NORTHERN
Himachal Pradesh 2 2330 4 4930 6 7260
Rajasthan 0 0 8 11000 8 11000
Uttarakhand 1 1000 0 0 1 1000
Uttar Pradesh 0 0 11 17220 11 17220
Northern Region
Himachal Pradesh
Uttarakhand
PFR Prepared
3 Mutkhel 110 Ahmednagar Pravara WRD, Maharashtra
in May-15
• Initially alloted to WRD,
Maharashtra
4 Warasgaon 1200 Pune/Raigad Mose river Kal river Balance
• No progress on S&I acitivities
from more than 6 months
Preliminary Investigation
12 Varandhghat 800 Pune Welvandi River Kharak River Report prepared in Dec WRD, Maharashtra
16
Preliminary Investigation
13 Panshet 1600 Satara Mose River Kal River Report Prepared WRD, Maharashtra
in March-17
PFR Prepared
14 Nive 1200 Pune Kundalika River Kundalika River WRD, Maharashtra
in August-2015
PFR Prepared
15 Kodali 220 Kolhapur Kodali River Kharal River WRD, Maharashtra
in April-2014
18-06-25 2 of 14
17 Atvan 500 Pune/raigad pawana uttara PFR prepared WRD, Maharashtra
1 Kadana 240 Panchmahal Mahi Mahi In Operation Not Working in Pumping Mode
2 Sardar Sarover 1200 Baharuch Narmada Narmada In Operation Not Working in Pumping Mode
•Agency NHDC
Indira Sagar- Omkareshwar •Date of MOA-07.06.2023
1 640 Khandwa ISP Reservoirr Under S&I
Omkareshwar PSP reservior •Target date of DPR preparation -
12/25
11 Aliyar 700 Coimbatore Aliyar River PFR prepared PFR prepared by TANGEDCO
18-06-25 4 of 14
West Bengal
2 Bandhu 900 Purulia Bandhu Nala Bandhu Nala PFR under preparation WBSEDCL
18-06-25 5 of 14
State-wise Potential of OFF River Pumped Storage Projects
River
Probable I.C.
S.N. Region/ Name of the Projects District Loop Status Agency/Remarks
(MW)
Upper Reservoir Lower Reservoir
Northern Region
Himachal Pradesh
at Sadda Dhaulasidh HEP Reservoir Yet to be allotted by the State •Indicated by MoP to SJVNL
1 Dhaulasidh( Sadda) 180 Hamirpur Open
(in a Depression) (for both the alternatives) for development • PFR Prepared
Rajasthan
•Agency-Greenko
1 Sukhpura Off-Stream 2560 Chittorgarh Under S&I •Target date of DPR preparation-12/25
Off -stream Off -stream Closed
•Date of MOA-24.01.2023
•Agency-Greenko
2 Shahpur 1800 Baran Off Stream Off Stream, Closed Under S&I •Target date of DPR preparation-09/25
•Date of MOA-08.12.2021
•Agency-JSW Energy
3 Sirohi 1200 Sirohi Off Stream off stream Closed Under S&I •Target date of DPR preparation-12/25
•Date of MOA-24.01.2022
(acknowledgment letter to LOI )
•Agency-JSW Energy
1 Kandhaura 1680 Sonbhadra Off Stream Off Stream Closed Under Examination
•Agency-Greenko
3 UP01 3660 Sonbhadra Off Stream Off Stream Closed Under S&I •Target date of DPR preparation-07/25
•Date of MOA-01.02.2023
•Agency-Torrent Power
4 Shoma 2400 Sonbhadra Off Stream Off Stream Closed Under S&I •Target date of DPR preparation-12/25
•Date of MOA-20.01.2023
• Agency-Adani Green
8 Panaura 1500 Sonbhadra Off Stream Off Stream Closed Under S&I • Target Date of DPR Preparation-
12/25
• Date of MOA-16.05.2025
• Avaada
• Target Date of DPR preparation-
10 Chichlik 1560 Sonbhadra Off Stream Off Stream Closed Under S&I
12/25
• Date of MoU- 03.04.2024
•Allotment pending
2 Tekwa-2 800 Khargone Off Stream Off Stream Closed Balance
•Initially alloted to NHDC
Latitude - 22.4043o Latitude - 22.4283o Yet to be allotted by the State •Indicated by MoP to NHPC
3 Satpura-2 1000 Chhindwara Closed
Longitude - 78.8169o Longitude - 78.7933o for development •PFR Prepared
•Proposal not yet received in CEA
• Agency- Sri Siddharth Infratech &
4 Panari 1800 Satna Open TOR Granted
Services (I) Privated Limited
•Date of grant of TOR-13.03.2020
connected to a small
•Agency-JSW Energy
stream
2 Pane 1500 Raigad Off Stream open Under S&I •Target date of DPR preparation-08/25
which joins the
•Date of MOA-29.09.2022
downstream Kal river
on Minor nallah
on Minor nallah draining •Agency-Adani Green Energy Ltd.
