Annexure-1
Building Name Floor Nos Percentage%
B. CONSTRUCTION
I.Civil Works
i. Excavation, Foundation and Construction upto
100% 4.297% 17.190%
Plinth level, etc., complete
ii. Structure Work RCC frame of the entire building
from Ground level to terrace, stair roof, overhead
21.705%
tank, Lift machine room, & anti-termite treatment
etc., complete
a. Basement Floor 20%
b. Ground Floor 12%
c. First Floor 12%
17.190%
d. Second Floor 12%
21.705%
e. Third Floor 12%
f. Fourth Floor 12%
g Fifth Floor 12%
h. Mumty, machine room, OHT 8%
1
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
iii. Completion of all AAC block / Brick masonry walls
including cavity wall with insulation and internal walls 6.071%
and drain as per GFC drawings.
a. Basement Floor
20%
b. Ground Floor
12%
c. First Floor
12%
f. Fourth Floor
12%
g Fifth Floor
12%
a. Basement Floor
20%
b. Ground Floor
12%
c. First Floor
12%
17.190%
d. Second Floor
12%
5.616%
e. Third Floor
12%
f. Fourth Floor
12%
g Fifth Floor
12%
h. Mumty, machine room, OHT
8%
2
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
v. On completion of fixing of all types of doors &
windows as mentioned in schedule of opening in GFC
3.794%
drawing and all necessary hardware’s as given
hardware schedule complete for all floors.
a. Basement Floor
20%
b. Ground Floor
12%
c. First Floor
12%
17.190%
d. Second Floor
12%
3.794%
e. Third Floor
12%
f. Fourth Floor
12%
g Fifth Floor
12%
h. Mumty, machine room, OHT
8%
vi. Completion of all internal finishing including
2.466%
primer, paint etc as per GFC drawings
a. Basement Floor 20%
b. Ground Floor 12%
c. First Floor 12%
d. Second Floor 12% 17.190%
2.466%
e. Third Floor 12%
f. Fourth Floor 12%
g Fifth Floor 12%
h. Mumty, machine room, OHT 8%
vii. False Ceiling Work, etc., complete
100% 3.984% 17.190%
3
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
II. Services
a. Lift 1.817%
Supply @ 60%
17.190%
Installation @ 25% 1.817%
Supply @ 60%
17.190%
Installation @ 25% 2.783%
Acoustic 2.543%
Supply @ 60%
17.190%
Installation @ 25% 2.543%
4
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
9.372%
Audio visual & sound system
Supply @ 60%
5.098%
Façade
Supply @ 70% 17.190%
5.098%
Installation @ 30%
100.000% 17.190%
5
Annexure-1
Building Name Floor Nos Percentage%
LECTURE HALL B+G+2 1 21.430%
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
Planning, Design & Engineering Works -
A Investigation, planning, Designing and obtaining 2.50%
approvals for works
a. On approval of Engineer-in-charge, the inception
report & detailed survey and architectural drawings
40%
ready for submission for approval of local bodies and
statutory authorities
b. On approval of structure design by the proof
12%
consultant and Engineer-in-charge
c. On obtaining all required approvals from
statutory authorities and local bodies for
12%
commencement of construction as per requirements 21.430%
and directions of Engineer-incharge.
d. On submission of all Good for Construction 2.50%
drawings as per requirements & directions of Engineer-
in-charge:
i. Architectural drawings
12%
ii. Structural design & Drawings
12%
iii. On Submission of Vetted Drawings
8%
6
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
iii. Completion of all AAC block / Brick masonry
walls including cavity wall with insulation and
6.204%
internal walls and drain as per GFC drawings.
7
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
II. Services
a. Lift 1.318%
Supply @ 60%
21.430%
Installation @ 25% 1.318%
Testing and Commissioning @ 15%
b. Electrical 9.368%
i. Internal electrical works, LT Panels & Cabling,
Rising main &MCBs, DBs, RCBOs& other related 30%
works, etc, complete
ii. Earthing & Lightning Protection System & Cable 21.430%
30% 9.368%
tray, etc., complete
iii. Light Fixtures, Fans, etc., complete 30%
iv.External Service Connection
10%
Supply @ 60%
21.430%
Installation @ 25% 1.246%
Acoustic 2.455%
Supply @ 60%
21.430%
Installation @ 25% 2.455%
Supply @ 60%
21.430%
Installation @ 25% 9.545%
Supply @ 70%
4.926%
Installation @ 30%
Supply @ 60%
21.430%
Installation @ 25% 0.201%
9
Annexure-1
Building Name Floor Nos Percentage%
BOYS HOSTEL S+6 1 8.600%
Break up of total % payable cost for the sub
S. No. Description of Component component
Converted to % for
Percentage %
100% individual
Planning, Design & Engineering Works -
A Investigation, planning, Designing and obtaining 2.50%
approvals for works
a. On approval of Engineer-in-charge, the inception
report & detailed survey and architectural drawings ready
40%
for submission for approval of local bodies and statutory
authorities
b. On approval of structure design by the proof consultant
12%
and Engineer-in-charge
c. On obtaining all required approvals from statutory
authorities and local bodies for commencement of
12%
construction as per requirements and directions of 8.600%
Engineer-incharge.
