Professional Documents
Culture Documents
For these reasons, engineers are tasked more and more to place their project ideas within the larger
framework of the environment within a specific planet, country, or region. Engineers must ask themselves
if a particular project will offer some net benefit to the people who will be affected by the project, after
considering its inherent benefits, plus any negative side-effects (externalities), plus the cost of consuming
natural resources, both in the price that must be paid for them and the realization that once they are used
for that project, they will no longer be available for any other project(s).
Simply put, engineers must decide if the benefits of a project exceed its costs, and must make this
comparison in a unified framework. The framework within which to make this comparison is the field of
engineering economics, which strives to answer exactly these questions, and perhaps more. The
Accreditation Board for Engineering and Technology (ABET) states that engineering "is the profession in
which a knowledge of the mathematical and natural sciences gained by study, experience, and practice is
applied with judgment to develop ways to utilize, economically, the materials and forces of nature for the
benefit of mankind".1
It should be clear from this discussion that consideration of economic factors is as important as regard for
the physical laws and science that determine what can be accomplished with engineering. The following
figure shows how engineering is composed of physical and economic components:
1. Physical Environment : Engineers produce products and services depending on physical laws
(e.g. Ohm's law; Newton's law).
1
Haery Sihombing/ IP
Satisfaction of the physical and economic environments is linked through production and
construction processes. Engineers need to manipulate systems to achieve a balance in attributes
in both the physical and economic environments, and within the bounds of limited resources.
Following are some examples where engineering economy plays a crucial role:
With items 1 and 2 in particular, note that coursework in engineering should provide sufficient
means to determine a good design for a furnace, or a suitable robot for an assembly line, but it is
the economic evaluation that allows the further definition of a best design or the most suitable
robot.
In item 1 of the list above, what is meant by " high-efficiency"? There are two kinds of efficiency
that engineers must be concerned with. The first is physical efficiency, which takes the form:
System output(s)
Economic (efficiency ) = -----------------
System input(s)
For the furnace, the system outputs might be measured in units of heat energy, and the inputs in units of
electrical energy, and if these units are consistent, then physical efficiency is measured as a ratio
between zero and one. Certain laws of physics (e.g., conservation of energy) dictate that the output from
a system can never exceed the input to a system, if these are measured in consistent units. All a
particular system can do is change from one form of energy (e.g. electrical) to another (e.g., heat). There
are losses incurred along the way, due to electrical resistance, friction, etc., which always yield
efficiencies less than one. In an automobile, for example, 10-15% of the energy supplied by the fuel might
be consumed simply overcoming the internal friction of the engine. A perfectly efficient system would be
the theoretically impossible Perpetual Motion Machine!
The other form of efficiency of interest to engineers is economic efficiency, which takes the form:
system worth
Economic (efficiency ) = -----------------
system cost
You might have heard economic efficiency referred to as "benefit-cost ratio". Both terms of this ratio are
assumed to be of monetary units, such as dollars. In contrast to physical efficiency, economic efficiency
can exceed unity, and in fact should, if a project is to be deemed economically feasible. The most difficult
part of determining economic efficiency is accounting for all the factors which might be considered
benefits or costs of a particular project, and converting these benefits or costs into a monetary equivalent.
Consider for example a transportation construction project which promises to reduce everyone's travel
time to work. How do we place a value on that travel time savings? This is one of the fundamental
questions of engineering economics.
In the final evaluation of most ventures, economic efficiency takes precedence over physical efficiency
because projects cannot be approved, regardless of their physical efficiency, if there is no conceived
demand for them amongst the public, if they are economically infeasible, or if they do not constitute the
"wisest" use of those resources which they require.
There are numerous examples of engineering systems that have physical design but little economic worth
(i.e it may simply be too expensive !!). Consider a proposal to purify all of the water used by a large city by
2
Haery Sihombing/ IP
boiling it and collecting it again through condensation. This type of experiment is done in junior physical
science labs every day, but at the scale required by a large city, is simply too costly.
For the purposes of this brief tutorial, we cannot delve further into the analytical extensions required to
accommodate risk or uncertainty in the decision process. We must recognize that these things exist,
however, and be careful about reaching strong conclusions based on data which might be susceptible to
these. Because engineering is concerned with actions to be taken in the future, an important part of the
engineering process is improving the certainty of decisions with respect to satisfying the objectives of
engineering applications.
3
Haery Sihombing/ IP
Decisions among system alternatives should be made on the basis of their differences.
For a small number of real world systems there will be complete knowledge. Dll facts/information
and their relationships, judgements and predictive behavior become a certainty.
For most systems, however, even after all of the data that can be bought to bear on it has been
considered, some areas of uncertainty are likely to remain. If a decision must be made, these
areas of uncertainty must be bridged by consideration of non-quantitative data/information, such
as common sense, judgement and so forth.
Examples :
At the most basic level, cost allocation is simply part of good program budgeting and accounting
practices, which allow managers to determine the true cost of providing a given unit of service (Kettner,
Moroney, & Martin, 1990). At the most ambitious level, well-publicized cost-benefit studies of early
intervention programs have claimed to show substantial long-term social gains for participants and cost
savings for the public (Berreuta-Clement, Schweinhart, Barnett, et al., 1984). Because these studies have
been widely cited and credited with convincing legislators to increase their support for early childhood
programs, some practitioners advocate making more use of cost-benefit analysis in evaluating social
programs (Barnett, 1988, 1993). Others have cautioned that good cost-benefit or cost-effectiveness
studies are complex, require very sophisticated technical skills and training in methodology and in
principles of economics, and should not be undertaken lightly (White, 1988). Whatever position you take
in this controversy, it is a good idea for program evaluators to have some understanding of the concepts
involved, because the cost and effort involved in producing change is a concern in most impact
evaluations (Rossi & Freeman, 1993).
4
Haery Sihombing/ IP
COST ALLOCATION: Cost allocation is a simpler concept than either cost-benefit analysis or cost-
effectiveness analysis. At the program or agency level, it basically means setting up budgeting and
accounting systems in a way that allows program managers to determine a unit cost or cost per unit of
service. This information is primarily a management tool. However, if the units measured are also
outcomes of interest to evaluators, cost allocation provides some of the basic information needed to
conduct more ambitious cost analyses such as cost-benefit analysis or cost-effectiveness analysis. For
example, for evaluation purposes, you might want to know the average cost per child of providing an
after-school tutoring program, including the costs of staff salaries, snacks, and other overhead costs.
Besides budget information, being able to determine unit costs means that you need to be collecting the
right kind of information about clients and outcomes. In many agencies, the information recorded in
service records is based on reporting requirements, which are not always in a form that is useful for
evaluation. If staff in a prenatal clinic simply report the number of clients served by gender, for example,
you might know only that 157 females were served in March. For an evaluation, however, you might want
to be able to break down that number in different ways. For example, do young first-time mothers usually
require more visits than older women? Do single mothers or women with several children miss more
appointments? Is transportation to appointments more of a problem for women who live in rural areas?
Are any client characteristics commonly related to important outcomes such as birth weight of the the
baby? Deciding how to collect enough client and service data to give useful information, without
overburdening staff with unnecessary paperwork requirements, requires a lot of planning. Larger
agencies often hire experts to design data systems, which are called MIS or management-and-
information-systems.
