RENCANA DAN REALISASI TENAGA KERJA MEP

PROYEK PEMBANGUNAN RUMAH SUSUN TINGKAT TINGGI KEMAYORAN


MINGGU KE : III ( DESEMBER 2016 )

CUT OF 18 NOV' 2016 CUT OF RENCANA PENAMBAHAN TENAGA KERJA


NO BLOK/TOWER PEKERJAAN NAMA SUBKONT RENCANA REALISASI KURANG STATUS 18 DES' DESEMBER 2016 TOTAL
(-) 2016 18 19 20 21 22 23 24 25

I BLOK D 10-2 1. PLUMBING PT BINTANG MILENIUM PERKASA 51 39 12 RENCANA 35 - - - - - - - - 23


TOWER 3 REALISASI 23 - - - - - - - - 23

2. HYDRANT/SPRINKLER PT BINTANG MILENIUM PERKASA 42 39 3 RENCANA 35 - - - - - - - - 31


REALISASI 31 - - - - - - - - 31

3. ELEKTRIKAL PT. CAHAYA TEKNINDO MAJUMANDIRI 56 41 15 RENCANA 46 - - - - - - - - 36


REALISASI 36 - - - - - - - - 36
-
4. TATA UDARA PT. CAHAYA HAFIS CONSTRUCTION 33 0 33 RENCANA 0 - - - - - - - - 42
REALISASI 42 - - - - - - - - 42

5.FIRE ALARM & SOUND PT. DANATEL PRATAMA 0 0 0 RENCANA 0 - - - - - - - - 0


SYSTEM REALISASI 0 - - - - - - - - 0

RENCANA 0 0 0 0 0 0 0 0 132
Sub Total Blok D10-2 Tower 3
REALISASI 0 0 0 0 0 0 0 0 132

II BLOK D 10-2 1. PLUMBING PT BINTANG MILENIUM PERKASA 51 29 22 RENCANA 31 - - - - - - - - 42


TOWER 4 REALISASI 42 - - - - - - - - 42

2. HYDRANT/SPRINKLER PT BINTANG MILENIUM PERKASA 42 48 -6 RENCANA 31 - - - - - - - - 31


REALISASI 31 - - - - - - - - 31

3. ELEKTRIKAL PT. CAHAYA TEKNINDO MAJUMANDIRI 56 42 14 RENCANA 48 - - - - - - - - 62


REALISASI 62 - - - - - - - - 62

4. TATA UDARA PT.WASKITA KARYA ( Ex. PT.CHC ) 33 0 33 RENCANA 8 - - - - - - - - 8


REALISASI 8 - - - - - - - - 8
- - - -
5.FIRE ALARM & SOUND PT. DANATEL PRATAMA 0 0 0 RENCANA 0 - - - - - - - - 0
SYSTEM REALISASI 0 - - - - - - - - 0

RENCANA 0 0 0 0 0 0 0 0 143
Sub Total Blok D10-2 Tower 4
REALISASI 0 0 0 0 0 0 0 0 143

III BLOK C2 - 2 1. PLUMBING PT. INNOTEK MEGAH INDONESIA 50 33 17 RENCANA 50 - - - - - - - - 32


TOWER 2 REALISASI 32 - - - - - - - - 32

2. HYDRANT/SPRINKLER PT. CAHAYA TEKNINDO MAJUMANDIRI 56 30 26 RENCANA 51 - - - - - - - - 57


REALISASI 57 - - - - - - - - 57
3. ELEKTRIKAL PT. CAHAYA TEKNINDO MAJUMANDIRI 56 30 26 RENCANA 64 - - - - - - - - 64
REALISASI 64 - - - - - - - - 64

4. TATA UDARA PT. PANATA BAYU 28 4 24 RENCANA 28 - - - - - - - - 25


REALISASI 25 - - - - - - - - 25

5.FIRE ALARM & SOUND PT. DANATEL PRATAMA 0 0 0 RENCANA 0 - - - - - - - - 0


SYSTEM REALISASI 0 - - - - - - - - 0

JUMLAH 554 335 219


RENCANA 0 0 0 0 0 0 0 0 178
Sub Total Blok C2-2 Tower 2
REALISASI 0 0 0 0 0 0 0 0 178

RENCANA 0 0 0 0 0 0 0 0 453
TOTAL
REALISASI 0 0 0 0 0 0 0 0 453

Jakarta, 19 Desember 2
REALISASI TENAGA KERJA MEP
UMAH SUSUN TINGKAT TINGGI KEMAYORAN

DEVIASI
DARI KETERANGAN
RENCANA

- Jumlah pekerja belum


-28 terpenuhi dari rencana.

- Jumlah pekerja belum


-11 terpenuhi dari rencana.

- Kendala Fitting Kabel


-20 Tray & Kabel Ladder.

- Progres lapangan belum


9 tercapai sesuai target.

- Persiapan
0

-50

- Tenaga kerja berkurang


-9 19 Org setelah Cut Of
Tgl 18 Nov 16
- 48 Org dari Cut Of tgl.18
-11 Nov 2016

- Kendala Fitting Kabel


6 Tray & Kabel Ladder

- On Progres
-25

- Persiapan
0

-39

- Jumlah pekerja belum


-18 terpenuhi dari rencana.

- Kondisi saat ini dapat


1 mengikuti progres.
- Kendala Fitting Kabel
8 Tray & Kabel Ladder

- Kondisi saat ini dapat


-3 mengikuti progres.

