insure anyone utilizing a standard against liability for
infringement of any applicable letters patent, nor assumes any such liability. Users of a code or standard are expressly
advised that determination of the validity of any such patent rights, and the risk of infringement of such rights, is
entirely their own responsibility.
Participation by federal agency representative(s) or person(s) affiliated with industry is not to be interpreted as
government or industry endorsement of this code or standard.
ASME accepts responsibility for only those interpretations of this document issued in accordance with the established
ASME procedures and policies, which precludes the issuance of interpretations by individuals.
Copyright © 2007 by
THE AMERICAN SOCIETY OF MECHANICAL ENGINEERS
All rights reserved
Printed in U.S.A.
CONTENTS
Foreword . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iv
Committee Roster . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . v
1 Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
2 Criteria . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
3 Design Recommendations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
4 Operating Recommendations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
5 Testing, Inspection, Maintenance, and Monitoring. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
6 Conclusion. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
Figures
iii
FOREWORD
In the late 1960s, a substantial increase in the number of reported occurrences of steam turbine
damage by water induction precipitated design recommendations from the two major U.S. steam
turbine manufacturers in an attempt to reduce such incidents. Consequently, utilities and designers
began formulating their own design criteria because of the economic need to keep the generating
units in service. Realizing the common need for a uniform set of design criteria to alleviate this
problem, an American Society of Mechanical Engineers (ASME) Standards Committee was formed,
consisting of representatives of utilities, equipment manufacturers, and design consultants to
develop recommended practices for use in the electric generating industry.
This Standard, resulting from the work and deliberation of the Turbine Water Damage Preven-
tion Committee, was approved as a Standard of the American Society of Mechanical Engineers
by the ASME Standardization Committee and the ASME Policy Board, Codes and Standards, on
July 26, 1972.
In 1979, the Committee proposed a revision to this ASME Standard to include information on
iv
ASME TWDP COMMITTEE
Turbine Water Damage Prevention
(The following is the roster of the Committee at the time of approval of this Standard.)
R. G. Narula, Chair
L. A. Kielasa, Vice Chair
O. Martinez, Secretary
v
Supplied by Book Supply Bureau under license from ASME,
to BHEL Consortium for internal use at BHEL, PEM, Noida.
vi
ASME TDP-1–2006
1
ASME TDP-1–2006
enter the turbine. If an ICS is available, the additional (seal areas at rotor shaft ends). This is done to prevent
redundancy and availability of that system should be air leakage into turbines operating with steam condi-
used as indicated in this Standard. However, if no ICS tions less than atmospheric pressure. The system nor-
is provided, following the non-ICS specific recommen- mally includes piping to route high pressure turbine
dations is intended to still represent a conservative gland leakoff steam to the low pressure turbine glands.
design for protection from water induction. heater drain: a system that removes condensate from
2.2 Definitions feedwater heaters in the feedwater and condensate sys-
tems. The systems are generally designed to cascade the
2.2.1 General drains to the next lowest pressure heater, with the heat-
cold steam: as a general rule, defined as steam inducted ers in the feedwater system ultimately draining to the
into the steam turbine with the steam temperature more deaerator, and the drains from the heaters in the conden-
than 100°F lower than the temperature expected for the sate system draining to the condenser. The drains may
operating condition of the turbine, or loss of measurable be pumped forward from the feedwater heater into the
superheat. Temperature mismatches of more than 100°F condensate line downstream of the heaters. The system
may be permissible on a case-by-case basis, if this has also includes alternate drains to the condenser for start-
already been considered in the design of the turbine. up, shutdown, and emergency conditions.
combined cycle: used in this Standard, a hybrid of the gas motive steam: a steam system that supplies steam to a
turbine (Brayton) and steam (Rankine) cycles. Waste heat steam turbine for the primary purpose of power produc-
contained in the gas turbine exhaust is fed through a tion or to an auxiliary turbine such as a boiler feed pump
2
ASME TDP-1–2006
etc. This turbine is generally supplied with motive steam These heaters are often provided with a separate stor-
from the steam cycle. This turbine may exhaust into the age tank.
steam cycle, to a process, or to a condenser. drain tank (flash tank): a tank into which relatively high
block valve: an on-off valve that is used to start or stop temperature water and steam at a higher pressure enters
the process flow. These valves are also referred to as and separates into steam and water at the lower tank
isolation or shutoff valves. pressure. The steam and water components can then be
taken separately from the tank. This device is often used
boiler feedwater pump: a motor- or steam-turbine-driven
to reduce the temperature/pressure severity of water/
pump that raises the feedwater water pressure to that
steam entering high-energy drains before they are
required at the steam generator inlet.
dumped into the condenser.
bypass valve: a valve used in a bypass line that circum-
drain valve: a block valve used to isolate a steam line
vents a primary valve or device.
drain.
closed feedwater heater: a shell-and-tube heat exchanger
gas turbine (combustion turbine): a mechanical device that
used to heat condensate and feedwater in the steam
operates in the Brayton cycle converting chemical energy
cycle. Water is pumped through the tube side and is
in a liquid or gaseous fuel into electrical power. When
heated by turbine extraction steam introduced on the
operating in combined cycle mode, the waste heat from
shell side of the heater. Condensate on the shell side is
the gas turbine is used in a heat recovery steam generator
removed by the heater drain system.