If you are working for an existing agency, your ability to separate out unit costs for services or outcomes
may depend on the systems that are already in place for budgeting, accounting, and collecting service
data. However, if you are in a position to influence these functions, or need to supplement an existing
system, there are a number of texts that discuss the pros and cons of different ways of budgeting,
accounting, and designing MIS or management-and-information-systems (see Kettner, Moroney & Martin,
1990).
5
Haery Sihombing/ IP
COST-BENEFIT ANALYSIS: The basic questions asked in a cost-benefit analysis are, "Do the
economic benefits of providing this service outweigh the economic costs" and "Is it worth doing
at all"? One important tool of cost-benefit analysis is the benefit-to-costs ratio, which is the total
monetary cost of the benefits or outcomes divided by the total monetary costs of obtaining them. Another
tool for comparison in cost-benefit analysis is the net rate of return, which is basically total costs minus
the total value of benefits.
The idea behind cost-benefit analysis is simple: if all inputs and outcomes of a proposed alternative can
be reduced to a common unit of impact (namely dollars), they can be aggregated and compared. If
people would be willing to pay dollars to have something, presumably it is a benefit; if they would pay to
avoid it, it is a cost. In practice, however, assigning monetary values to inputs and outcomes in social
programs is rarely so simple, and it is not always appropriate to do so (Weimer & Vining, 1992;
Thompson, 1982; Zeckhauser, 1975).
An example will illustrate some of the differences between Cost-Effectiveness and Cost-Benefit
studies, what they can tell you, and some of the issues that neither can effectively address:
"Suppose the drop-out rate in an inner-city high school is 50%. Prevention Program A enrolls 20 students,
costs $20,000, and 15 of the 20 students (75%) graduate. Thus Program A resulted in 5 additional
graduates at a cost of $20,000, or one additional graduate for every $4,000. Prevention Program B
enrolls 20 students, costs $15,000, and 12 of the 20 students (60%) graduate. Thus Program B resulted
in 2 additional graduates at a cost of $15,000, or one additional graduate for every $7,500 spent.
Although Program B is cheaper ($15,000 compared to $20,000), Program A is more COST-EFFECTIVE
($4,000/each additional graduate, compared to $7,500/additional graduate). A COST-BENEFIT
ANALYSIS in this situation, instead of comparing unit costs, would require estimating the dollar value of
high school graduation (for example, by projecting the difference in lifetime earning capacity of graduates
over drop-outs, and lifetime social service costs), and comparing the monetary value of producing more
graduates to the monetary cost of providing the program in the first place. Neither method effectively
addresses more intangible outcomes of graduation, such as increased self-esteem, or the value of
a peer support system." (White, 1988, p. 430)
6
Haery Sihombing/ IP
x Whether the least expensive alternative is always the best alternative. Often political or
social values other than cost need to determine program and policy choices. When there are
competing values or goals involved, cost analysis is often just one factor to be considered, and
we need to have some other way of deciding which factors should take priority.
Tier 2 - Accountability
Clearly, fiscal accountability is one of the primary reasons for using any kind of cost analysis as part of
your evaluation. Any responsible program should keep service statistics and financial records that are
accurate and up-to-date enough to be able to determine some very basic information about unit costs,
and funders usually require this. However, the minimal information routinely collected by programs for
fiscal and reporting purposes is not always in a form that lends itself to evaluation uses. Often, unless
advance planning has taken place, this data is too aggregated to reflect outcomes of interest to
researchers and evaluators. At this stage (or earlier), careful consideration should be given to the kinds of
client and cost data that will be needed later, so that it can be built into the accounting and record-keeping
systems of the program (see Kettner, Moroney & Martin, 1990).
7
Haery Sihombing/ IP
The most common format is the Line-Item Budget format, which simply looks at revenues (money
coming in from various sources, including grants, user fees or United Way funds) and expenditures (costs
broken down into broad categories like salaries, rent, utilities, and postage), and tries to ensure that they
balance. The main purpose of a line-item budget is financial control, and the categories are usually too
broad to give much information about the cost of providing a particular service or obtaining a particular
result.
8
Haery Sihombing/ IP
The Functional Budget format starts with a line-item budget, and takes it a step further. It focuses on
process, or the cost of providing a service. For example, with a Functional Budget, we could determine
that it cost an adoption agency $45,000 to conduct 100 home studies (an activity which is a necessary
part of the process of placing children in permanent homes).
The Program Budget, which also starts with a line-item budget, looks at the same information from the
point of view of outcomes, or the cost of achieving a result. For example, if the 100 home studies resulted
in actually placing 50 children in adoptive homes, the Program Budget would allow us to say that it cost
the agency $45,000 to place 50 children, which is an outcome.
Another way to look at this is that functional budgets measure productivity, and program budgets
measure the cost of achieving goals and objectives.
9
Haery Sihombing/ IP
see whether one operates more efficiently. We can also compare the unit cost (per child) of adoptive
placement to the unit cost (per child) of placement in foster care or residential treatment. This is basically
what happens in a cost-effectiveness study.
In general, a cost-effectiveness study is more appropriate than a cost-benefit analysis when your goals or
outcomes can't easily be quantified or monetized, or when there are multiple competing goals. As with
budgeting and cost allocation, there are a variety of approaches to cost-effectiveness studies. The
approach that is best for your purposes will depend on a number of factors. A good source of more
detailed information about deciding what approach is most appropriate, and conducting the various types
of cost-effectiveness studies, is Weimer & Vining (1992).
10
Haery Sihombing/ IP
x Step 4: Estimate the Monetary Value of Outcomes - This is one of the most difficult and
controversial aspects of conducting a cost-benefit analysis, and it may require the help of
consultants. Some cost-savings are easier to estimate than others. For example, we may have
data that the average cost of placing a child in residential treatment is $20,000 a year, so if we
are able to prevent 20 children from being placed in residential treatment, the estimated savings
is 20 X $20,000. However, other important outcomes may be much less obvious, and much
harder to estimate.
x Step 5: Account for the Effects of Time - One of the trickiest and most technical aspects of
cost-benefit analysis, especially for longitudinal studies that follow clients or outcomes over a
period of years, is discounting of costs and calculating rates of return for alternative uses of the
money (such as investing it). This includes taking into account the effects of inflation on the value
of the dollar over time, or figuring the depreciation in the value of things like buildings and other
capital equipment. Similar issues apply in estimating the value of benefits over a period of time.