d. On submission of all Good for Construction drawings 2.50%
as per requirements & directions of Engineer-in-charge:
i. Architectural drawings
12%
ii. Structural design & Drawings
12%
iii. On Submission of Vetted Drawings
8%
11
Break up of total % payable cost for the sub
S. No. Description of Component component
Converted to % for
Percentage %
100% individual
v. On completion of fixing of all types of doors &
windows as mentioned in schedule of opening in GFC
4.301%
drawing and all necessary hardware’s as given
hardware schedule complete for all floors.
a. Ground Floor
20%
b. First Floor
12%
c. Second Floor
12%
f. Fifth Floor
12%
g Sixth Floor
12%
12
Break up of total % payable cost for the sub
S. No. Description of Component component
Converted to % for
Percentage %
100% individual
x. Completion of other miscellaneous works i.e. plinth
protection, brick edging, apron drain etc as per GFC
drawing. 100% 0.430% 8.600%
II. Services
a. Lift
2.135%
Supply @ 60%
7
8.600%
Installation @ 25% 2.135%
Supply @ 60%
8.600%
Installation @ 25% 4.105%
13
Break up of total % payable cost for the sub
S. No. Description of Component component
Converted to % for
Percentage %
100% individual
x. Completion of interior work such as wall panelling
etc and signage work including placing of all
Furniture. 5.800%
8.600%
Supply @ 70%
5.800%
Installation @ 30%
1.450%
Façade
Supply @ 70% 8.600%
1.450%
Installation @ 30%
0.580%
GYM EQUIPMENTS
Supply @ 70% 8.600%
0.580%
Installation @ 30%
Kitchen Equipment with ventilation and supression
4.350%
system
Supply @ 60%
8.600%
Installation @ 25% 4.350%
0.250%
Façade Lighting
Supply @ 60%
8.600%
Installation @ 25% 0.250%
14
Annexure-1
16
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
vi. Completion of all internal finishing including
primer, paint etc as per GFC drawings 2.727%
II. Services
a. Lift 2.345%
Supply @60%
5.650%
Installation @25% 2.345%
b. Electrical 13.403%
i. Internal electrical works, LT Panels & Cabling,
Rising main &MCBs, DBs, RCBOs& other related 30%
works, etc, complete
5.650%
ii. Earthing & Lightning Protection System & Cable
30% 13.403%
tray, etc., complete
iii. Light Fixtures, Fans, etc., complete 30%
iv.External Service Connection 10%
17
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
c. Water Supply & Sewerage System 6.187%
i. Water Supply System, etc complete
30%
ii. Sanitary & Sewerage System, etc., complete
30% 5.650%
6.187%
iii. Fittings & Fixtures, etc., complete
25%
iv.External Service Connection
15%
Supply @ 60%
5.650%
Installation @ 25% 4.018%
5.650%
Supply @ 70%
5.626%
Installation @ 30%
Façade 1.406%
Supply @ 60%
5.650%
Installation @ 25% 0.290%
19
Break up of total % payable cost for the sub
component
S. No. Description of Component
Converted to % for individual
Percentage %
100% Head
iii. Completion of all AAC block / Brick masonry walls
including cavity wall with insulation and internal walls 6.712%
and drain as per GFC drawings.
a. Ground Floor 20%
b. First Floor 12%
c. Second Floor 12% 2.810%
d. Third Floor 12%
6.712%
e. Fourth Floor 12%
f. Fifth Floor 12%
g Sixth Floor 12%
h. Mumty, machine room, OHT 8%
iv. Completion of all types of flooring, skirting, dado and
window sills, jambs including waterproofing for all 6.209%
floors as per GFC drawings and specifications
a. Ground Floor 20%
b. First Floor 12%
c. Second Floor 12% 2.810%
d. Third Floor 12%
6.209%
e. Fourth Floor 12%
f. Fifth Floor 12%
g Sixth Floor 12%
h. Mumty, machine room, OHT 8%
v. On completion of fixing of all types of doors &
windows as mentioned in schedule of opening in GFC
4.195%
drawing and all necessary hardware’s as given
hardware schedule complete for all floors.