(HRSG) to generate steam for use in a steam power cycle.
condenser: equipment that condenses low pressure tur-
3
ASME TDP-1–2006
the valve extreme positions and should be operable in (2) one transmitter failed: high select of remaining
the control room. The valve may be automatic or remote good signals (one of three trip signals).
manual, with actuation initiated by the control system (3) two transmitters failed: select remaining trans-
automatically (automatic valve) or by the operator man- mitter and two out of three protective trips.
ually from the control room. (4) three transmitters failed: level controllers revert
steam generator: the equipment that provides heat to turn to manual and hold last good output.
feedwater into motive steam and also reheats the steam (b) Two Transmitter Select With One Level Switch for
in a reheat cycle. In a conventional steam generator, the Two-Out-of-Three Logic (Example)
heat is produced by the burning of fuel (usually coal, (1) zero transmitters failed (normal operation): high
oil, or gas). In an HRSG, the heat comes from the exhaust select of two good signals.
of an external heat source such as a gas turbine, some- (2) one transmitter failed: remaining good transmit-
times supplemented by the burning of additional fuel ter selected (one of three trip signals).
in the gas turbine exhaust. Drum-type steam generators (3) one transmitter failed and high-level switch alarm:
employ a large drum to separate steam from the water remaining good transmitter selected and two out of
as it boils in the tubes. The drum accommodates the three protective trips.
increase in volume resulting from the water’s conversion (4) two transmitters failed: level controllers revert to
to steam, which is then taken from the drum through manual, hold last good controller output, and two out
a section of superheating tubes to obtain the temperature of three protective trips.
needed at the main turbine. In the once-through type
4
ASME TDP-1–2006
5
ASME TDP-1–2006
Alternate (B):
From
outlet and header
water
valve isolation
walls
LAHH
Flash tank/
separator LC LE
LAH
LSH
Alternate (A):
To condenser automatic
drain opening
6
ASME TDP-1–2006
From
Alternate (B): 2 2
water /3 /3
walls outlet and header
valve isolation
Note
(1)
Flash tank/ LT LT LT
separator
I LC
Alternate (A):
To condenser Open
automatic
drain opening valve
Local ICS
NOTE:
(1) Element may be transmitter or high-high level switch.
7
ASME TDP-1–2006
Open valve
water to condenser
walls (3) LSH LSHH (3)
Note
Leveling vessel, (1)
drain tank, LT LT LT
or water
collecting tank
LC
To condenser
Local ICS
NOTE:
(1) Element may be transmitter or high-high level switch.
flow over into the main steam system. When steam flow recognized that under some conditions it cannot be
is increased rapidly, this accumulation of water can be avoided. When this type of attemperator is required in
injected into the turbine. the motive steam line to control the temperature of the
steam entering a steam turbine, the following features
3.2.2 Spray water injection in the cold reheat line
should be provided in addition to the other features
or between primary and final reheat sections is used as
a means to control steam temperature at the reheater recommended in paras. 3.2.5 through 3.2.14:
outlet. These sprays are not effective or normally (a) The attemperators should not be allowed to oper-
required for reducing final reheat steam temperature ate when the steam exiting the attemperator will contain
when used at low loads or during turbine rolling. Most less than 50°F (28°C) of superheat unless a higher tem-
incidents of turbine water damage caused by attempera- perature is required by the turbine manufacturer.
tors have occurred during these periods as a result of (b) The attemperator should be located as far from
overspraying. The water accumulates and flows back to the steam turbine inlet as possible, but in no case closer
the turbine, in most cases because of low steam velocity than 50 pipe diameters.
and the arrangement of the piping. Another potential (c) The attemperator should be located such that any
source of water results when water accumulates from associated water accumulation will drain in the direction
condensation in pendant elements of the reheater during of steam flow to a drain pot located at an elevation
a low load operation. This water can be injected into lower than the connection to the steam turbine. Thus,
the turbine if flow is increased rapidly.
the piping should be sloped toward the drain pot, and
3.2.3 The use of attemperators external to the the drain pot should be located between the attempera-
steam generator, downstream of the last superheating tor and the steam turbine. This will result in the inten-
(or reheating) element, is discouraged; however, it is tional creation of a low point to allow steam separation
8
ASME TDP-1–2006
For details of
controlling functions
refer to para. 3.2
Steam pipe
and water collection in the bottom of the pipe. An over- the spray control and block valves when the master fuel
sized drain pot should be considered to enhance water trip actuates or the gas turbine trips.
collection at high steam velocity.
(d) The design of this type of attemperator system 3.2.7 The control valve should be kept in the closed
should be coordinated with the steam turbine manufac- position until the block valve has reached the full open
turer. position. This will prevent wire drawing of the block
valve seat and subsequent leakage through the block
3.2.4 The use of reheat attemperators should pro- valve.
hibit activation or increase in spray when the steam
conditions downstream of the attemperator are within 3.2.8 The block valve should be automatically
25°F (14°C) of saturation temperature. closed below a predetermined minimum load and any
3.2.5 A power-operated block valve should be time the demand signal to the control valves does not call
installed upstream of the attemperator spray control for spray. Sprays should not be released for automatic
valve. This valve provides tight shutoff to prevent water control at loads where it can be determined that it is
leaking past the spray control valve and provides a relatively ineffective in reducing final steam tempera-
backup in the event that the spray control valve fails to ture. The loads used should be in accordance with the
close when required (see Fig. 4). The spray control and boiler/bypass valve manufacturer’s recommendations.
block valves constitute a double line of defense against Manual control should not prevent operation of the auto-
the inadvertent introduction of spray water into the matic protection features specified in para. 3.2.6.
steam lines. Since spray control valves are susceptible
3.2.9 The attemperator should be designed to
to leakage, additional protection can be obtained by use
achieve suitable atomization at the lowest and highest
of a second block valve.
steam flow rates expected. Operation of the attempera-
3.2.6 The control system should automatically tor outside the range of suitable atomization is
close and override all manual and automatic settings of prohibited.