For example, if we want to look at the projected life-time earnings of a teenager who stays in
school due to a drop-out prevention program compared to one who does not, we need to make
projections about wages. If we want to look at whether the government will eventually recover its
investment in the drop-out program through the taxes he or she will pay on the increased income,
we need to make projections about future tax rates as well. These projections all require
assumptions. Unless you or someone on the program staff has expertise in this area, it is strongly
advised that you seek out a skilled consultant to help with this step.
x Step 6: Aggregate and Apply a Decision Rule - If you are looking at the costs and benefits on
several outcomes (which is often the case), how will you decide which has priority? If a program
for pregnant teenagers results in healthier babies (and lower hospital costs), but not in fewer
repeat pregnancies, which outcome is more important?
x Step 7: Describe Distributional Consequences - This is related to choosing your perspective of
analysis. It involves specifying who gains and who loses under different conditions (because in
some cases, one party's benefit is another party's loss). This may be a highly controversial and
political step in the process.
x Step 8: Conduct Sensitivity Analysis - This step involves identifying the assumptions behind
your cost estimates, and considering how critical they are to your calculations. If one of your
assumptions turns out not to be accurate, or if conditions change during the time of your study
(for example, the minimum wage goes up, affecting salary costs), will that change your whole
conclusion, or is the effect strong enough that there is some leeway?
x Step 9: Discuss the Qualitative Residual - Since there are almost always some things that
can't be quantified or given monetary values, it is important that your report include some
discussion of these issues. A frank description of some of these qualitative issues in your report
can help round out your conclusions, and reduce the chances of your study being used
inappropriately.
UTILITY
x Utility is the power of a good or service to satisfy human needs.
VALUE
x Designates the worth that a person attaches to an object or service.
x Is a measure or appraisal of utility in some medium of exchange.
x Is not the same as cost or price.
11
Haery Sihombing/ IP
2. Producer goods : Producer goods are the goods and services that satisfy human wants
indirectly as a part of the production or construction process. For example, factory equipment,
industrial chemicals ands materials.
UTILITY OF GOODS
1. Consumer goods : Basic human needs of food, clothing and shelter. In commercial
advertisements, emphasis is given to senses not reasoning. The utility in this case is considered
objectively and/or subjectively.
2. Producer goods : The utility stems for their means to get to an end. The utility in this case is
considered objectively.
ECONOMY OF EXCHANGE
1. Occurs when utilities are exchanged by two or more people.
2. It is possible because consumer utilities are evaluated subjectively.
3. Represents mutual benefit in exchange.
4. Persuasion in exchange. Salesperson.
ECONOMY OF ORGANIZATION
Through organizations, ends can be attained or attained more economically by:
1. Labor saving
2. Efficiency in manufacturing or capital use
CLASSIFICATION OF COST
A key objective in engineering applications is the satisfaction of human needs, which will nearly always
imply a cost.
12
Haery Sihombing/ IP
5. Law of diminishing return. A process can be improved at a rate with a diminishing return.
Example: cost of inspection to reduce cost of repair and lost production.
INTEREST RATE
Interest is a rental amount charged by financial institutions for the use of money.
1. Called also the rate of capital growth, it is the rate of gain received from an investment.
2. It is expressed on an annual basis.
3. For the lender, it consists, for convenience, of (1) risk of loss, (2) administrative expenses, and (3)
profit or pure gain.
4. For the borrower, it is the cost of using a capital for immediately meeting his or her needs.
Money has time-value because the purchasing power of a dollar changes with time.
13
Haery Sihombing/ IP
All disbursements and receipts (i.e. cash flows) are assumed to take place at the end of the year in which
they occur. This is known as the "end-of-year" convention.
Arrow lengths are approximately proportional to the magnitude of the cash flow.
Expenses incurred before time = 0 are sunk costs, and are not relevant to the problem.
Since there are two parties to every transaction, it is important to not that cash flow directions in cash flow
diagrams depend upon the point of view taken.
Example :
Figure 3 shows cash flow diagrams for a transaction spanning five years. The transaction begins with a
$1000.00 loan. For years two, three and four, the borrower pays the lender $120.00 interest. At year five,
the borrower pays the lender $120.00 interest plus the $1000.00 principal.
1. Cash Flow over Time : Upward arrow means positive flow, downward arrow means negative
flow. There are two cash flows to each problem (borrower and lender flows).
2. Net Cash Flow : The arithmetic sum of receipts (+) and disbursements (-) that occur at the same
point in time.
INTEREST FORMULAE
Interest formulae play a central role in the economic evaluation of engineering alternatives.
14
Haery Sihombing/ IP
TYPES OF INTEREST
1. Simple Interest : I = Pni.
P = Principal
i = Interest rate
n = Number of years (or periods)
I = Interestt.
Interest is due at the end of the time period. For fractions of a time period, multiply the interest by
the fraction.
Example : Suppose that $50,000 is borrowed at a simple interest rate of 8% per annum. At the
end of two years the interest owed would be:
I = $ 50,000 * 0.08 * 2
= $ 8,000
Principal P = $1000.00
Interest Rate i = 0.12.
Number of years (or periods) n = 5.
================================================================
Amount at Interest at Owed amount at
Year start of year end of year end of year Payment
================================================================
1 $1000.00 $120.00 $1120.00 $120.00
2 $1000.00 $120.00 $1120.00 $120.00
3 $1000.00 $120.00 $1120.00 $120.00
4 $1000.00 $120.00 $1120.00 $120.00
5 $1000.00 $120.00 $1120.00 $120.00
Example : A loan of $1,000 is made at an interest of 12% for 5 years. The principal and interest
are due at the end of the fifth year. The following table shows the resulting payment schedule:
Principal P = $1000.00
Interest Rate i = 0.12.
Number of years (or periods) n = 5.
================================================================
Amount at Interest at Owed amount at
Year start of year end of year end of year Payment
================================================================
1 $1000.00 $120.00 $1120.00 $0.00
2 $1120.00 $134.40 $1254.40 $0.00
3 $1254.40 $150.53 $1404.93 $0.00
4 $1404.93 $168.59 $1573.52 $0.00
5 $1573.52 $188.82 $1762.34 $1762.34
15
Haery Sihombing/ IP
F = P.[1 + i]^n
Example 1 : Let the principal P = $1000, the interest rate i = 12%, and the number of periods n = 4
years. The future sum is:
F = $1000 [1 + 0.12] ^ 4
= $1,573.5
Figure 4 shows the cash flow for the single present amount (i.e. P = 1000) and the single future
amount (i.e. F = $1,573.5).
F
P = =======
[1 + i]^n
The factor 1.0/[ 1 + i ]^n is known as the single-payment present-worth factor, and may be used to find
the present worth P of a future amount F.
Example 1 : Let the future sum F = $1000, interest rate i = 12%, and number of periods n = 4 years.
The single payment present-worth factor is:
F $1000.00
P = ========= = ============== = $635.50.
[1 + i]^n [ 1 + 0.12 ]^4
Example 2 : Let the future sum F = $1,573.5, the interest rate i = 12%, and the number of periods n
= 4 years. The single payment present-worth factor is:
16
Haery Sihombing/ IP
F $1573.50
P = ========= = ============== = $1000.00.
[1 + i]^n [ 1 + 0.12 ]^4
Figure 5 represents this scenario in graphical terms. At the end of Year 1 a payment of $ A begins the
accumulation of interest at rate i% for (n-1) years. At the end of Year 2 a payment of $ A begins the
accumulation of interest at rate i% for (n-2) years. End of year payments of $ A continue until Year N
(or n as written below).
