GRP Water Tank Risk Assessment Final

The document outlines a risk assessment for the installation and testing of a GRP water storage tank, detailing project scope, hazard identification, and risk levels associated with various activities. It includes control measures, personal protective equipment requirements, emergency procedures, and monitoring protocols. Approval sections for preparation, review, and authorization are also provided.

Uploaded by

mohamednigm666
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
544 views2 pages

GRP Water Tank Risk Assessment Final

The document outlines a risk assessment for the installation and testing of a GRP water storage tank, detailing project scope, hazard identification, and risk levels associated with various activities. It includes control measures, personal protective equipment requirements, emergency procedures, and monitoring protocols. Approval sections for preparation, review, and authorization are also provided.

Uploaded by

mohamednigm666
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Risk Assessment: Installation and Testing of GRP Water Storage Tank

1. Project Details

- Project Title: Installation and Testing of GRP Water Storage Tank

- Location: [Insert Project Location]

- Date: [Insert Date]

- Prepared By: [Insert Name]

2. Scope of Work

- Delivery and unloading of GRP tank components.

- Assembly and installation of the GRP tank.

- Connection to plumbing system.

- Hydrostatic testing of the tank.

3. Hazard Identification and Risk Assessment

Activity Hazard Risk Level (L/M/H) Control Measures

Delivery of tank components Manual handling injuries M Use mechanical lifting aids; ensure proper lif

Vehicle movement H Use banksman; restrict access during unload

Assembly of tank Working at height H Use scaffolding/ladders with fall protection; P

Use of power tools M Tools inspection; PPE (gloves, goggles); trai

Installation and plumbing work Slips, trips, and falls M Housekeeping; non-slip footwear.

Confined space hazards (if any)H Conduct gas testing; ventilation; confined sp

Hydrostatic testing Water spillage and slips M Ensure proper drainage; use caution signs.

Structural failure during testing H Gradual filling and pressure monitoring; insp

4. Personal Protective Equipment (PPE)

- Safety helmet

- Safety gloves

- Safety boots

- High-visibility vest

- Eye protection

- Fall arrest harness (if working at height)


Risk Assessment: Installation and Testing of GRP Water Storage Tank

5. Emergency Procedures

- First aid kits on site.

- Fire extinguisher available.

- Nearest hospital/contact details displayed.

- Emergency assembly point designated.

6. Monitoring and Review

- Supervisor to conduct daily toolbox talks.

- Safety officer to perform regular site inspections.

- Risk assessment to be reviewed and updated if work scope changes.

7. Approval

- Prepared by: [Name, Signature, Date]

- Reviewed by: [Name, Signature, Date]

- Approved by: [Name, Signature, Date]