9
ASME TDP-1–2006
3.2.10 The control system for opening the spray isolating the steam turbine during start-up and other
control valve should be designed to prevent the sudden times when condensate might be present and the valves
injection of large quantities of water. are already closed.
3.2.11 A manually operated drain valve should 3.3.3 A drain should be installed at each low point
be installed between the power-operated block valve in motive steam piping. The review for low points
and the spray control valve. This connection can be used should consider all portions of the lines from the steam
as a telltale for periodically testing for block valve source outlet to the connection on the steam turbine,
leakage. including any branches or dead legs (including those
caused by valve closure). Each drain should consist of
3.2.12 If a bypass valve around spray control
a drain line connection or a drain pot connected directly
valves is used, it should be power operated and actuated
to the bottom of the motive steam line. As a minimum,
to close when the block valve is closed. Use of manual
drain pots should be used for the following lines (other
bypass valves around spray control valves is not recom-
lines do not require drain pots, but this Standard does
mended. If a manual bypass is used, a second power-
not prohibit their use):
operated block valve should be provided as a second
line of defense. If a manual bypass is used, the inherent (a) motive steam lines that are prone to water accu-
possibilities of water induction should be reduced mulation during operation for which large drain collec-
through administrative control. tion areas and/or water detection devices are desired.
(b) cold reheat line at first low point downstream of
3.2.13 A bypass of the block valve should not be the steam turbine exhaust (this application requires
10
ASME TDP-1–2006
Drain pot
LAHH
LE
LAH
LE
HS
I
To drain receiver
drains from the steam generator unless the manifold 3.3.6 Steam bypass systems should be provided
has been analyzed and designed so that the flow of each with the same level of protection as motive steam piping.
drain will not be impeded under any mode of operation. The similarities should include drains, drain pots (if
applicable), and power-operated drain valves with con-
3.3.4 Before-seat drains, or an equivalent connec-
trol room indication. Bypass systems discharging to ves-
tion, should be provided on each turbine stop valve to
sels or process steam systems other than cold reheat (or
permit complete draining of any water that may accu-
any other line connected back to the steam turbine)
mulate at a low point if the valve body is not self-
draining. The before-seat drain on the turbine valve should be designed to prevent backup of water due to
body, if provided, is for drainage of localized accumula- vessel or process steam line high water level. Attempera-
tion of water in the valve body. It should be noted that tors in bypass systems that discharge to the cold reheat
this drain might not be sized to handle drainage or system (or any other line connected back to the steam
warming of the main steam inlet piping leading up to turbine) should be designed consistent with the require-
the stop valve. Separate drains may be required to drain ments of para. 3.2 on attemperators.
or warm up the main steam line. 3.3.7 Nonreturn valves should be provided in the
3.3.5 Drains should be provided between the cold reheat system to prevent the reverse flow of bypass
steam turbine stop valve and first-stage nozzles to steam into the steam turbine during start-up and during
ensure removal of water. These would consist of after- bypass system operation if the piping system design
seat drains on the steam turbine stop valve, before- and provides a source of cold reheat pressurization when
after-seat drains on the control or admission valves, the steam turbine is shut down. The nonreturn valve(s)
and/or low point drains on any of the piping down- may be power assisted according to the requirements
stream of the stop valves. of the main steam turbine manufacturer and actuated
11
ASME TDP-1–2006
by a main steam turbine trip. The number of nonreturn be power assisted according to the requirements of the
valves is to be determined by the main steam turbine main steam turbine and is actuated by a main steam
manufacturer. turbine trip. The number of nonreturn valves is to be
determined by the main steam turbine manufacturer.
3.3.8 Systems with a high potential to cause tur-
The nonreturn valves should be located so that they
bine water induction damage require the same protec-
prevent steam bypass from one main steam turbine
tion as motive steam systems and additionally require
extraction zone to another.
the special design considerations outlined below. One
such system is the cold reheat piping system, which 3.3.10.2 All motive steam pipes connected to
has caused numerous instances of steam turbine water auxiliary drive turbines, including alternate sources,
induction damage that have been attributed to the pres- should be heated whenever the units are operating so
ence of water in the cold reheat line. This water is usually that they are available for immediate service. Power-
introduced into the system from the reheat attemperator operated drain valves, continuous orificed drains, and
spray station, the high pressure bypass attemperators, auxiliary drive turbine above-seat drain valves should
or the feedwater heaters, which extract steam from the be considered typical. The power plant designer should
cold reheat line. Designing a drainage system with suffi- determine location of the warming orifices on the basis
cient capacity to remove all water that can be introduced of the actual piping arrangement. When locating drains
into the cold reheat pipe from these sources is considered and warming lines, the designer should consider the
impractical because of the potentially high rate of flow length of pipe both upstream and downstream of any
into this piping from these sources. For this reason, the valve that could cool down when that particular line is
12
ASME TDP-1–2006
(b) a power-assisted nonreturn valve valves in cascading drain lines (see para. 3.5.1.2 and
(c) a standard power-operated block valve Figs. 6 and 7)
(c) power-operated block valves on all sources of
3.4.2 The designer should consider steam supply
water entering the heater shell and power-operated
and process system upsets that may result in cold steam
block valves on all sources of water entering the heater
admission to the motive/extraction steam line.