The total accumulatio of funds at Year N is simply the sum of $A payments multiplied by the
appropriate single-payment present-worth factors. In tabular format we have:
n - 1 $ A . [ 1 + i ]
n $ A
==========================================================
$ F
==========================================================
17
Haery Sihombing/ IP
The total compound amount is simply the sum of the compound amounts for years 1 though n. This
summation is a geometric series:
[ 1 + i ]^n - 1
F = A * ------------------
i
[ 1 + 0.12 ]^4 - 1
F = 100 * ----------------------- = 477.9
0.12
0.12
A = 1000 * -------------------- = 209.2
[ 1 + 0.12 ]^4 - 1
Figure 6 summarizes the flow of disbursements and receipts (from the depositors point of view) for
this scenario.
Equating the principle $P (plus accumulated interest) with the accumulation of equal payments $A
(plus appropriate interest) gives:
18
Haery Sihombing/ IP
[ [ 1 + i ]^n - 1 ]
P [ 1 + i ]^n = A -----------------------
i
i * [ 1 + i ]^n
A = P * ---------------------
[ 1 + i ]^n - 1
[ 1 + i ]^n - 1
P = A * ---------------------
i * [ 1 + i ]^n
[ 1 + 0.12 ]^4 - 1
P = 100 * ----------------------------- = 303.7
0.12 * [ 1 + 0.12 ]^4
The gradient (G) is a value in the cash flow that starts with 0 at the end of year 1, G at the end of year
2, 2G at the end of year 3, and so on to (n-1)G at the end of year n.
*- -*
| 1 n |
A = G . | - - --------------- |
| i [ 1 + i ]^n - 1 |
*- -*
*- -*
| 1 4 |
A = $100 . | ---- - ------------------ | = $ 135.9
| 0.12 [ 1 + 0.12 ]^4 - 1 |
*- -*
19
Haery Sihombing/ IP
Therefore, the effective interest rate for any time interval is given by:
*- -* ^ l*m
| r |
i = | 1 + --- | - 1.0
| m |
*- -*
The product l*m is called c = the number of compounding periods in the time interval l. Note that c should
be > 1.
Continuous compounding: The limiting case for the effective rate is when compounding is performed
an infinite times in a year, that is continuously. Using l = 1, the following limit produces the continuously
compounded interest rate
*- -* ^ m
| r |
i_a = Limit | 1 + --- | - 1.0
m->infinity | m |
*- -*
i_a = e^r - 1
Example :
================================================================
Compounding Number of Effective interest Effective annual
frequency Periods rate per period interest rate
================================================================
20
Haery Sihombing/ IP
Example 1 : Let P = $1000, i = ??, n = 4 years, and F = $1200. The interest rate is
F
P = ---------
[1 + i]^n
$1000.00
P = -------------------- = $635.5
[1 + 0.12]^4
[ 1 + i ]^n - 1
F = A * ---------------------
i
The derivation of this formula can be found on page 46 of the economics text.
Example 1 : Let A = $100.00, i = 10%, and F = $1000.00. How many years n are needed ?
[ 1 + 0.12 ]^n - 1
$1000.00 = $100.00 * -----------------------
0.12
21
Haery Sihombing/ IP
i
A = F * ---------------
[ 1 + i ]^n - 1
Example 1 : Paying towards a future amount. Let F = $1000.00, i = 12%, and n = 4 years. What is A ?
0.12
A = $1000.00 * ------------------------------ = $209.20
1 + 0.12 ]^4 - 1
i * [ 1 + i ]^n
A = P * --------------------------
[ 1 + i ]^n - 1
[ 1 + i ]^n - 1
P = A * -------------------------
i * [ 1 + i ]^n
[ 1 + 0.10 ]^8 - 1
P = 100 * ----------------------------- = 533.49
0.10 * [ 1 + 0.10 ]^8
*- -*
| 1 4 |
A = 100.| ---- - ------------------ | = 135.9.
| 0.12 [ 1 + 0.12 ]^4 - 1 |
*- -*
22
Haery Sihombing/ IP
The equivalence can be established at any point in time. Arbitrarily setting n = 8 years, for example,
gives:
Note : Two or more distinct cash flows are equivalent if they are equivalent to the same cash flow.
The above cash flow can be converted to its present value as follows:
In this case, equivalence states that the actual interest rate earned on an investment is the one that sets
the equivalent receipts to the equivalent disbursements.
23
Haery Sihombing/ IP
By trial and error i = 10% will make the above equation valid. The equivalence can be made at any point
of reference in time, it does not need to be the origin (time = zero) to produce the same answer.
If the receipts and disbursement of cash flow are equivalent for some interest rate, the cash flows of any
equivalent portion of the investment are equal at that interest rate to the negative (-) of the equivalent
amount of t= he cash flows that constitute the remaining portion on the investment.
For example, break-up the above cash flow between year 4 and 5. Perform the equivalence at the 4th
year produces the following:
-1000(F/P,10,4)-500(F/P10,3)+482(F/A,10,3) = -(-250(P/F,10,1)+482(P/A,10,2)(P/F,10,1))
-1000(1.464)-500(1.331)+482(3.310) = -$(-250(0.9091)+482(1.7355)(0.9091))
-$534 = -$534
Example 1 : Payments = 100 at year end for three years; Interest = 6% per year compounded
quarterly.
I = 6/4 = 1.25%
F = $100 (F/P,1.25,8) + $100 (F/P,1.25,4) + $100
= $318.8
o *- -*^l *- -*^4
o | r | | 6 |
o i = | 1 + --- | - 1 = | 1 + --- | - 1 = 6.14%
o | m | | 4 |
o *- -* *- -*
Example 2 : Assume that end of month payments = 100 with interest of 15% continuous
compounding. What is the accumulated amount after 5 years ? The number of periods =12*5 =
60 years. The interest per month is 1/12= 1.25%. Then,
*- -* *- -*
| e^(rn) - 1 | | e^0.0125*60 - 1 |
F = A | ---------- | = $100.00 * | --------------- | = $8,865
| e^r -1 | | e^0.0125 - 1 |
*- -* *- -*
24
Haery Sihombing/ IP
By trial and error, it can be determined that i = 3.94% per semiannual period.
The nominal rate is 2(3.94) = 7.88%.
The effective rate is 8.04%.
The bond market.
Therefore,
I_t = A(P/A,i,n-(t-1))(i)
B_t = A - I_t
= A[1-(P/A,i,n-(t-1))(i)]
Since
Example : For P = $1000.00 (loan), n = 4, and i = 15%, the following table can be constructed:
The payment is A = $1000(A/P,15,4) = $1000(0.3503) = $350.30
25
Haery Sihombing/ IP
===============================================================
Year Loan Interest
End Payment Payment on Principal Payment
===============================================================
1 $350.30 $350.30(P/F,15,4) = $200.30 $150.00
2 $350.30 $230.32 $119.98
3 $350.30 $264.90 $85.40
4 $350.30 $304.62 $45.68
TOTAL $1401.12 $1000.14 $401.06
Note : Actual Consumer price index (CPI) and annual inflation rates for 1965 are shown in Table 5.1 of
the Economics Text.
