Professional Documents
Culture Documents
200918TS148 Final Report
200918TS148 Final Report
By
S Rengarajan
200918TS148
Annexure B Customer End Line Rejection Reduction in Hyundai i20 RR FLR Assy.
BITS ZC423T: Project Work
By
S Rengarajan
200918TS148
M.S. Balajee, Deputy General Manager Sungwoo Gestamp Hitech (Chennai) Ltd
Irungakkatukottai, Chennai
Certificate
Page - 3 - of 64
Page - 4 - of 64
Page - 5 - of 64
Evaluation Sheet
Page - 6 - of 64
Page - 7 - of 64
Abstract
Page - 8 - of 64
Page - 9 - of 64
Acknowledgement
Page - 10 - of 64
ACKNOWLEDGEMENT
I am deeply indebted to Mr. C.S. Kim, General Manager (Quality) for having given me an opportunity to work on this project.
I would like to express my sincere gratitude to my project supervisor cum mentor Mr. M.S. Balajee, Deputy General Manager, SGH and to my additional examiner Mr G.Giridharan Senior Manager, Head - Production Dept, SGH. I acknowledge their valuable suggestions throughout the course of this project work. It is worth mentioning that without their guidance and help, the completion of the project would have not been possible.
I would like to express my sincere thanks to Prof. S Gurunarayanan Dean WILPD BITS and Dr. G Venkiteswaran Asst Dean for the opportunity given to present the project successfully.
Also I am very much appreciating the extended support rendered by Mr. S Dhanasekar, Asst Manager Production, Mr. K Ramesh, Dy. Manager Quality, N Gobikrishnan, Sr.Engineer Quality, Mr. P. Venkatesan, Sr.Engineer Quality for their enthusiastic cooperation, without which the project would not have been successful. Finally I wish to express my sincere thanks to people contributed directly & indirectly for the successful completion of this project.
S Rengarajan
Page - 11 - of 64
Annexure - II
Page - 12 - of 64
ABBREVIATIONS
MNC ISO TS - Multinational Company - International Standard Organization - Technical Specification
OHSAS - Occupational Health and Safety Assessment System NABL - National Accreditation Board for Laboratories QC MNT PED TQM TPM MTBF HMI HMC SGH - Quality Control Department - Maintenance Department - Production Engineering Department - Total Quality Management - Total Productivity Maintenance Mean Time between Failures - Hyundai Motor India Ltd - Hyundai Motor Company Sungwoo Gestamp Hitech (Chennai) Ltd
RR FLR Rear Floor Assy QTR RH LH Assembly Quarter complete Right hand side Left hand side
Page - 13 - of 64
PQCDMS Production, Quality, Cost, Delivery, Morale & Safety PPM 4M 1E KA mm Nm L/ + Rej. Drg 2D Parts Per Million (Defective parts) - Man. Machine. Method & Material - Environment - Kilo Amphere - Millimetre - Newton Meter - Coordinate L (Y-Axis) - Rejection - Drawing - 2 Dimensional
Page - 14 - of 64
Table of Contents
Page - 15 - of 64
TABLE OF CONTENTS
Chapter Unit
Introduction 1.1 1.2 1.3 1.4 1 1.5 1.6 1.7 1.8 1.9 1.10 2.1 2 2.2 2.3 2.4 Analysis 3.1 3 3.2 3.3 3.4 3.5 Action 4 4.1 4.2 Check 5.1 5 5.2 5.3 5.4 6 Evaluation of results Cost analysis Scope for Horizontal deployment Benefits Development of solutions for root causes Trial implementation Cause & Effect Diagram - Level 1 Gemba Audit Cause & Effect Diagram Level 2 Validation & Root Cause Identification Cause & Effect Diagram Level -3 Company profile Our Major Customers Organization structure Responsibilities of Quality Head Production shops in SGH Process Flow of Operations SGHs understanding of TQM Introduction to the project Plan of Work Theme & Target Current level of rejection Observation Collect & Analyze data Understanding the Phenomena Defect generating & Revealing area
Title
Page No.