tubes (see para. 3.5.1.3 and Figs. 8 and 9)
3.4.3 Water detection and removal features
between a motive steam line and the block valve should 3.5.1.1 The automatic drain system from the
be designed in accordance with this section and the heater should consist of a normal (primary) and an alter-
requirements for motive steam lines. Water detection nate (emergency) drain. An alternate drain should be
and removal features between an extraction steam line installed on each feedwater heater in addition to any
and the block valve should be designed in accordance drains cascading to another feedwater heater. This alter-
with this section and the requirements for extraction nate drain should include a power-operated drain valve.
steam lines. Figures 6 and 8 show the normal primary drain line
with its associated level control and an automatically
3.4.4 If an attemperator is required, it should be operated alternate drain and its level control system.
located downstream of the second power-operated block Figures 7 and 9 depict the same control scheme using
valve. an integrated control system. The following features
3.4.5 If the piping downstream of the second should be incorporated into the automatic heater shell
power-operated block valve is not self-draining to a ves- side drain system:
13
ASME TDP-1–2006
Fig. 6 Typical Heater Steam Side Isolation System: Local Control System
LAHH
ZS
Primary drain
Drain valve if
required
High level (see para. 3.5.6) Drain to
LSH condenser
Normal level
LE LC LC
14
ASME TDP-1–2006
Fig. 7 Typical Heater Steam Side Isolation System: Integrated Control System
Note
(1)
LT LT LT
XMTR
select
LC
LC
Alternate drain
to condenser Primary Primary drain shutoff
drain line signal from high-high
level element on heater
receiving primary
ICS Local drain flow
NOTE:
(1) Element may be transmitter or high-high level switch.
15
ASME TDP-1–2006
Fig. 8 Typical Heater Tube Side Isolation System: Local Control System
LAHH Feedwater/
condensate
LE LC LC Bypass
valve
with a control independent from that described in para. from conditions described in para. 3.5.1.2(a) or (b) is
3.5.1.1. then considered to be contributing to a rising level in
Actuation of these valves indicates that the heater the heater. The required time of operation of the block
drainage system described in para. 3.5.1.1 is not keeping valves is then calculated by using the larger flow rate
up with the draining of the heater. Therefore, cascaded of the above two conditions and the usable pipe and
drains to this feedwater heater should be designed to heater storage volume between the high-high level and
automatically close on this heater’s high-high level. This the block valve. With some heater arrangements such
cascaded drain flow from the previous heater will then as vertical heaters or heaters at or above the turbine, care
be bypassed to the condenser through its alternate drain. should be taken in determining usable storage volume,
The required speed of operation of the power-oper- since water can begin to flow backward once the invert
ated block valves depends on the total amount of excess elevation in the piping is flooded. Additionally, the tube
water flowing to the heater and the volume between bundle occupies a large portion of the shell volume that
the high-high level and the block valve. The total amount
cannot be counted in the storage volume.
of excess water flowing to the heater for purposes of
More information regarding the calculation of tube
this calculation should be the larger of
rupture flow rates can be obtained from the Heat
(a) water flowing from two ruptured tubes (four
Exchange Institute (HEI), Standards for Closed Feedwa-
open ends)
ter Heaters (see para. 2.5).
(b) water equivalent to 10% of the tube side flow
Check valves of either the free swing, power-assisted,
For these two conditions, it is assumed that the normal
heater drain or its alternate to the condenser is capable or positive closing design are not considered a satisfac-
of draining the water that is cascaded to the heater from tory block valve for this application because of possible
previous heaters and from the normal stage extraction seat and disk distortions. These check valves are nor-
flow for this heater (including lower pressure heater mally provided for fast action to limit overspeed due to
out-of-service scenarios). The maximum flow of water entrained energy in the extraction system. They can
16
ASME TDP-1–2006
Fig. 9 Typical Heater Tube Side Isolation System: Integrated Control System
Feedwater/
LAH LAHH
condensate
2/ 2/
3 3 Primary drain
from previous
heater
Note
(1)
LT LT LT
Bypass
valve
LC
LC
Alternate Primary
drain to drain line
Primary drain shutoff condenser
signal from high-high
level element on heater
receiving primary
ICS Local
drain flow
NOTE:
(1) Element may be transmitter or high-high level switch.
afford some protection from a water induction stand- never by automatic preprogrammed control system
point; however, they should be closed automatically by action. The bypass valve should be opened concurrent
the same signal that closes the block valve. They may with closing the isolation valves and should be sized to
be located on either side of the block valve. handle the full flow. The bypass operator speed should
be fast enough to avoid system upsets. The bypass valve
3.5.1.3 It may be impractical to install the block
closure may need to be independently operated to pro-
valves as shown in Figs. 6 and 7 for feedwater heaters
vide start-up flexibility. Drains cascaded into the heater
in the condenser neck. Therefore, an acceptable alterna-
should also be automatically shut off based on the signal
tive to the second line of defense shown in Figs. 6 and
from the high-high level element.