CPI(t+1) - CPI(t)
-------------------------
CPI(t)
Assume the average inflation rate = f. The average rate can be computed as
CPI(t) [ 1 + f ] ^ n = CPI(t+n)
Example : Let the CPI(1966) = 97.2 and the CPI(1980) = 246.80. The average rate of inflation over the
14 year interval is:
*- -* ^ (1/14)
| 246.80 |
f = | -------- | - 1.0 = 6.88% per year.
| 97.2 |
*- -*
CPI(t-n)
--------------
CPI(t)
Now let's define k = annual rate of loss in purchasing power. Therefore the average rate of loss of
purchasing power is
CPI(t+n) [ 1 - k] ^ n = CPI(t)
It follows that
1
[ 1 + f ]^n = -----------
[ 1 - k ]^n
26
Haery Sihombing/ IP
This equation relates the average f inflation rate to k, the annual rate of loss in purchasing power.
CONSTANT DOLLARS
By definition
1
Constant dollars = ------------------ (actual dollars)
[ 1 + f] ^ n
When using actual dollars, use the market interest rate (i).
When using constant dollars, use the inflation-free interest rate (i*), defined as
1+i
i* = ------------ - 1
1+f
1+i
i* = -------------- - 1
[ 1 + f ]^n
CURRENCY EXCHANGE
Add notes later ......
PRESENT-WORTH AMOUNT
It is the difference between the equivalent receipts and disbursements at the present.
Assume F_t is a cash flow at time t, the present worth (PW) is
t=n
PW(i) = sum F(t) * [ 1 + i ] ^ -t
t=0
*- -* *- -*
| t = n | | i(1+i)^n |
= | sum F(t) * [ 1 + i ] ^ -t | * | ------------- |
| t = 0 | | (1+i)^n - 1 |
*- -* *- -*
27
Haery Sihombing/ IP
=======================================
Year end Receipts Disbursements
=======================================
0 $0.00 -$1000.00
1 $400.00 $0.00
2 $900.00 -$1000.00
3 $400.00 ....
4 $900.00 -$1000.00
... ....... ....
n-2 $900.00 -$1000.00
n-1 $400.00 $0.00
n $900.00 $0.00
Therefore,
AE(10) = [-1000+400(P/F,10,1)+900(P/F,10,2)](A/P,10,2)
for 10%, or
AE(10) = [-$1000+400(0.9091)+900(0.8265)](0.5762)
= $61.93
PW, AE, and FW differ in the point of time used to compare the equivalent amounts.
t=n
0 = PW(i*) = sum F(t) * [ 1 + i* ] ^ -t
t=0
28
Haery Sihombing/ IP
MEANING OF IRR
It represents the rate of return on the unrecovered balance of an investment (or loan). The following
equation can be developed for loans:
It should be noted that the basic equation for i^* requires the solution of the roots of a nonlinear
(polynomial) function. Therefore, more than one root might exist. The following conditions results in one
root (single i*):
PAYBACK PERIOD
a. Without Interest : The payback period without interest is the length of time required to recover the first
cost of an investment from the cash flow produced by the investment for an interest rate of zero. It can be
computer as the smallest n that produces
t=n
Sum [ F_t > 0 ]
t=o
b. With Interest : The payback period with interest is the length of time required to recover the first cost
of an investment from the cash flow produced by the investment for a given interest rate. It can be
computer as the smallest n that produces
t=n
Sum F_t * [1 + i]^[-t] >= 0
t=o
ANNOTATED BIBLIOGRAPHY
1. Barnett, W. S. (1993). The economic evaluation of home visiting programs. The Future of Children:
Home Visiting, 3. Center for the Future of Children, the David and Lucile Packard Foundation, 93-112.
The Future of Children journal is available on-line. Some issues can be viewed or downloaded at the following World Wide Web
site, and older hard copy issues can be ordered free of charge at: http://www.futureofchildren.org/
Barnett is a strong advocate of more use of cost-benefit or cost-effectiveness analyses in evaluations of social programs. He has
been involved in conducting several influential cost-benefit studies of home visiting and early intervention programs (including the
well-known Perry Preschool Program study), and reviews several others. He argues that it is more feasible than most evaluators
believe, and provides a relatively detailed discussion of steps and procedures.
2. Barnett, W.S. (1985). Benefit-cost analysis of the Perry Preschool program and its policy implications.
Educational evaluation and policy analysis, 7. 333-342.
29
Haery Sihombing/ IP
3. Berreuta-Clement, J. R., Schweinhart, L. J., Barnett, W. S. , et al. (1984). Changed lives: The effects of
the Perry Preschool program on youths through age 19. Monographs of the High/Scope Educational
Research Foundation, no. 8. Ypsilanti, MI: High/Scope Press.
One of the best-known and most influential longitudinal studies of the effects of early intervention programs. The influence of this
study on funders and policy makers is often attributed to its use of a cost-benefit analysis to show that funding intensive
programs for low-income preschoolers can be a good long-term investment for society.
4. Callor, S., Betts, S. C., Carter, R., & Marczak, M. (1997). State Strengthening Evaluation Guide.
Tucson, AZ: USDA/CSREES & University of Arizona.
Program development and evaluation manual designed by the Evaluation Collaboration for use in State Strengthening Projects.
Based on the five-tiered model of evaluation of Jacobs (1988). The manual may be viewed or downloaded from the World Wide
Web at: http://ag.arizona.edu/fcr/fs/cyfar/evalgde.htm
5. Cook, T. D., & Campbell, D. T. (1979). Quasi-experimentation: Design and analysis issues for field
settings. Boston: Houghton-Mifflin Co.
This is a standard reference on quasiexperimental research designs, which are commonly used for evaluation of community-
based programs.
6. Jacobs, F.H. (1988). The five-tiered approach to evaluation: Context and implementation. In H.B.
Weiss, & F.H. Jacobs (Eds.), Evaluating family programs. New York: Aldyne de Gruyter.
This chapter describes a model of evaluation of community-based programs which served as the basis for the model used in the
State Strengthening Evaluation Guide.
7. Kettner, P. M., Moroney, R. M., & Martin, L. L. (1990). Designing and managing programs: An
effectiveness-based approach. Newbury Park, CA: Sage.
Useful discussion of the pros and cons of several budgeting systems (line-item, functional, and program budgeting) in terms of
facilitating the calculation of unit costs. Emphasizes that cost allocation is time-consuming and requires careful choices about
methodology. Concludes that despite the difficulties of setting up such a budgeting system, it is worth the time and effort for
programs to be able to accurately determine true unit costs and program costs. Although the advantages are primarily discussed
in terms of practical benefits for program managers, the ability to accurately allocate costs and value of services is also a
prerequisite for cost-benefit analysis as a long-term evaluation strategy.
8. Mishan, E. J. (1988). Cost-benefit analysis (4th ed.). London: Unwin Hyman.
An economics textbook, and one of the standard references for cost-benefit analysis techniques. Although fairly technical and
mathematically oriented, this book is intended to be accessible to serious non-economists who are willing to devote some time
and effort to learning the theory and techniques. Includes a sometimes whimsical discussion of the problems of valuing
intangibles, such as time.
9. Rossi, P. H., & Freeman, H. E. (1993). Evaluation: A systematic approach (5th ed.). Newbury Park:
Sage Publications, pp. 363-401.
A standard evaluation text. Rossi and Freeman take the position that while "efficiency assessment" (their term for cost-benefit
and cost-effectiveness analyses) is highly technical therefore not always feasible, all program evaluators should at least have
some understanding of the basic concepts involved. This is because impact evaluations always implicitly involve issues of how
much effort or cost is required to achieve a desired outcome.