20 21 23 24 25 26 27 27 29 32 32 33 34 34 35 35 36 37 37 38 38 41 42 43 43 49 50 51 51 52 53 54 57 58 58 59 61 63
Observation
Resolution of results 7 8 9 10 7.1 7.2 Upadated planning sheet Used QC tools & Techniques
Page - 16 - of 64
Page - 17 - of 64
LIST OF FIGURES
List of Figures
Fig. 1 Fig. 2 Fig. 3 Fig. 4 Fig. 5 Fig. 6 Fig. 7 Fig. 8 Fig. 9 Fig. 10
Details
SGH Chennai Plant Products View Major customers SGH Organisation Structure Press shop Weld shop Process Flow of Operations Understanding the phenomena Robot programme master Weld bolt drawing
Chapter
1 1 1 1 1 1 1 2 6 6
Page No.
21 23 23 24 26 26 27 35 54 55
LIST OF TABLES
List of tables
Table 1 Table 2 Table 3 Table 4 Table 5 Table 6 Table 7 Table 8 Table 9 Table 10 Table 11 Table 12 Table 13 Table 14 Table 15 Table 16 Table 17 Table 18 Table 19 Table 20 Table 21 Table 22 Table 23 X-Matrix Planning Schedule Theme and target i20 RR FLR Assy Customer end line rejection trend i20-RR FLR Assy Rejection Defect Pareto Defect generating & Revealing area Cause & Effect Diagram Level-1 Audit sheet Cause & Effect Diagram Level - 2 Validation of root cause - 1 Validation of root cause -2 Validation of root cause -3 Validation of root cause -4 Validation of root cause -5 Validation of root cause - 6 Cause & Effect Diagram Level-3 Tree diagram for development of solution Trial implementation results - 1 Trial implementation results - 2 Trial implementation results - 3 Good & Bad analysis table Trial implementation results - 4 1 1 2 2 3 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4
Details
Customer end line rejection Stratification of all part-wise
Chapter
1
Page No.
31 31 32 32 34 34 35 37 37 38 38 39 39 40 40 41 41 43 43 44 44 45 45
Page - 18 - of 64
List of tables
Table 24 Table 25 Table 26 Table 27 Table 28 Table 29 Table 30 Table 31 Table 32 Table 33 Table 34 Table 35 Table 36 Table 37 Table 38 Table 39
Details
Stud separation Rejection Trend chart Comparative Pareto Before Vs After Kaizen sheet Sub-Part miss phenomena Kaizen sheet Nut hard entry phenomena QC Story at a glance Target Vs Actual comparison graph Overall customer rejection of i20 - RR FLR Cost incurred analysis Horizontal deployment parts Cost saving details table Standardisation plan Master Spares list Standardization summary HODs feedback Updated Gantt chart Used QC tools & Techniques
Chapter
4 4 4 4 4 5 5 5 5 5 6 6 6 7 7 7
Page No.
46 46 47 47 48 50 50 51 51 52 54 55 56 56 58 58
Page - 19 - of 64
Chapter-1. Introduction
Page - 20 - of 64
1. Background
Sungwoo Gestamp Hitech Limited (SGH) is one of the largest automotive components manufacturing group in worldwide with total sales revenue of more than Rupees 8,000 crores. The group has been able to achieve this pre-eminence in view of its commitment to the cherished values of promoting trust, value and customer service.
2. The company
Sungwoo Gestamp Hitech (Chennai) Limited (SGH), is one the Korean based company located in Irungakkatukottai near Chennai, Tamilnadu.
Page - 21 - of 64
M/s Sungwoo Hitech Korean based company having collaboration with M/s.Gestamp, Spain.
SGH, Irungakkatukottai division produces sheet metal bodies for various automobile applications and supplying to the following automobile OEM customers. Hyundai Motor India Ltd, Ford India Ltd, Ashok Leyland Ltd, Tata Johnson Ltd.