a. Ground Floor 20%
b. First Floor 12%
2.810%
c. Second Floor 12%
d. Third Floor 12%
4.195%
e. Fourth Floor 12%
f. Fifth Floor 12%
g Sixth Floor 12%
h. Mumty, machine room, OHT 8%
vi. Completion of all internal finishing including primer,
2.727%
paint etc as per GFC drawings
a. Ground Floor 20%
b. First Floor 12%
c. Second Floor 12%
d. Third Floor 2.810%
12%
2.727%
e. Fourth Floor 12%
f. Fifth Floor 12%
g Sixth Floor 12%
h. Mumty, machine room, OHT 8%
vii. False Ceiling Work, etc., complete
100% 4.405% 2.810%
viii. Finishing Works– External Plastering, Stone
100% 2.937% 2.810%
Cladding & painting works, etc., complete.
20
Break up of total % payable cost for the sub
component
S. No. Description of Component
Converted to % for individual
Percentage %
100% Head
ix. Completion of S.S railing/M.S railing, paneling, GRC
Jali and any other M.S work for all floor as per GFC 100% 1.678% 2.810%
drawing.
x. Completion of other miscellaneous works i.e. plinth
protection, brick edging, apron drain etc as per GFC 100% 0.420% 2.810%
drawing.
II. Services
a. Lift 2.825%
Supply @ 60%
2.810%
Installation @ 25% 2.825%
Testing and Commissioning @ 15%
b. Electrical 10.782%
i. Internal electrical works, LT Panels & Cabling, Rising
main &MCBs, DBs, RCBOs& other related works, etc, 30%
complete
ii. Earthing & Lightning Protection System & Cable tray, 2.810%
30% 10.782%
etc., complete
iii. Light Fixtures, Fans, etc., complete 30%
iv.External Service Connection 10%
c. Water Supply & Sewerage System 8.511%
i. Water Supply System, etc complete 30%
ii. Sanitary & Sewerage System, etc., complete 30% 2.810%
8.511%
iii. Fittings & Fixtures, etc., complete 25%
iv.External Service Connection 15%
d. Fire Protection System
3.747%
Supply @ 60%
2.810%
Installation @ 25% 3.747%
2.810%
Supply @ 70%
5.675%
Installation @ 30%
Façade 1.419%
21
Break up of total % payable cost for the sub
component
S. No. Description of Component
Converted to % for individual
Percentage %
100% Head
Supply @ 60%
2.810%
Installation @ 25% 0.478%
100.000% 2.810%
22
Annexure-1
Building Name Floor Nos Percentage%
STAFF HOUSING - 2BHK S+10 1 9.270%
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
Planning, Design & Engineering Works - Investigation,
A planning, Designing and obtaining approvals for works 2.50%
23
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
ii. Structure Work RCC frame of the entire building
from Ground level to terrace, stair roof, overhead
27.759%
tank, Lift machine room, & anti-termite treatment
etc., complete
a. Ground Floor 6%
b. First Floor 9%
c. Second Floor 9%
d. Third Floor 9%
e. Fourth Floor 9%
9.270%
f. Fifth Floor 9%
g. Sixth Floor 27.759%
9%
h. Seventh Floor 9%
i. Eighth Floor 9%
j, Ninth Floor 9%
f. Tenth Floor 9%
g. Mumty, machine room, OHT
4%
iii. Completion of all AAC block / Brick masonry walls
including cavity wall with insulation and internal 7.765%
walls and drain as per GFC drawings.
a. Ground Floor 6%
b. First Floor 9%
c. Second Floor 9%
d. Third Floor 9%
e. Fourth Floor 9%
9.270%
f. Fifth Floor 9%
7.765%
g. Sixth Floor 9%
h. Seventh Floor 9%
i. Eighth Floor 9%
j, Ninth Floor 9%
f. Tenth Floor 9%
g. Mumty, machine room, OHT 4%
24
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
iv. Completion of all types of flooring, skirting, dado
and window sills, jambs including waterproofing for
all floors as per GFC drawings and specifications 7.182%
a. Ground Floor 6%
b. First Floor 9%
c. Second Floor 9%
d. Third Floor 9%
e. Fourth Floor 9% 9.270%
f. Fifth Floor 9%
7.182%
g. Sixth Floor 9%
h. Seventh Floor 9%
i. Eighth Floor 9%
j, Ninth Floor 9%
f. Tenth Floor 9%
g. Mumty, machine room, OHT 4%
v. On completion of fixing of all types of doors &
windows as mentioned in schedule of opening in GFC
4.853%
drawing and all necessary hardware’s as given
hardware schedule complete for all floors.