10. Thompson, M. S. (1980). Benefit-cost analysis for program evaluation. Beverly Hills: Sage.
Another basic text, which elaborates on the quantitative aspects of benefit-cost (or cost-benefit) analysis. Includes in-depth
discussions of issues of discounting and cost adjustments.
11. Weimer, D. L., & Vining, A. R. (1992). Policy analysis: Concepts and practice (2nd ed.). Englewood
Cliffs, NJ: Prentice Hall.
Fairly technical discussion aimed at professional policy analysts; assumes a background in economics. Useful discussion and
flow chart distinguishes five related approaches and when they are appropriate to use: Benefit-Cost Analysis, Qualitative Benefit-
Cost Analysis, Modified Benefit-Cost Analysis, Cost-Effectiveness Analysis, and Multi-Goal Analysis. Appropriateness of each
method is determined primarily by 1) whether the relevant impacts and inputs can be readily quantified and monetized, and 2)
whether there are goals or benefits other than economic efficiency which need to be incorporated into the analysis.
12. White, K. R. (1988). Cost analyses in family support programs (pp. 429-443). In H. B. Weiss & F. H.
Jacobs (Eds.), Evaluating family programs. New York: Aldyne de Gruyter.
Suggests use of general term "cost analyses". Basically takes a skeptical approach, noting that "present conceptualizations of
cost analysis are overly simplistic, expectations are unrealistically high, and much of what is labeled as cost-effectiveness or
cost-benefit research suffers from serious conceptual and methodological inadequacies" (p.429).
13. Zeckhauser, R. (1975). Procedures for valuing lives. Public Policy, 23(4), 419-464.
30
Haery Sihombing/ IP
ENGINEERING ECONOMICS
Introduction:
The objective of this module is to describe the return to capital in the form of interest (or profit) and
to illustrate how basic equivalence calculations are made with respect to the time value of capital in
engineering economy studies.
Concept of Equivalence
To compare alternatives that provide the same service over extended periods of time when interest
is involved, we must reduce them to an equivalent basis that is dependent on: ---If two alternatives
are economically equivalent, then they are equally desirable.
Equivalence factors are needed in engineering economy to make cash flows (CF) at different points
in time comparable. For example, a cash payment that has to be made today cannot be compared
directly to a cash flow that must be made in 5 years.
We need a way to reduce CF's at different times to an equivalent basis. Equivalence factors allow
us to do so.
Principles of Equivalence
x Equivalent cash flows have the same economic value at the same point in time.
x Cash flows that are equivalent at one point in time are equivalent at any point in time.
x Conversion of a cash flow to its equivalent, at another point in time must reflect the interest
rate(s) in effect for each
period between the equivalent cash flows.
x Equivalence between receipts and disbursements: the interest rate that sets the receipts
equivalent to the disbursements is
the actual interest rate (IRR).
x Economic equivalence is established, in general, when we are indifferent between a future
payment, or series of payments, and a present sum of money.
31
Haery Sihombing/ IP
1. The Horizontal line is a time scale, with progression of time moving from left to right. The period
(e.g., year, quarter, month) labels can be applied to intervals of time rather than to points on the
time scale.
2. The arrows signify cash flows and are placed at the end of the period. If a distinction needs to be
made, downward arrows represent expenses (negative cash flows or cash outflows) and upward
arrows represent receipts (positive cash flows or cash inflows).
3. The cash flow diagram is dependent on the point of view. The situations shown in the figure were
based on the cash flows as seen by the lender. If the directions of all arrows had been reversed, the
problem will have to be diagrammed from borrower's viewpoint.
Simple Interest
The amount of interest earned (or paid) is directly proportional to the principal of the loan, the umber
of interest periods for which the principal is committed, and the interest rate per period.
Compound Interest
The amount of interest earned (or paid) per interest period depends on the remaining principal of
the loan plus any unpaid interest charges.
Example
Loan $1000 for 3 years at 10% per year.
(1) (2)=(1)x10% (3)=(1)+(2)
Period
Amount Owed @ Interest Amount Amount Owed @
Beginning of Period for Period End of Period
1 $1,000 $100 $1,100
2 $1,100 $110 $1,210
3 $1,210 $121 $1,331
A graphical comparison of simple interest and compound interest is given in Figure 4-1. As the
number of periods increases, the difference in the compound and simple becomes greater. The
32
Haery Sihombing/ IP
difference is due to the effect of compounding, which is essentially the calculation of interest on
previously earned interest. This difference would be much greater for larger amounts of money,
higher interest rates, or greater number of years. Thus, simple interest does consider the time value
of money but does not involve the compounding of interest. Compound interest is much more
common in practice than simple interest.
The F/P factor converts a single cashflow or an equivalent cash flow in a year after it. Another way
to think of it is, a F/P factor moves a cash flow forward in time.
33
Haery Sihombing/ IP
Annuities
Annuities are a series of equal cash flows that occur every period. Don't let the name mislead you;
these cash flows are not restricted to years. Monthly car payments can be treated as monthly
annuities, likewise for equal CF's that occur every quarter, or every six months.
Two factors are used to convert annuities to single cash flow equivalents F/A and P/A.
Likewise, A/F and A/P factors allow us to convert single cash flows into an equivalent
series of annuities. It should be noted that the formulas and tables to be presented are
derived such that A occurs at the end of each period, and thus:
1. P (present equivalent value) occurs one interest period before the first A (uniform amount).
2. F (future equivalent value) occurs at the same time as the last A, and N periods after P.
3. A (annual equivalent value) occurs at the end of periods 1 through N, inclusive.
34
Haery Sihombing/ IP
If a cash flow in the amount of A dollars occurs at the end of each period for N periods and i% is the
interest (profit or growth) rate per period, the future equivalent value F, at the end of the Nth period
is obtained by summing the future equivalents of each of the cash flows. Thus,
35
Haery Sihombing/ IP
Deferred Annuities
Up to this point, we have been discussing ordinary annuities where the first cash flow is
made at the end of the first period. A deferred annuity exists when the first cash flow does
not begin until J periods after the zeroth period, as shown in the figure below.
Besides the fact that the annuity begins in year j, we can use the factors presented before to
work with it. However, we will have to exercise a bit of care and in some cases we will need
to use multiple factors.
First, we use a P/A factor to collapse the annuity into a single cash flow in year j.
Pj = A (P/A, i, n-j)
Next, a P/F factor is used to bring Pj back to year zero.
P0 = Pj (P/F, i, j)
36
Haery Sihombing/ IP
Treating the cash flows in a step-by-step manner can be tedious, it is easier to combine the factors
into one equation by substituting for Pj in the second expression, giving:
P0 = [A (P/A, i, n-j)](P/F, i, j)
P0 = Pj (P/F, i, j)
Treating the cash flows in a step-by-step manner can be tedious, it is easier to combine the factors
into one equation by substituting for Pj in the second expression, giving:
P0 = [A (P/A, i, n-j)](P/F, i, j)
Find the present equivalent of the following CFD (i=5%). In this case, we have to transform each
cash flow into its equivalent in year 0 using a P/F factor. We'll build the expression for P0 one step
at a time,
37
Haery Sihombing/ IP
P0 = 750(P/F,5%,3) + ...