SGH, Chennai plant have 20 heavy duty and light duty application Presses and fully Automized welding facilities to meet the car body and various auto applications.
It is ISO/TS16949 certified company, proving its quality of supply with all of its customers. Every employee is the responsible for the quality of component produced. Quality is assured in the every sphere of Operation.
Even though the stamping and welding Operations are involved with Dust and Noise, SGH has proved its best in the way of controlling parameters affecting the environment and certified for ISO 14001 and ISO 18001.
Page - 22 - of 64
Our Products:
Page - 23 - of 64
Chairman
Managing Director
Vice president
Materials
PPE
Production
QC
Finance
HR & IR
GM - QC
Head - QC
A - Shift Incharge
B - Shift Incharge
C - Shift Incharge
A - Shift Incharge
B - Shift Incharge
C - Shift Incharge
Inspectors
Inspectors
Inspectors
Inspectors
Inspectors
Inspectors
Page - 24 - of 64
Page - 25 - of 64
In Press Shop all the sheet metal panels, like, the floor, doors, roof, fenders, hood and tailgate of a car are produced using equipment like Blanking Line, Tandem press line etc., these panels are stored in pallet and send to the Welding shop for assembling.
The major process of an automotive body is electric resistance welding. Welded sub- Assy parts are sent to customer after de-burring and final inspection.
Page - 26 - of 64
Page - 27 - of 64
Project Introduction
Page - 28 - of 64
The major challenges to achieve the motto of customer satisfaction are quality and cost which in turn are interrelated. At present we are facing major problem with Customer in Hyundai i20 RR FLR Assy sheet metal car body part. Hyundai i20 RR FLR Assy is having a heavy rejection due to Stud
separation in customers vehicle assembly shop. This is directly has the impact on customer capacity / productivity on some occasion leads to vehicle production line stoppages and field failures.
As our customer commits zero defect at assembly to their customers, rejection elimination becomes the ultimate goal for Sungwoo Gestamp Hitech Limited (SGH). SGH manufactures and supplies RR FLR Assy for i20 passenger car to Hyundai Motor India Ltd (HMIL). This model was introduced in 2009. The daily customer requirement is 400 Nos per day. And SGH is the single source supplier for this component. This sub- Assy part is supplied in De-burred and stacked condition free from Aesthetics dent & Damage free and appearance within acceptable level. HMIL carry out Body assembling, painting, Vehicle assembly, Pre-Delivery Inspection.
Page - 29 - of 64
Customer has the Assembly shop with the capacity of 408 Nos only per day with a defect level of 2% rework / rejection. Considering customer constraints on their assembly line quality requirements becomes important for SGH to focus their product to achieve customer requirement in this stipulated time. Therefore I have chosen this project as part of my studies in BITS.
The project background area as follows i20 - RR FLR Assy rejection contributes to 30% of the total rejection leads to customers line capacity loss. Hyundai i20 RR FLR Assy rejection is high in model wise also.
Page - 30 - of 64
Inference:
i20 - RR FLR Assy contributes to 30% of the total rejection at Customer end. Customer end line rejection directly affects the business opportunity of SGH.
Inference:
Departmental target is to reduce i20 - RR FLR Assy from 3000 to 30 PPM
Page - 31 - of 64
Step
Mar'12
1 2 3
Plan Actual Plan 2 Observation Actual Plan 3 Analysis Actual Plan 4 Action Actual Plan 5 Check Actual Plan 6 Standardisation Actual Plan 7 Conclusion Actual Plan 8 Presentation Actual 1 Problem
Table 2: Planning Schedule
Page - 32 - of 64
Chapter-2. Observation
Page - 33 - of 64
Table 5: i20-RR FLR Assy Customer end line rejection Defect Pareto
Page - 34 - of 64
Page - 35 - of 64
Chapter-3. Analysis
Page - 36 - of 64
Inference: Based on the Gemba audit, the probable causes are listed
Page - 37 - of 64
Page - 38 - of 64
Inference: No variation in gap between panel & sustainer Insignificant to the phenomena
Page - 39 - of 64
Page - 40 - of 64
Page - 41 - of 64
Chapter-4. Action
Page - 42 - of 64
Inference: Various possible solutions have been developed for the identified
root causes. Those are to be tried out and validated.