7 is to bypass the feedwater heaters as noted in Figs. 8
and 9. This will remove the heater from service and cut 3.5.1.4 If the feedwater heater bypass control
off the source of water that results from tube leaks. The method is used to protect more than one heater, separate
required speed of operation of these power-operated level elements on each heater should independently
isolation and bypass valves should be determined actuate the isolation system on high-high level in either
according to the method of para. 3.5.1.2 based on the heater. Occasionally, small bypass valves are installed
time required to fill the heater to the top of the shell. around the tube side isolation valves shown in Figs. 8
Isolation valves should not be interlocked with any per- and 9. These are generally used to equalize the pressure
missive that would prevent closure and should be acti- on each side of these large isolation valves to open them
vated on high-high level independent of control from and to warm the tube sheets of high pressure heaters.
that identified in para. 3.5.1.1. These isolation valves Where such bypass valves are provided, they should be
should only be opened with direct operator intervention, power operated and close automatically on the same
17
ASME TDP-1–2006
signal that closes the larger valves, or they should be provided with two-out-of-three logic configuration.
manual valves that are locked closed during normal (e) Separate controllers should control the heater nor-
operation. mal and alternate drain valves. The controllers may use
3.5.2 Baffles placed above the water level in feed- a transmitter select function to interface with the level
water heaters are frequently required to control the rate transmitters.
of steam flow back into the turbine to limit the resulting 3.5.6 A drain should be located at the low point(s)
energy contribution to overspeed. These baffles can also in the extraction pipe between the turbine and the extrac-
be useful in minimizing the amount of water entrained tion steam block valve. The drain piping should be
with the steam flowing back into the turbine following sloped in the direction of flow away from the steam
a turbine trip. turbine. The drain should be routed separately to the
3.5.3 Suitable alarms should be provided for the condenser or other receiver that is at condenser pressure.
benefit of the operator to indicate when the first and A power-operated drain valve should be installed in
second lines of defense have been called into operation. this line and should open automatically upon closure
This should be accomplished through the use of separate of the block valve in the extraction pipe.
high and high-high alarm annunciations in the control Any other low points in the extraction piping between
room. The high alarm should be an indication that the the block valve and the heater should be similarly
heater level has risen to the point where the alternate drained. A power-operated drain valve should be
drain system is required to function. The high-high installed in this line that opens automatically prior to
alarm should be an indication that the heater isolation opening of the block valve.
3.5.4 Level alarms and indications should be 3.5.7 When there is more than one heater from a
designed to reflect the actual level in the heater. The single extraction point, operation of the extraction line
physical arrangement of instrumentation and heater drain valve(s) depends on the design of the connecting
drain piping should preclude unnecessary actuation extraction piping and the possibility for collection of
from level surges during start-up and normal operation. water in the extraction line before the closed block
The physical arrangement should minimize instrumen- valve(s).
tation interconnecting piping lengths to avoid inaccura- 3.5.8 All steam line drain valves in the extraction
cies in level indication. Sensing piping and valves for steam lines between the turbine and the block valve
level controls and elements should be designed so that should be configured to Fail-Open on loss of power, air,
failure or maloperation will not render all lines of water or ICS processor communications as applicable.
induction protection inoperative.
3.5.9 Bypass lines around extraction line block or
3.5.5 Where an integrated control system is used nonreturn valves are not acceptable.
for plant control and monitoring functions, the following
should be considered to provide the minimum reliability 3.5.10 Thermocouples may be installed in the tur-
and redundancy required by this Standard: bine at locations determined by the turbine manufac-
(a) Three transmitters should be connected directly turer or in the connecting steam piping to assist in
to the heater shell with individual isolation for mainte- locating sources of water that may enter the turbine.
nance, as required. The transmitters can be connected 3.5.11 The design of these protective systems
to the heater by a direct connection to the heater shell should include provision for periodic testing. (See sec-
or via a standpipe that cannot be isolated from the shell. tion 5 for testing.)
A level switch may replace one of the transmitters to
generate the third level signal. 3.5.12 For heaters in the condenser neck, margins
for preventing water induction are increased if subcool-
(b) Each transmitter should have its own input/out-
ing zones are avoided and drains are not cascaded into
put (I/O) channel on different I/O cards in the ICS.
these heaters.
(c) High-high alarm and isolation of the heater per
Fig. 7 or 9 should be provided with two-out-of-three 3.5.13 Where a separate drain tank is employed
logic configuration. with a low-pressure heater, adequately sized vents and
(d) High level alarm, indicating opening of the alter- drains are essential. To account for possible flow restric-
nate drain to the condenser per Fig. 7 or 9, should be tion in the interconnecting pipe, a separate level element
18
ASME TDP-1–2006
should be mounted on the heater and should operate 3.6.3 If a drain from the DC heater storage tank
the heater’s isolation system similar to the arrangement or the feed pump suction line is provided as the second
shown in Fig. 7 or 8. means of protection, it should discharge to either the
condenser, a flash tank, or an external storage tank and
3.5.14 Other arrangements of feedwater heaters
should be activated on high-high level in the DC heater
and bypasses are satisfactory, provided they accomplish
storage tank. Figures 10 and 11 show a typical arrange-
the same objective as the arrangement shown in Figs. 8
ment of a drain from the DC heater storage tank and
and 9.
its associated level element. The drain connection at the
3.5.15 Dual extraction/admission lines should fol- storage tank should be located high enough on the tank
low the steam turbine manufacturer’s recommendations shell or configured with a standpipe so that the tank is
between the steam turbine casing and the stop/control not drained dry if the drain valve should fail open. For
valve. The steam lines up to the steam turbine stop/ a drain connection from the feed pump suction line, low
control valve should meet the requirements outlined in DC heater storage tank water level protection should be
the motive steam system description in para. 3.3. provided for the feed pump in addition to the elements
shown in Figs. 10 and 11.