P0 = 750(P/F,5%,3) + 1500(P/F,5%,6) + ..
38
Haery Sihombing/ IP
While a single correct sequence of CFs does not exist, we have to be careful to include all the cash
flows in the CFD. One sequence:
We could treat the annuities as one of $1000 in years 4 through 10 and a second annuity of $500 in
years 8, 9, and 10.
39
Haery Sihombing/ IP
For example, convert the following into an annual series of equal cash flows in years 1 through 6.
(i=9%)
A= -25(A/G, 9%, 6)
Note that even though there is no cash flow in year 1 with the gradient cash flows, with the annuity
cash flows there is a cash flow in year 1.
40
Haery Sihombing/ IP
Gradients can be confusing, although in the generic cases shown above we'd say that the gradient
occurs in years 1 through N there is no cash flow in year 1.
If we had the cash flow given below, we can use the P/G factor to find the present equivalent
(i=8%).
P0 = 50(P/G, 8%, 5)
For more complex cases, it is usually easiest to decompose a cash flow into two parts: an annuity
and a gradient so that
P = A(P/A, i, N) + G(P/G, i, N)
Where
A = the magnitude and sign of the annual cash flow (equal to the magnitude of the first observed
cash flow,
G = the magnitude and sign of the gradient cash flow
i = the interest rate
N = the number of periods over which the annuity and gradient occur.
41
Haery Sihombing/ IP
Introduction:
When we talk of alternatives, we mean distinct, independent solutions to a given problem (Mutually
Exclusive Alternatives).
The problem may be the purchase of a new piece of machinery, in which case the alternatives are
different models of the desired machine. Another problem could be deciding how to save money for
a child's college education, in which case the alternatives could include savings vehicles such as
savings accounts, bonds, or stock investments.
Alternatives can be broadly classified as either investment alternatives or cost alternatives.
Investment alternatives involve an initial, first time cost (usually in year zero - the present) with net
positive future cash flows (Revenue minus Costs). Unless otherwise stated, Do Nothing is always
an alternative when choosing from a set of investment alternatives. Do Nothing would be the most
desirable choice if none of the investment alternatives is profitable at the given MARR.
Cost alternatives involve an initial, first time cost and further cost cash flows during the life of the
project. When cost alternatives are being considered, Do Nothing is rarely a feasible option. The
organization must spend the money with no chance to recover it. The most desirable cost
alternative is the one that minimizes the total cost (as measured by PW, AW, or FW).
An alternative is profitable if its PW (MARR)>=0. When choosing from a set of alternatives, the most
desirable is the alternative with the most positive present worth.
To find PW as a function of i % (per interest period) of a series of cash inflows and outflows, it is
necessary to discount future amounts to the present by using the interest rate over the appropriate
study period (years, for example) in the following manner:
Where
i = effective interest rate, or MARR, per compounding period
k= index for each compounding period
Fk= future cash flows at the end of period k
N = number of compounding periods in the planning horizon (i.e., study period)
42
Haery Sihombing/ IP
An alternative is profitable if its FW(MARR)>=0. When choosing from a set of alternatives, the most
desirable is the alternative with the most positive annual worth.
An alternative is profitable if its AW (MARR)>=0. When choosing from a set of alternatives, the most
desirable is the alternative with the most positive annual worth.
The AW of a project is annual equivalent revenues or savings (R) minus annual equivalent
annual expenses (E), less its annual equivalent Capital Recovery (CR) amount, which is
can be calculated by,
where,
An annual equivalent value pf R, E and CR is computed for the study period, N, which is usually in
years. In equation form the AW, which is a function of i%, is N, which is usually in years. The AW
can be calculated by the following formula,
AW(i%)=R-E-CR(i%)
Also, we need to notice that the AW of a project is equivalent to its PW and FW. That is,
AW=PW(A/P, i%,N) and AW=FW(A/F,i%,N). Hence, it can be computed for a project from these
equivalent values.
The AW worth is most useful when comparing alternatives with unequal expected lives.
43
Haery Sihombing/ IP
Solution
Although no method was specified, PW is usually the most straightforward to use. Since all
products have expected lives of 6 years, PW is a good choice. We'll also assume that the study
period is 6 years. Now, we just have to calculate the PW of each alternative. Remember, since
these are investment alternatives, Do Nothing is also a possible choice, if none of the alternatives
prove profitable with a MARR of 15%.
Since PWB<0, it can immediately be ruled out as an option since at a MARR of 15% it is not
profitable. The final choice must be made between products A and B, both have PW>0. Since
PWC>PWA, Product C is the final choice, since it is the most profitable - even though it has the
highest initial investment.
ABC Company must install a water purification system to comply with local clean water laws. All
relevant estimates for systems on the market are supplied in the table below. If the company's
MARR is 12%, which alternative should they pursue?
A B C
Investment 80,000 88,000 94,000
Estimated Annual Expenses 8,000 6,200 5,800
Salvage Value 22,000 26,000 31,000
Expected Life 15 years 15 years 15 years
44
Haery Sihombing/ IP
Solution:
Although no method was specified, PW is usually the most straightforward to use. Since all 3
products have expected lives of 15 years, PW is a good choice. We'll also assume that the study
period is 15 years. Now, we just have to calculate the PW of each alternative.
Remember, since these are cost alternatives, Do Nothing is not a possible choice, none of the
alternatives will be profitable with a MARR of 12% (since they involve mostly negative cash flows)
but the company must choose one.
Since we have cost alternatives, we want to choose the one that has the least negative present
worth, that is the one that costs the least over the study period. System B is the final choice, since it
is the least costly- even though it is not the least expensive to install or operate.
45
Haery Sihombing/ IP
Solution
In this case the useful life of Investment B is shorter than the study period of 10 years, so we can
assume repeatability, we will invest in B in years 0 and 5 - repeating it twice.
Since we are assuming repeatability, it is easiest to use the Annual Worth method to compare the
alternatives. That way, we only need to compute the AW for each during its useful life.
Since we are looking at investment alternatives, we want to choose the most profitable project. B is
not profitable while A is just profitable at the chosen MARR, so the final selection would be
alternative A.
46
Haery Sihombing/ IP
Boiler A Boiler B
Capital Investment $50,000 $120,000
Useful Life (N) 20 years 40 years
Salvage Value at EOY N 10,000 20,000
9,000 3,000 increasing 300 per year
Annual Operating Costs
after the first year
If the MARR is 10% per year, which boiler would you recommend? State all assumptions.
Solution:
First, the choice involves cost alternatives, so Do Nothing is not an option - the plant must add
another boiler. From the data we can assume that the study period is 40 years, and since the useful
life of Boiler A is 20 years, we must assume repeatability.
Once again we will use the Annual Worth method to compare the alternatives. That way, we only
need to compute the AW for each during its useful life.
If electricity costs $0.07 per kilowatt-hour, which motor should be selected if MARR=8% per year?
Refer to the data below.