Inference: By converting the stud head type from PIP to conical type
rejection has been reduced from 1100 to 700 PPM. But the rejection level has not reduced and still gap in the target to the actual, which has trigged for innovative thinking.
Page - 44 - of 64
Alternate types of studs were analyzed and the results are shown here.
Page - 48 - of 64
Chapter-5. Check
Page - 49 - of 64
Inference: i20 RR FLR Assy customer end rejection has been reduced. I
am proud to express that the target of reducing the rejection from 3000 PPM to 210 PPM has been achieved.
Page - 50 - of 64
Inference: Total cost spent for this project is Rs 3600 / - One time for the
purchase of materials and die correction. Internal manual work content is not accounted for cost calculation purpose.
Inference: Improvements are deployed horizontal for the possible model & parts.
Page - 51 - of 64
5.4. Benefits:
Chapter - 6 Standardisation
Page - 53 - of 64
6.1. Standardisation:
Page - 54 - of 64
Inference: All the newly introduced parts are included in the Spares list.
Page - 55 - of 64
Page - 57 - of 64
Inference: All the 7 QC tools and 7 techniques are used for this project.
Page - 58 - of 64
Chapter-8. Bibliography
Page - 59 - of 64
BIBLIOGRAPHY
Mahadevan, B. Operations Management: Theory and Practice, 2th Ed., Pearson Education, 2010.
Rusell, R.S. & Taylor, B.W., Operations Management, Wiley Student Edition, 6th Ed., 2009
Arnold, J.R. Tony & others, Introduction to Materials Management, Pearson Education, 6th Edition, 2007.
Callister & R. Balasubramaniam, Materials Science and Engineering, WSE, 7th Edition, 2007.
Rangan C.S., et. al., Instrumentation Devices and Systems, Tata McGraw Hill, 1st Edition, 1989
Rowe, Richard, and Larry Jeffus. The Essential Welder: Gas Metal Arc Welding Classroom Manual. Albany: Delmar, 2000 William L. Galvery and Frank B. Marlow, Welding Essentials: Questions & Answers, Second edition, Industrial Press 2006 (336 pages) Citation
Regis Blondeau, Metallurgy and Mechanics of welding: Processes and industrial applications International Scientific and Technical Encyclopedia 2008
Websites
www.weldingtechnology.org www.efunda.com/processes/metal_processing/welding.cfm
Page - 60 - of 64
Chapter-9. Conclusion
Page - 61 - of 64
9.0 CONCLUSION:
By implementing this project we are extremely satisfied and happy about the outcome of this project work which enabled a rejection reduction at customer end by implementing the actions to overcome the root cause. We also more satisfied with corrective actions has been effectively implemented and adhered and the results are consistent and reliable.
Further improvement was achieved with the reduction of in house rejection. It has also reduces the cost of the rejection and satisfying the customer through Nil customer complaints good Quality parts and timely delivery of pats to them.
This same kind of project can be horizontally deployed in all the parts with desire process modification. The TPM QM 8 Step Methodology of this project is very attractive and we suggest that similar kind of projects would help any management in reducing its overheads.
It only increases the effectiveness of the project through mandatory participation and continuously strives to achieve excellence in each of the following area.
Beyond the theory I have engaged with data collection, training of operators, creating formulae for monitoring the results, data analysis and problem solving by team approach. In this project, the following learnings were made: 1. 2. 3. 4. 5. Systematic approach leads to better understanding and yields a better result. Usage of technology helped in achieving the targets. Team work yields the best result. Able to reach the customer expectations within time limit. It will be helpful in Launching of the new product at the least rejection levels.
Page - 62 - of 64
Chapter-10. Checklist
Page - 63 - of 64
Page - 64 - of 64