a. Ground Floor 6%
b. First Floor 9%
c. Second Floor 9%
d. Third Floor 9%
e. Fourth Floor 9%
9.270%
f. Fifth Floor 9%
4.853%
g. Sixth Floor 9%
h. Seventh Floor 9%
i. Eighth Floor 9%
j, Ninth Floor 9%
f. Tenth Floor 9%
g. Mumty, machine room, OHT 4%
25
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
vi. Completion of all internal finishing including
3.154%
primer, paint etc as per GFC drawings
a. Ground Floor 6%
b. First Floor 9%
c. Second Floor 9%
d. Third Floor 9%
e. Fourth Floor 9%
f. Fifth Floor 9.270%
9%
3.154%
g. Sixth Floor 9%
h. Seventh Floor 9%
i. Eighth Floor 9%
j, Ninth Floor 9%
f. Tenth Floor 9%
g. Mumty, machine room, OHT 4%
vii. False Ceiling Work, etc., complete
100% 5.096% 9.270%
a. Lift
4.093%
Supply @ 60%
9.270%
Installation @ 25% 4.093%
26
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
b. Electrical
11.978%
i. Internal electrical works, LT Panels & Cabling, Rising
main &MCBs, DBs, RCBOs& other related works, etc,
complete 30%
ii. Earthing & Lightning Protection System & Cable tray, 9.270%
etc., complete 30%
11.978%
iii. Light Fixtures, Fans, etc., complete
30%
Supply @ 60%
9.270%
Installation @ 25% 5.281%
Façade 1.597%
Supply @ 70% 9.270%
1.597%
Installation @ 30%
e. Completion and Handling Over with all statuatory
approval after completion of work & as built
100% 1.500% 9.270%
drawings
100.000% 9.270%
27
Annexure-1
Building Name Floor Nos Percentage%
G+3 1 13.420%
CENTRE OF EXCELLENCE & CENTRAL EDP INCUBATION
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
Planning, Design & Engineering Works - Investigation,
A 2.50%
planning, Designing and obtaining approvals for works
a. On approval of Engineer-in-charge, the inception report &
detailed survey and architectural drawings ready for submission 40%
for approval of local bodies and statutory authorities
b. On approval of structure design by the proof consultant and
12%
Engineer-in-charge
c. On obtaining all required approvals from statutory
authorities and local bodies for commencement of
12% 13.420%
construction as per requirements and directions of Engineer-
incharge. 2.50%
d. On submission of all Good for Construction drawings as per
requirements & directions of Engineer-in-charge:
i. Architectural drawings 12%
ii. Structural design & Drawings 12%
iii. On Submission of Vetted Drawings 8%
iii. Design & Drawings for Services 4%
B. CONSTRUCTION
I.Civil Works
i. Excavation, Foundation and Construction upto Plinth
100% 5.459% 13.420%
level, etc., complete
ii. Structure Work RCC frame of the entire building from
Ground level to terrace, stair roof, overhead tank, Lift 25.208%
machine room, & anti-termite treatment etc., complete
28
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
iii. Completion of all AAC block / Brick masonry walls
including cavity wall with insulation and internal walls and 7.051%
drain as per GFC drawings.
a. Ground Floor 30%
13.420%
b. First Floor 20%
c. Second Floor 20%
d. Third Floor 20%
e. Mumty, machine room, OHT 10%
iv. Completion of all types of flooring, skirting, dado and
window sills, jambs including waterproofing for all floors as 6.522%
per GFC drawings and specifications
a. Ground Floor 30%
13.420%
b. First Floor 20%
c. Second Floor 20%
d. Third Floor 20%
e. Mumty, machine room, OHT 10%
v. On completion of fixing of all types of doors & windows as
mentioned in schedule of opening in GFC drawing and all
4.407%
necessary hardware’s as given hardware schedule complete
for all floors.
a. Ground Floor 30% 13.420%
b. First Floor 20%
c. Second Floor 20%
d. Third Floor 20%
e. Mumty, machine room, OHT 10%
vi. Completion of all internal finishing including primer,
2.865%
paint etc as per GFC drawings
a. Ground Floor 30%
b. First Floor 20% 13.420%
c. Second Floor 20%
d. Third Floor 20%
e. Mumty, machine room, OHT 10%
vii. False Ceiling Work, etc., complete 100% 4.627% 13.420%
viii. Finishing Works– External Plastering, Stone Cladding &
100% 3.085% 13.420%
painting works, etc., complete.