Pump X Pump Y
Initial cost $1,200 $1,000
Electrical efficiency 0.82 0.77
Annual Maintenance cost $60 $100
Useful Life 5 years 5 years
Salvage value at end of useful life 0 0
47
Haery Sihombing/ IP
Solution:
First, the choice involves cost alternatives, so Do Nothing is not an option - a pump must be
purchased.
Any of the equivalent worth methods can be used to make the recommendation, we'll use AW and
then check the answer using PW.
Motor X
Each pump has three costs associated with it: the initial purchase cost, the annual maintenance
cost, and the annual operating cost (consumption of electricity - Cx). The first two are given to us
and we have enough data to calculate the third as follows:
Cx = Electrical Input x (conversion factor from hp to kW) x (hours of operation) x (cost of electricity)
[HINT: Check your units to make sure the final number is in the correct units]
Electrical input refers to the electrical efficiency of the pump. Both motors output 50hp but require
different amounts of input since neither is 100% efficient. Since efficiency=ouput/input, we can find
the electrical input of pump X as follows:
We know electricity costs $0.07 per kW-hr and we need 1000 hours per year. Finally, we find that
1hp = 0.746kw. We are ready to find Cx:
Motor Y
A similar approach is used to calculate the AW of Motor Y:
Confirm with PW
PWX = -$1,200 + (-$60 -$3,184.15)(P/A,8%,5)
PWX = -$1,200 + (-$60 -$3,184.15)(3.9927)
PWX = -$14,152.92
PWY = -$1,000 + (-$100 -$3,390.91)(P/A,8%,5)
PWY = -$1,000 + (-$100 -$3,390.91)(3.9927)
PWY = -$14,938.16
As we should expect, PW confirms that Pump X is the better alternative.
48
Haery Sihombing/ IP
The concept that items are of the same type or desirability. If two
Equivalence alternatives are economically equivalent, then they are equally desirable.
Future Worth Method that evaluates the desirability of an alternative relative to some
Method future point in time, such as the end of the study period.
Interest the profit in goods or money that is made on invested
MARR Minimum Attractive Rate of Return
Present Worth Method that evaluates the desirability of an alternative relative to some
Method base point in time called the present
The amount of interest earned (or paid) is directly proportional to the
Simple Interest principal of the loan, the number of interest periods for which the
principal is committed, and the interest rate per period.
49
ENGINEERING ECONOMICS
Factor Name Converts Symbol Formula
Single Payment
to F given P (F/P, i%, n) (1 + i)n
Compound Amount
Single Payment
to P given F (P/F, i%, n) (1 + i) –n
Present Worth
Uniform Series i
to A given F (A/F, i%, n)
Sinking Fund 1 i n 1
i 1 i
n
Capital Recovery to A given P (A/P, i%, n)
1 i n 1
Uniform Series
to F given A (F/A, i%, n)
1 i n 1
Compound Amount i
Uniform Series 1 i n 1
to P given A (P/A, i%, n)
i 1 i
Present Worth n
Uniform Gradient 1 i n 1 n
to P given G (P/G, i%, n)
i 2 1 i i 1 i
Present Worth n n
Uniform Gradient †
to F given G (F/G, i%, n)
1 i n 1 n
Future Worth i2 i
Uniform Gradient 1 n
to A given G (A/G, i%, n)
Uniform Series i 1 i n 1
B ..........Benefit ie ¨1 ¸ 1
© m¹
BV ........Book Value
BREAK-EVEN ANALYSIS
C ..........Cost
By altering the value of any one of the variables in a
d...........Combined interest rate per interest period
situation, holding all of the other values constant, it is
Dj .........Depreciation in year j possible to find a value for that variable that makes the two
F ..........Future worth, value, or amount alternatives equally economical. This value is the break-
f............General inflation rate per interest period even point.
G ..........Uniform gradient amount per interest period Break-even analysis is used to describe the percentage of
capacity of operation for a manufacturing plant at which
i............Interest rate per interest period
income will just cover expenses.
ie...........Annual effective interest rate
The payback period is the period of time required for the
m ..........Number of compounding periods per year profit or other benefits of an investment to equal the cost of
n...........Number of compounding periods; or the expected the investment.
life of an asset
P ..........Present worth, value, or amount INFLATION
To account for inflation, the dollars are deflated by the
r ...........Nominal annual interest rate
general inflation rate per interest period f, and then they are
Sn..........Expected salvage value in year n shifted over the time scale using the interest rate per
Subscripts interest period i. Use a combined interest rate per interest
j............at time j period d for computing present worth values P and Net P.
The formula for d is
n...........at time n
†...........F/G = (F/A – n)/i = (F/A) u (A/G) d = i + f + (i u f)
ENGINEERING ECONOMICS (continued)
A
DEPRECIATION Capitalized Costs = P =
i
C Sn
Straight Line Dj
n BONDS
Bond Value equals the present worth of the payments the
Accelerated Cost Recovery System (ACRS)
purchaser (or holder of the bond) receives during the life of
Dj = (factor) C the bond at some interest rate i.
A table of modified factors is provided below. Bond Yield equals the computed interest rate of the bond
BOOK VALUE value when compared with the bond cost.
BV = initial cost – 6 Dj RATE-OF-RETURN
TAXATION The minimum acceptable rate-of-return is that interest rate
that one is willing to accept, or the rate one desires to earn
Income taxes are paid at a specific rate on taxable
on investments. The rate-of-return on an investment is the
income. Taxable income is total income less
interest rate that makes the benefits and costs equal.
depreciation and ordinary expenses. Expenses do not
include capital items, which should be depreciated. BENEFIT-COST ANALYSIS
In a benefit-cost analysis, the benefits B of a project should
CAPITALIZED COSTS exceed the estimated costs C.
Capitalized costs are present worth values using an
B – C t 0, or B/C t 1
assumed perpetual period of time.
But wait! Bank 3 says they will give us 6% nominal interest rate
compounded weekly:
Project has been told that they may win their bid to house the
Bush Library, if they can guarantee that they can fund the upkeep and
repairs in perpetuity forever.) The library is expected to cost $2000
every two months for light bulbs, plus $100,000 every 12 months for minor
repairs, plus an additional $5,000,000 every 5 years for a complete
refurbishing of the facility. How much must be deposited today to
guarantee the funding of these expenses? Assume a nominal interest rate
of 6%, compounded monthly.
repairs, and then continue depositing $8110 each month forever, and you
will always be able to withdraw $100,000 at the end of every year.
Now let's change the a3 into a monthly (the bank's compounding period)
annuity. Setting the value needed ($2000 every two months) to the Future
value needed, and realizing that we are paid 0.005% per period, and that
we have two periods to get the money:
This says that if you will invest $997.60 dollars each month as an annuity
(you must follow the rules - first deposit goes in at the end of the first
month,) for a total of 2 months, you will have $2,000 at the end of the 2
month period. You can then withdraw this to make your necessary
repairs, and then continue depositing $997.60 each month forever, and
you will always be able to withdraw $2,000 at the end of every 2 month
period.
Now let's change the into a monthly (the bank's compounding period)
annuity. Setting the value needed ($5,000,000 every 60 months) to the
Future value needed, and realizing that we are paid 0.005% per period,
and that we have 60 periods to get the money:
This says that if you will invest $71,500 dollars each month as an annuity
(you must follow the rules - first deposit goes in at the end of the first