Estimate
Estimate
Name of work:-
Round Rs.
Sl. No. Description Amount (Rs.)
1 Cost for Road Works ₹ 1,987,495.00
Cost for Protective Work
2 Sub-total Cost ₹ 1,987,495.00
3 Add 18% GST on Sl. No. 2 ₹ 357,749.00
4 Cost of civil works excluding labour welfare cess =2+3 ₹ 2,345,244.00
5 Labour welfare cess @1% on Sl. No. 4 ₹ 23,452.00
6 Cost of civil works including labour welfare cess & GST=4+5 ₹ 2,368,696.00
7 Contingency charge @3% on Sl. No. 4 ₹ 70,357.00
8 1%
Total Rs.= ₹ 2,439,053.00
0.00
Sub-Head
of As Estimated As Executed Differences
Estimate
Estimated Estimated Executed Executed Difference Difference
Rate Rate
Sl. No. Quantity Amount Quantity Amount Quantity Amount
1 11731.10 14.40 168927.84 11380.44 163878.34 350.66 14.40 5049.50
2 315.00 27.90 8788.50 292.50 8160.75 22.50 27.90 627.75
3 1789.67 691.20 1237019.90 1731.14 1196563.97 58.53 691.20 40455.94
4.01 732.13 2042.06 1495053.39 694.79 1418802.87 37.34 2042.06 76250.52
4.02 345.00 1808.47 623922.15 297.15 537386.86 47.85 1808.47 86535.29
5 7231.00 530.00 3832430.00 7089.30 3757329.00 141.70 530.00 75101.00
6 10109.45 834.00 8431281.30 9675.23 8069141.82 434.22 834.00 362139.48
7.01 388.26 5677.99 2204536.40 372.15 2113063.98 16.11 5677.99 91472.42
7.02 55.50 5533.00 307081.50 58.58 324123.14 -3.08 5533.00 -17041.64
8 45.00 5927.33 266729.85 37.37 221504.32 7.63 5927.33 45225.53
9.01 2.83 55938.51 158305.98 2.6850 150194.90 0.15 55938.51 8111.08
9.02 2.61 55985.44 146122.00 2.4788 138776.71 0.1312 55985.44 7345.29
10 2400.00 115.00 276000.00 1992.00 229080.00 408.00 115.00 46920.00
11.01 153.00 4087.00 625311.00 148.00 604876.00 5.00 4087.00 20435.00
11.02 20.00 3495.00 69900.00 19.00 66405.00 1.00 3495.00 3495.00
11.03 266.00 3591.00 955206.00 252.00 904932.00 14.00 3591.00 50274.00
11.04 5.00 5049.00 25245.00 4.00 20196.00 1.00 5049.00 5049.00
11.05 20.00 6470.00 129400.00 18.00 116460.00 2.00 6470.00 12940.00
12 11495.00 255.00 2931225.00 11440.00 2917200.00 55.00 255.00 14025.00
13 5822.03 584.00 3400065.52 5074.31 2963397.04 747.72 584.00 436668.48
14 2376.00 2286.00 5431536.00 2168.00 4956048.00 208.00 2286.00 475488.00
15 1533.00 386.00 591738.00 526.00 203036.00 1007.00 386.00 388702.00
16 3400.00 783.00 2662200.00 3331.00 2608173.00 69.00 783.00 54027.00
17 2899.75 99.00 287075.25 3110.54 307943.46 -210.79 99.00 -20868.21
18.01 6.00 399.00 2394.00 5.34 2130.66 0.66 399.00 263.34
18.02 12.79 1011.00 12930.69 6.92 6996.12 5.87 1011.00 5934.57
19 26.90 280.00 7532.00 15.48 4334.40 11.42 280.00 3197.60
20 62.21 114.00 7091.94 62.21 7091.94 0.00 114.00 0.00
21.01 4.38 5404.99 23673.86 4.38 23673.86 0.00 5404.99 0.00
21.02 32.35 5403.99 174819.08 32.03 173089.80 0.32 5403.99 1729.28
22 26.87 6327.99 170033.09 25.57 161806.70 1.30 6327.99 8226.39
23 2.15 55805.51 119981.85 2.15 119981.85 0.00 55805.51 0.00
24 3.74 56856.51 212643.35 2.936 166930.71 0.80 56856.51 45712.63
25 10.53 161.00 1695.33 9.78 1574.58 0.75 161.00 120.75
26 231.00 266.00 61446.00 231.00 61446.00 0.00 266.00 0.00
27 40.66 4801.91 195245.66 40.66 195245.66 0.00 4801.91 0.00
28 674.46 150.00 101169.00 585.66 87849.00 88.80 150.00 13320.00
29 305.89 1991.00 609026.99 305.88 609007.08 0.01 1991.00 19.91
30 526.50 45.10 23745.15 526.50 23745.15 0.00 45.10 0.00
31 526.50 67.00 35275.50 526.50 35275.50 0.00 67.00 0.00
32 213.27 1810.00 386018.70 193.25 349782.50 20.02 1810.00 36236.20
33 270.75 21.00 5685.75 270.75 5685.75 0.00 21.00 0.00
34.01 28.00 251.00 7028.00 28.00 7028.00 0.00 251.00 0.00
34.02 8.00 160.00 1280.00 8.00 1280.00 0.00 160.00 0.00
34.03 8.00 111.00 888.00 8.00 888.00 0.00 111.00 0.00
35 67.50 1753.36 118351.80 67.10 117650.46 0.40 1753.36 701.34
ST-1 2130.50 1276.00 2718518.00 2044.02 2608169.52 86.48 1276.00 110348.48
ST-2 1984.88 232.36 461206.72 1969.98 457744.55 14.90 232.36 3462.16
Estimate for Dismantling of Old and Dilapidated Bagrai Bridge over river Kunur at
16 th. K.M. of Guskara-Ausgram-ChhoraPhari Jungle Road. under Sadarghat Highway
Sub Division II under Asansol Highway Division, Public Works (Roads) Directorate in
the district of Paschim Bardhaman during the year 2022-2023.