3.6 Direct Contact Feedwater Heaters and Extraction
Systems 3.6.4 If block valves are used as the second means
A direct contact (DC) feedwater heater (deaerator) can of protection, they should be power operated and
be a source of cold steam or water that can flow back to installed in series with the normal control valves in all
the turbine. A power-assisted check valve(s) is normally water lines entering the DC heater. Feed pump recircula-
19
ASME TDP-1–2006
Fig. 10 Typical Deaerator Arrangement With Drain System: Local Control System
Cascading
drains
LAHHH LAHH LAH
Drain
LC LE LE LE
One or two
Extraction Extreme High-high High
nonreturn
steam high-high level level
valves as
level element element element
required
P P
Extraction steam
to feed pump turbine Drain
and other auxiliaries
Drain Drain
20
ASME TDP-1–2006
Fig. 11 Typical Deaerator Arrangement With Drain System: Integrated Control System
Cascading
LAHHH LAHH LAH
drains
Primary
control valve
Primary
ZS
control
valve
Condensate
Drain
LT LT LT
21
ASME TDP-1–2006
Fig. 12 Typical Deaerator Arrangement With Inlet Isolation: Local Control System
Cascading drains
Primary
control valve
LAHHH LAHH LAH
Block
Primary Block valve
valve ZS
control
valve
Condensate
Drain
LC LE LE LE
Drain Drain
(c) Emergency high-high alarm and isolation of the 3.7.1 Drain lines should be designed for both hot
heater per Fig. 11 or 13 should be provided with two- and cold conditions and should slope in the direction
out-of-three logic configuration. of flow to the terminal point with no low points. Any
(d) High-high alarm and isolation of the heater per loops required for flexibility should be in the plane of
Fig. 11 or 13 should be provided with two-out-of-three the slope or in vertical runs.
logic configuration.
3.7.2 Drains should discharge to a receiver with
(e) High-level alarm per Fig. 11 or 13 should be pro-
a pressure always the same as or lower than that of the
vided with two-out-of-three logic configuration.
steam lines. Care should be taken to ensure that, during
3.6.7 The location of drains, valving, and the trips, the vacuum created in some lines does not draw
alarms provided should be as previously mentioned in water back to the steam line because the discharge pres-
paras. 3.5.3 and 3.5.6. sure is greater than the steam line pressure. Sections of
the reheat system piping and piping between the turbine
3.6.8 All steam line drain valves from extraction
stop valve and the turbine casing are typically exposed
steam lines should be arranged for Fail-Open operation.
to a vacuum condition during steam turbine start-up
3.7 Drain Systems: Turbine and Cycle Steam Piping and trip.
General design rules for turbine and cycle steam pip- 3.7.3 Drain lines and drain valve ports should be
ing drain systems are specified in paras. 3.7.1 through sized for the maximum amount of water to be handled
3.7.25. They reflect past successful design practices and under any operating condition. However, to minimize
should be used in conjunction with the specific drain the risk of plugging by foreign materials, they should
recommendations made in the system-specific sections never be less than 3⁄4 in. (19 mm) internal diameter. Drain
of this Standard and by the manufacturer(s) of the vari- lines, including the connections for cold reheat and
ous equipment. motive steam attemperator systems, should have an
22
ASME TDP-1–2006
Fig. 13 Typical Deaerator Arrangement With Inlet Isolation: Integrated Control System
Cascading
drains LAHHH LAHH LAH
Primary
control valve
2/ 2/ 2
/3
3 3
Drain
P P
Extraction steam
to feed pump turbine LC
and other auxiliaries
Local ICS
Drain Drain
inside diameter of not less than 11⁄2 in. (38 mm). Care also be used to assist gravity drainage for systems with
should be taken not to use nominal pipe or valve sizes low-pressure differentials. If used, drain pots should be
without clearly determining that the inside diameter fabricated from 4 in. (100 mm) or larger diameter pipe
will meet this minimum dimension. for most steam lines except for cold reheat drain pots,
which should be 6 in. (150 mm) or larger in diameter.
3.7.4 Consideration should be given to the pres-
Drain pots should be at least 9 in. (230 mm) long but
sure difference that exists during various operating
should not be longer than is required to install level
modes, including start-up and shutdown, so that the
detection equipment. Drain lines and valves should be
drain line will be designed to handle the maximum
sized as discussed earlier in para. 3.7.
expected flows under the minimum pressure differential
conditions. Without sufficient line size, adequate drain- 3.7.7 To help ensure that the drain pot remains dry
age will not be obtained, particularly during the early during normal unit operation, the pot and connecting
stages of start-up when large amounts of water are pro- piping should be fully insulated.
duced in the motive steam lines and yet differential
pressure is very low. When differential pressures are 3.7.8 A power-operated drain valve should be
very low, the drain lines should be designed to allow located in each steam line drain. Position indication at
complete drainage by gravity flow. the full-open and full-closed position should be pro-
vided in the control room to allow the operator to deter-
3.7.5 Drain piping from the connections provided
mine the position of each of the power-operated drain
by the turbine manufacturer should be large enough
valves. Determination of the failure mode for drain
to ensure adequate flow area for the volume increase
valves should be made on the basis of the philosophy
following critical pressure drop through the drain valve.
set forth in para. 2.1.3. If a drain valve is arranged to Fail-
3.7.6 Drain pots are required to be used when Open, attention should be given to receiver overpressure
level control of a drain line is required. Drain pots may protection during plant power failures, since a large
23
ASME TDP-1–2006
amount of steam will pass from each steam line to the (b) If a baffle is used, the free area at the discharge
receiver through the failed open drain valve. of the manifold should not be less than 11⁄2 times the
internal cross-sectional area of the manifold. The baffle
3.7.9 Power-operated drain valves should have should be arranged so that it does not interfere with
control features that allow them to be remotely opened proper functioning of adjacent baffles.