ix. Completion of S.S railing/M.S railing, paneling, GRC Jali
and any other M.S work for all floor as per GFC drawing. 100% 1.763% 13.420%
a. Lift 1.337%
Supply @ 60%
13.420%
Installation @ 25% 1.337%
Supply @ 60%
13.420%
Installation @ 25% 2.648%
2.714%
Acoustic
Supply @ 60%
13.420%
Installation @ 25% 0.000%
30
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
2.714%
Audio visual & sound system
Supply @ 60%
13.420%
Installation @ 25% 2.714%
5.429%
Façade
0.320%
Façade Lighting
Supply @ 60%
13.420%
Installation @ 25% 0.320%
31
Annexure-1
Building Name Floor Nos Percentage%
HIGHER DIGNITARY - 6 NOS G+1 1 1.470%
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
Planning, Design & Engineering Works - Investigation,
A 2.50%
planning, Designing and obtaining approvals for works
a. On approval of Engineer-in-charge, the inception report &
detailed survey and architectural drawings ready for submission
40%
for approval of local bodies and statutory authorities
32
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
iv. Completion of all types of flooring, skirting, dado and
window sills, jambs including waterproofing for all floors as 6.209%
per GFC drawings and specifications
1.470%
a. Ground Floor 40%
b. First Floor 40% 6.209%
g. Mumty, machine room, OHT 20%
v. On completion of fixing of all types of doors & windows
as mentioned in schedule of opening in GFC drawing and all
4.195%
necessary hardware’s as given hardware schedule complete
for all floors.
a. Ground Floor 40% 1.470%
33
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
II. Services
b. Electrical 10.218%
i. Internal electrical works, LT Panels & Cabling, Rising main
&MCBs, DBs, RCBOs& other related works, etc, complete
30%
ii. Earthing & Lightning Protection System & Cable tray, etc.,
30% 1.470%
complete 10.218%
iii. Light Fixtures, Fans, etc., complete
30%
1.470%
Supply @ 70%
8.046%
Installation @ 30%
5.364%
Façade
Supply @ 70% 1.470%
5.364%
Installation @ 30%
e. Completion and Handling Over with all statuatory
100% 1.500% 1.470%
approval after completion of work & as built drawings
100.000% 1.470%
34
Annexure-1
100.000% 1.370%
35
Annexure-1
2 FOOTPATH - PAVER BLOCK LAYING, KERB STONE & PARKING 100% 17.053%
100.00% 8.690%
36
Annexure-1
Nos Percentage%
E & M - WORKS TOTAL
1 9.700%
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
E EXTERNALELECTRIFICATION
a) SUBSTATION 3.866%
Supply @ 60%
9.700%
Installation @ 25% 3.866%
Testing and Commissioning @ 15%
b) SUBSTATIONEQUIPMENT 17.415%
Supply @ 60%
9.700%
Installation @ 25% 17.415%
Testing and Commissioning @ 15%
c) DGSET 11.592%
Supply @ 60%
9.700%
Installation @ 25% 11.592%
Testing and Commissioning @ 15%
d) UPS 3.138%
Supply @ 60%
9.700%
Installation @ 25% 3.138%
g) Testing and Commissioning @ 15%
h) EV CHARGING STATION 100% 0.200% 9.700%
1 ADMIN 6.327%
Supply @ 60%
9.700%
Installation @ 25% 6.327%
g) Testing and Commissioning @ 15%
2 LECTURE HALL 7.100%
Supply @ 60%
9.700%
Installation @ 25% 7.100%
g) Testing and Commissioning @ 15%
3 COE & EDP 4.071%
Supply @ 60%
9.700%
Installation @ 25% 4.071%
g) Testing and Commissioning @ 15%
37
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
4 HIGHER DIGNITARY 0.405%
Supply @ 60%
9.700%
Installation @ 25% 0.405%
b) CCTVSYSTEM
I GAS SUPPLY LINE, HSD YARD SUPPLY SYSTEM 100% 2.000% 9.700%
100.00% 9.700%
38
Annexure-1
Nos Percentage%
OPERATION & MAINTAINANCE TOTAL
1 0.400%
Break up of total % payable cost for the sub
component
S. No. Description of Component % for
Converted to
individual Percentage %
100%
Head
100.00% 0.000%
N.B - Items/ specifications to be provided at any location even though left out in the above positions but it is required as per
functional requirements and as per approved drawings shall be provided as per direction of Engineer-In-Charge and the rates for same
shall be deemed to be inclusive in quoted amount of contractor, Nothing extra on this account shall be payble.
39