SL Item No
No & Page Description of Item Unit Nos Quantity Total Qty Rate Amount
1 Item Dismantling of existing structures like
2.05 (II) culverts, bridges, retaining walls and other
Page structure comprising of masonry, cement
concrete, steel work, including T&P and
233
scaffolding wherever necessary, sorting the
P.W.R dismantled material, disposal of unserviceable
schedul material and stacking the serviceable material
e with all lifts and lead of 1000 m as per
Technical Specifications Clause 202 for Rural
Roads of MORD. (II) By Mechanical Means
b) Reinforced Cement Concrete.
A. COST OF CIVIL WORK EXCLUDING GST & LABOUR WELFARE CESS = ### Rs.=
B. ADD GST @ 18% Rs.= ###
C. COST OF CIVIL WORK EXCLUDING LABOUR WELFARE CESS = Rs.= ###
D. TOTAL LABOUR WELFARE CESS @ 1.00% = Rs.= 23452.45
E. COST OF CIVIL WORK INCLUDING GST & LABOUR WELFARE CESS = Rs.= ###
F. CONTINGENCY CHARGE @ 3% = Rs.= 70357.34
GRAND TOTAL = Rs.= ###
SAY, Rs ###
SL. NO. 4 Vide Page- 238 It. No.- 3.06, and Page No. 239, 3.15, (d)
Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with disposal upto
1000 metres.Excavation for roadwork in soil with hydraulic excavator of 0.9 cum
bucket capacity including cutting and loading in tippers,trimming bottom and side
slopes, in accordance with requirements of lines, grades and cross sections, and
transporting to the embankment location within all lifts and lead upto 1000m as
per Clause 301 of Specifications for Road & Bridge Works of MoRT&H (5th
Revision). (Mode of measurement: pre works and post works)
SL. NO. 3
Rate of R.C.Concrete including Steel per Cum.
Considering 1% Steel with concrete.
Quantity of Steel Per Cum =
1 Cum. 0.01 % 7850.00 Kg
78.50 Kg/Cum
Cost of Steel of 78.50 kg. = 78.50 Kg. x Rs. 56.602 4443.26
Hence Cost of Reinforced Cement concrete ( Including cost of Steel ) Per Cum.
6665.36 /m
3
Cost Of M 25 Grade Cement Concrete = Rs.
4443.26 /m
3
Cost of Steel per Cum = Rs.
11108.62 /m
3
SL. NO. 4 Page No. - 333, Item - 18.07 of P.W. (R) Sch.
Providing and laying Design Mix concrete for plain / reinforced
concrete work in any part of bridge (excluding bottom plugging)
with coarse aggregates of appropriate nominal size and grading,
fine aggregate (sand) conforming to proper grading zone, both of
approved quality and cement, as necessary, including labour,
cost and carriage of all materials and including preparation of
design mix, approval of the same by the Engineer-in-Charge and
cost for quality control, sampling, testing etc. all complete but
excluding cost of labour and materials for formwork &
reinforcement works (a) M15 grade: Using concrete mixer
Full Size Bricks 85.65 Cum 12848.00 Rs. 7381.00 per 8796.68 Rs. 3219.87 per 1000 41368.89
(Page No.- 10, Item no. 1C of S.o.R. Building 1000 Nos. Nos.
2017)
(Serviceable Brick Should be available 150 Nos. of
per cum. )
Brick Bats 85.65 Cum 21.41 Rs. 952.00 per Cum. 1134.59 Rs. 415.30 per Cum. 8891.57
(Serviceable Brick bats (25%. Of volume of Brick
Volume)
Reinforcement ( 1.25% x 1634.76 M3 X 7.850) 160.41 M.T. 80.205 Rs. 56602.56 Per 67458.93 Rs. 24692.15 per M.T. 1980433.89
(Assumunig 1.25% of Steel was used) M.T.
4. Basis for calculation of Depreciation Value for : Consider Structural life approximate 100 years for
Reserved Bid Price (PWD Code-Part-II, Vide P- item wise calculation as per code.
78, Rule-297)
Process-I
(As per PWD Code volume - I Rule 297(4), page -78; Minimum reserve
value should be 6% of booked value)