0% found this document useful (0 votes)
81 views2 pages

Atms Tms Work Status

Uploaded by

Divyanshu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
81 views2 pages

Atms Tms Work Status

Uploaded by

Divyanshu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

Draft Letter

Date: 20th May, 2024


To,
The Authorised Signatitory,
M/s Yashodhan Highways private Limited
Survey no.139, 140 &.143, Thottam pannai Ettam,
Panrimatai road, Patayakannivadi
Dindigut (Dist)-624705.,
Tamil Nadu –.
Sir,
Sub: lndependent Engineer Services -Four Laning of Kamalapuram to Oddanchatram Section of
NH-209 (New NH-83) from Design Km 0.000 to KM 35.822 (Total Length 36.505Km ) under
Bharatmala Pariyojna. Phase 1 Under the category of Residual Works of NHDP on HAM in
State of Tamil Nadu Status of Procurements & Installation of ATMS & TMS equipment
status– Regarding

Ref :
1. Concession Agreement dated November-2019.
2. IRC: SP: 84 – 2014 Clause 12.12
3. NHAI policy circular no. 11041/218/2007-Admn dated 15.09.2016, Regarding
implementation of Advance Traffic Management System (ATMS)
4. YHPL/NHAI/SA Infra/IE/Package-I/NH209/490/2023 dated 25.08.2023
5. YHPL/NHAI/SA Infra/IE/Package-I/NH209/442/2023 dated 13.05.2023
6. SAICPL/Kam-Odd/NH-209(NH-83)/TN/IE/YHPL/2023/1010 dated 13.11.2023
7. SAICPL/Kam-Odd/NH-209(NH-83)/TN/IE/YHPL/2023/1034 dated 08.12.2023
8. SAICPL/Kam-Odd/NH-209(NH-83)/TN/IE/YHPL/2023/1035 dated 08.12.2023

Dear Sir,

In connection with captioned subject, please find the enclosed herewith the “ Inspection Report and
Status of Procurements and installation of ATMS & TMS Equipment by our HTMS/Toll Expert “
Mr Dharmendra Kumar ( Annexure A & B ) , after conducting site visit project at 18 May 2024

IE observe that Installation of ATMS & TMS equipment work is not started.IE already instructed to
concessioner by different correspondence
SAICPL/Kam-Odd/NH-209(NH-83)/TN/IE/YHPL/2023/1010 dated 13.11.2023 and SAICPL/Kam-
Odd/NH-209(NH-83)/TN/IE/YHPL/2023/1035 dated 08.12.2023
IE again instructed to Concessioner start the ATMS work as per “NHAI Policy Circular No
214/2016 dated 15.09.2016” and IRC Code SP: 84:2014 Sub Clause 12.12 ATMS for ATMS
Clause 816.1 to 816.17 of Specification for Road and Bridge Works of MORTH .ATMS work

Page 1 of 2
directly effect the safety of Highway user .Due to ATMS works not complete due time it effect the
PCOD/COD of project and whole responsibility of the late works is to concessioner.

IE provide the Installation chainage of all ATMS Equipments as per Attachment-Annexure-A & B

Thanking you assuring our best services at all time.

With Regards
For SA lnfrastructure Consuttants pvt Ltd,

Pramod Cherian
(Team Leader cum Senior Highway Engineer),
SA lnfrastructure Consuttants pvt Ltd,
Kamatapuram Oddanchatram -pKG-1,
Oddanchat ram"624619 .

Enc- Annexure A & B


1 DGM (Tech) cum Project Director, plu, NHAI, sennamanaickenpatti (PO),Thadikombu Road,
Dindigut- 624004, Tamit Nadu.
2 IE, SAICPL, Head Office, Noida- 201321

Page 2 of 2