or closed by the operator in the control room at any
(c) Drain lines to the manifolds should be mounted
time, except those from level-controlled drain pots,
at 45 deg to the manifold axial centerline, with the drain
which should be prevented from closing. Motive steam
line discharge pointing toward the condenser or other
line power-operated drain valves should not close until
receiver. The drain lines should be arranged in descend-
the main line superheat is in accordance with turbine
ing order of pressure, with the drain from the highest-
manufacturer’s recommendations.
pressure source farthest from the manifold opening at
3.7.10 Drain valves are often located for ease of the condenser wall. Drain manifolds at the condenser
maintenance; however, it is suggested that the power- should be located in accordance with the condenser
operated drain valve be located in the drain line as manufacturer’s recommendation.
close to the source as is practicable. This will reduce the (d) The drains into the manifolds should be grouped
amount of water trapped upstream of the (closed) drain in approximately the same operating pressure ranges.
valve. Locating the power-operated drain valve close to Ideally, manifolds should contain drains from the same
the source can lead to problems with flashing in the area of the cycle or turbine. Care should be taken in
piping downstream of the valve, and the piping should routing drains together from different sections of a pipe
24
ASME TDP-1–2006
(c) The tank drain line should be sized for the maxi- 3.8.3 Condenser neck high-energy diffusion head-
mum service conditions. When a drain pump is required, ers are used by condenser designers under special
it should be actuated automatically based on drain tank operating conditions. This system may pose a risk for
level. If a drain pump is required and its failure could turbine water induction if incorrectly designed. The tur-
possibly lead to water entering the turbine, redundant bine manufacturer’s design recommendations should be
drain pumps (supplied with power from separate power considered when designing these components.
sources) should be furnished, each controlled by an inde-
3.8.4 Improperly designed steam and water
pendent level controller actuated automatically based
dumps to the condenser can cause turbine casing distor-
on drain tank level. Independent level signals indicating
tions and damage to stationary and rotating turbine
a high-high alarm condition in the tank should be pro-
parts comparable to that caused by water from extrac-
vided in the control room.
tion and from motive steam lines. The damage has con-
(d) Connections for incoming drains on the tank
sisted of low pressure inner casing distortion leading to
should be located above the maximum water level in
severe packing rubs, permanent distortion of horizontal
the tank.
joints that cannot be closed, bucket/blade damage, and
3.7.21 Drain lines in exposed areas should be pro- damage to the condenser itself. Dump flow should be
tected from freezing. directed away from turbine components by properly
designed spargers, baffles, and flow deflectors.
3.7.22 Continuous drain orifices, when used,
should be located and designed so that they can be 3.8.5 Because of a side exhaust steam condenser’s
cleaned frequently and will not be susceptible to plug- relatively compact design and close proximity to the
25
ASME TDP-1–2006
high volume, high energy flows that occur infrequently should be pitched (minimum of 2%) so that they self-
should also be considered, so as to reduce the duty on drain to the header. Any low points in this piping sys-
the condenser and to eliminate the need to handle these tem, including the header, should be drained to the
large flows at the low absolute pressures maintained in gland condenser or main condenser using continuous
the condenser. orifice drains.
3.8.7 The injection points of continuous steam flow 3.9.3 Pipes of the steam seal leakoff system
to the condenser, such as auxiliary turbine exhausts, between the turbine and gland steam condenser should
should be located where the incoming jet will not be pitched (minimum of 2%) so they self-drain to the
impinge at high velocity on turbine components or con- gland steam condenser. Any low points in this piping
denser tubes nor interfere with the high flow regions. system should be drained to the same pipe at a lower
A suggested location is in the region beneath heater elevation or through a loop seal to a drain tank or atmo-
shells or extraction piping, well below the turbine inner sphere.
casing. Care should be taken to orient the vanes of the
3.9.4 If an attemperator station is used, a power-
grid to avoid an upward flow component. The connec-
operated block valve for remote manual operation
tion should normally be located in the condenser dome.
should be used to prevent water flow into the steam
Alternatively, this connection may be located on the
seal header when the steam seal system is out of service.
condenser side wall if the steam lane is sufficiently wide
Piping downstream of an attemperator station should
to provide escape area. In this event, the tubes opposite
be configured to maximize mixing and evaporation of
the connections would be provided with appropriate
the attemperator spray. Refer to the turbine manufactur-
26
ASME TDP-1–2006
TC
Block
valve
PC
Main source
Water
Orifice
supply
drain
Desuperheater Station
Orifice drain
PC
Auxiliary source
PC
Discharge
Dump Station PC
Cold reheat
Orifice drain
or overflow connection should be provided to prevent sharp drops in metal temperature, or shaking steam
the water level in the gland steam condenser/leakoff pipes that result from water flashing to steam. In addi-
system from reaching the turbine. The gland steam con- tion, training should be tailored to each installation to
denser normal drain should be sized to handle the quan- the extent that special or unusual operating characteris-
tity of water formed when the maximum amount of tics may make that unit or type of unit more susceptible
steam entering the gland steam condenser (including to water induction (e.g., units that require extended con-
margin, as determined by the manufacturer, for in- densate/feedwater system pressurization and operation
service increase in flow) from the glands, valve leakoffs, for system cleanup or cooldown hold a greater potential
or other sources is condensed, while maintaining a nor- for water induction). Damage can be minimized if