4 Malshej Ghat Bhorande 1500 Pune & Thane draining into Kukadi Closed Under S&I
Into Kalu rive •Target date of DPR preparation-08/25
river
•Date of MOA-28.06.2022
minor nallah flowing On intial reaches of a Yet to be allotted by the State •Indicated by MoP to THDC
6 Humbarli Birmani 1000 Satara/ Ratnagiri
to koyna river basin nallah flowing to suk river for development •PFR prepared
•Agency-Greenko
Chhatrapati minor nallah draining into •Target Date of DPR preparation-
12 Nayagaon 2000 offstream Closed Under S&I
Sambhajinagar Hivra River 08/25
•Date of MOA-16.01.2023
• Agency- NHPC
upper dam proposed lower dam proposed across • target Date of DPR Preparation-12/25
21 Savitri 2400 Satara-Raigad Open Under S&I
across Koyna River Savitri River • date of MoA-06.06.2023(revised
MoU on 03.09.2024)
•CSPGCL
Yet to be allotted by the State •Techno Commerical Feasibility
1 Dangari 1400 Jashpur Bichri Nala Goer river
for development Report (TCFR) has been prepared for
IC of 1400 MW
•Agency-CSPGCL
2 Rouni 2100 Jashpur Off Stream Dorki Nadi (seasonal nala) Balance
• Allotment Pending
•Agency -CSPGCL
Existing Hasdeo Bango
•Date of MOA-06.10.2023
10 Hasdeo Bango 800 Korba Off Stream Reservoir on Hasdeo Open Under S&I
•Target date of DPR preparation -
River
03/26
•Agency-Greenko
1 Ukai 1600 Tapi Off Stream Off Stream Closed Under S&I
•Target date of DPR preparation-12/25
•Agency-GSECL
4 Serula 960 Tapi Off Stream Off Stream Closed Under S&I •Target date of DPR preparation-12/25
•Date of MOU-17.09.2024
•Agency-GSECL
5 Juni Kayaliwel 300 Tapi Off Stream Off Stream Closed Under S&I •Target date of DPR preparation-12/25
•Date of MOU-17.09.2024
•Agency-GSECL
6 Amalpada 300 Tapi Off Stream off Stream Closed Under S&I •Target date of DPR preparation-12/25
•Date of MOU-17.09.2024
•Agency-GSECL
7 Juni Bavli 450 Tapi Off Stream existing Ukai Reservoir open Under S&I •Target date of DPR preparation-12/25
•Date of MOU-17.09.2024
•Agency-GSECL
8 Satkashi 330 Tapi Off Stream Off Stream Closed Under S&I •Target date of DPR preparation-12/25
•Date of MOU-17.09.2024
•Agency-GSECL
9 Dharoi 500 Banaskantha Off Stream Dharoi Reservoir Open Under S&I •Target date of DPR preparation-12/25
•Date of MOU-17.09.2024
Near Gorakallu
reservoir in In Pannapuram Village
Likely commissioning by 2025-
1 Pinnapuram 1680 Kurnool Pannapuram Village Lat 15o37'26" N Under Active Construction
Closed 26(Sept'25)
Lat 15o36'26" N Long 78o15'30" E
Long 78o15'13" E
•Agency-JSW Energy
10 Vempalli 1500 YSR Kadapa Off Stream Off Stream Under S&I
Closed •Target date of DPR preparation-12/25
•Date of MOA-25.01.2022
on a tabletop hill
•Agency-Adani Green Energy Ltd.
12 Raiwada 900 Anakapalle across a minor rivulet across Sarada river Open Under S&I
•Target date of DPR preparation-08/25
draining into a nallah
•Date of MOA-23.05.2022
•Agency-APGENCO
15 Kamalapadu 950 Ananthapuramu Off Stream Off Stream Under S&I •Target date of DPR preparation-08/25
Closed
•Date of MOA- 23.08.2023
•Agency-APGENCO& ONGC
17 Rayavaram 1500 Annamayya On minor Stream On minor Stream Under S&I
Closed •Target date of DPR preparation-03/26
•Agency-APGENCO
•Target date of DPR preparation-03/26
18 Gadikota 1200 Annamayya Off Stream Off Stream Under S&I
Closed •Date of MOA-31.01.2024 (letter from
NREDCAP)
New Reservoir
Nilgiris & Yet to be allotted by the State
2 Sillahalla Stage-II 1000 Lat 11°16'47.79" N Bhavani Open Indicated by MoP to NTPC
Coimbtore for development
Long 76°47'51.85" E
proposed on minor
Narihalla Reservoir •Agency-JSW Energy
3 Narihalla 300 Bellary rivulet draining into Open Under S&&I
existing on Narihalla River •Target date of DPR preparation-03/26
Narihalla Reservoir
•Date of MOA-28.11.2022
Eastern Region
Odisha
•Agency-OHPC
•Target date of DPR preparation-06/26
2 Upper Kolab 600 Koraput Upper Kolab Off Stream Open Under S&I
•Date of MOA- 18.03.21 (layout
approval by govt. odisha)
•Agency-NHPC
6 Masinta 1000 Deogarh Off Stream Off Stream Closed Under S&I •Target date of DPR preparation-12/25
•Date of MOA- 23.06.2023