mal level in the shell. prompt and decisive action is taken at the first warning
of water induction into a turbine. An operator training
review is recommended periodically to keep the specific
4 OPERATING RECOMMENDATIONS instructions fresh in the operator’s mind.
Operating recommendations provided in this section Many of this Standard’s design requirements will pro-
are based on generic requirements because of the many vide indications and initiate automatic actions when
variations in equipment and unit system designs and water (or cold steam) is present in components that
the varying needs of different system grids. Operating could lead to turbine damage. Operators need to give
companies should develop and conduct a training pro- priority to investigating all actions of turbine-water-
gram for each installation to guide operators in handling induction-influenced sensors and controls. Over-
normal start-up, shutdown, steady state, and varying reliance on automatic features has resulted in turbine
load conditions; loss of steam generator fire; and trips water induction incidences. Operators who can readily
and situations involving water induction. These instruc- detect the presence of water can isolate the water from
tions should cover the steps to take should there be any the turbine and dispose of it, thus preventing damage
symptoms of water induction such as high level alarms, to the steam turbines.
27
ASME TDP-1–2006
4.1 Motive Steam whether that steam source is in service. Caution should
Paragraphs 4.1.1 through 4.1.4 describe features that be exercised when bringing an additional steam source
should be incorporated into plant operating philosophy on line to ensure that steam lines are adequately warmed
related to motive steam systems. The features may be and drained and steam temperature meets the turbine
programmed into a plant computer control system or manufacturer’s requirements for superheat. Because it
may be operator procedures or a combination thereof. is recognized that induction of cold steam can also dam-
age the turbine, the steam conditions should be such
4.1.1 Prior to starting the unit, the condenser that the turbine manufacturer’s recommendations for
should be in operation and ready to accept drainage. inlet steam temperature rate of change and/or instanta-
The condenser should remain available to provide cool- neous (step) change are not exceeded when the addi-
ing for drains routed to the condenser prior to opening tional steam source is tied into the steam supply header.
these drains during shutdown. Proper operation of drain (or bypass) systems is needed
to ensure that these recommendations are not exceeded.
4.1.2 It is recommended that drain valves be
opened (and remain open) during steam turbine shut- 4.2 Main Steam Turbine
down and steam turbine trip. Under certain conditions,
it is desirable to keep the motive steam lines pressurized. 4.2.1 If water enters the turbine while operating
Under those conditions, provisions should be made to at rated speed or while carrying load, the unit should
determine if water is present and, if so, to drain the line. not be tripped if the vibration and differential expansion
When a steam turbine is to be restarted shortly after are satisfactory and no other signs of distress are
28
ASME TDP-1–2006
a distorted cylinder or bowed rotor has returned to 4.5.3 If an alarm sounds and power-operated con-
acceptable conditions, the restart should be closely trols isolate the source of water, the operator should
supervised following procedures recommended by the follow up by actuating the remaining isolating and drain
turbine manufacturer. valves.
4.2.7 If the rotor is bowed or the shell distorted so 4.5.4 If any heater is taken out of service, drain
the turning gear cannot turn the rotor, periodic attempts valves in the associated extraction lines should be
(once per hour) should be made to rotate the rotor and opened and the drain line from the drain valve checked
get the unit on turning gear. No attempt should be made to verify that it is not plugged. When returning the
to free a locked rotor by use of a crane or by the admis- heater to service, the operator should check that the
sion of steam to the turbine. heater shell pressure is lower than the corresponding
turbine stage pressure before opening the extraction line
4.2.8 During start-up, all drains between the main block valve.
steam stop valve and turbine casing should remain open
until adequate superheat is achieved, water has com- 4.5.5 Where the boiler start-up cycle pressurizes
pletely drained, or as recommended by the turbine man- feedwater heaters, the block valves between the turbine
ufacturer. and the pressurized feedwater heaters should be inter-
locked closed during the start-up cycle to prevent any
4.3 Turbine Steam Seal System backflow from the heaters into the turbine. This is in
addition to any possible check valve action. Once the
4.3.1 When the turbine is hot and it is necessary
pressure in the associated turbine stage is sufficient to
29
ASME TDP-1–2006
such testing.) All annunciators should be checked for 5.3 Inspection and Maintenance During Planned Unit
alarm indications. Bypassing of interlocking devices Outages
should be avoided, but when this is necessary for testing 5.3.1 All valves essential to water induction pre-
critical water prevention equipment (such as extraction vention (such as attemperator spray valves and power-
nonreturn valves, drain lines, and feedwater heater level operated block valves) should be tested for tight shutoff,
controls), the equipment should be verified to have been or an internal visual inspection made. This test should
restored to the original operating condition. also include all interlocks and controls.
5.1.2 The mechanical and electrical operation of 5.3.2 All level-actuated drain valves should be
all drain valves should be tested. Where applicable, the tested.
valves should be operated from the control room and 5.3.3 Drain pots, traps, and orifices for all drains
determined to open and close properly by observing should be cleaned.
control room indicating lights. At least once a year, this
5.3.4 Where the tests of para. 5.2.1 indicate inoper-
inspection should include verification that control room
ative drain lines, the drain valves should be disassem-
indication of valve position is working as intended by
bled and inspected internally to verify that they will
physical checks of the actual valve movement.
operate properly.
5.1.3 Mechanical operation of all power-assisted 5.4 Monitoring
check valves should be tested, including all solenoid Monitoring techniques that can be used to detect con-
valves, air filters, air supply, air sets, etc. ditions that have subsequently been associated with
30
Supplied by Book Supply Bureau under license from ASME,
to BHEL Consortium for internal use at BHEL, PEM, Noida.
K06606
ASME TDP-1–2006