- Persiapan
0

-12

-101

Jakarta, 19 Desember 2016


RENCANA DAN REALISASI TENAGA KERJA MEP
PROYEK PEMBANGUNAN RUMAH SUSUN TINGKAT TINGGI KEMAYORAN
MINGGU KE : IV ( NOPEMBER 2016 )

CUT OF 18 NOV' 2016 UPDATE DEVIASI


NO BLOK/TOWER PEKERJAAN NAMA SUBKONT RENCANA REALISASI KURANG 11/29/2016 DARI
(-) RENCANA

I BLOK D 10 - 3 1. PLUMBING PT BINTANG MILENIUM PERKASA 51 39 12 35 16

2. HYDRANT/SPRINKLER PT BINTANG MILENIUM PERKASA 42 39 3 33 9

3. ELEKTRIKAL PT. CAHAYA TEKNINDO MAJUMANDIRI 56 41 15 39 17

4. TATA UDARA PT. CAHAYA HAFIS CONSTRUCTION 33 0 33 20 13

II BLOK D 10 - 4 1. PLUMBING PT BINTANG MILENIUM PERKASA 51 29 22 31 20

2. HYDRANT/SPRINKLER PT BINTANG MILENIUM PERKASA 42 48 -6 40 2

3. ELEKTRIKAL PT. CAHAYA TEKNINDO MAJUMANDIRI 56 42 14 61 -5

4. TATA UDARA PT. CAHAYA HAFIS CONSTRUCTION 33 0 33 16 17

III BLOK C 2 - 2 1. PLUMBING PT. INNOTEK MEGAH INDONESIA 50 33 17 34 16

2. HYDRANT/SPRINKLER PT. CAHAYA TEKNINDO MAJUMANDIRI 56 30 26 45 11

3. ELEKTRIKAL PT. CAHAYA TEKNINDO MAJUMANDIRI 56 30 26 58 -2

4. TATA UDARA PT. PANATA BAYU 28 4 24 15 13

JUMLAH 554 335 219 427 127


Total Saat Ini
Rekapitulasi : Plumbing PT.Bintang Milenium Perkasa 66
Plumbing PT.Innotek Megah Indonesia 34
Pemadam Kebakaran PT.Bintang Milenium Perkasa 73
Elektrikal PT.Cahaya Teknindo Majumandiri 158
Tata Udara PT. Cahaya Hafis Construction 36
Tata Udara PT.Panata Bayu 15
N REALISASI TENAGA KERJA MEP
UMAH SUSUN TINGKAT TINGGI KEMAYORAN

KETERANGAN

- Tenaga kerja berkurang


19 Org setelah Cut Of
Tgl 18 Nov 16
- 48 Org dari Cut Of tgl.18
Nov 2016
RENCANA DAN REALISASI TENAGA KERJA MEP
PROYEK PEMBANGUNAN RUMAH SUSUN TINGKAT TINGGI KEMAYORAN
MINGGU KE : III ( JANUARI 2017 )

CUT OF 15 DES' 2016 UPDATE DEVIASI


NO BLOK/TOWER PEKERJAAN NAMA SUBKONT RENCANA REALISASI KURANG 1/16/2017 DARI
(-) RENCANA

I BLOK D 10 - 3 Tata Udara PT. CAHAYA HAFIS CONTRUCTION 42 42 0 28 -14

JUMLAH 42 42 0 28 -14

Total Saat Ini Jakarta, 15 Desem


Rekapitulasi : Tata Udara PT. Cahaya Hafis Contruction 28
REALISASI TENAGA KERJA MEP
UMAH SUSUN TINGKAT TINGGI KEMAYORAN

KETERANGAN

1. Pekerjaan Lt.1 s/d 3


belum bisa dilaksanakan
karna kondisi di lapangan
masih banya matrial dan
stager khususny LT.3
Lantai 1, masih banyak
keramik
Lt. 2 menunggu Acc
merk unit AC

2. Lt. 4 s/d 16, AC sudah


dilaksanakan on progress

Jakarta, 15 Desember 2016


RENCANA DAN REALISASI TENAGA KERJA MEP
PROYEK PEMBANGUNAN RUMAH SUSUN TINGKAT TINGGI
MINGGU KE : II ( DESEMBER 2016 )

CUT OF 18 NOV' 2016 CUT OF


NO BLOK/TOWER PEKERJAAN NAMA SUBKONT RENCANA REALISASI KURANG STATUS 11 DES'
(-) 2016 11

I BLOK D 10-2 1. PLUMBING PT BINTANG MILENIUM PERKASA 51 39 12 RENCANA 38 -


TOWER 3 REALISASI 35 -

2. HYDRANT/SPRINKLER PT BINTANG MILENIUM PERKASA 42 39 3 RENCANA 35 -


REALISASI 35 -

RENCANA 0
Sub Total Blok D10-2 Tower 3
REALISASI 0

II BLOK D 10-2 1. PLUMBING PT BINTANG MILENIUM PERKASA 51 29 22 RENCANA 51 -


TOWER 4 REALISASI 31 -

2. HYDRANT/SPRINKLER PT BINTANG MILENIUM PERKASA 42 48 -6 RENCANA 48 -


REALISASI 31 -

RENCANA 0
Sub Total Blok D10-2 Tower 4
REALISASI 0

PT. BINTANG MILENIUM PERKASA


REALISASI TENAGA KERJA MEP
MAH SUSUN TINGKAT TINGGI KEMAYORAN

RENCANA PENAMBAHAN TENAGA KERJA DEVIASI


DESEMBER 2016 TOTAL DARI KETERANGAN
12 13 14 15 16 17 18 RENCANA

- - - - - - - 35 - Jumlah pekerja belum


- -12 - - - - 23 -28 terpenuhi dari rencana.

- - - - - - - 35 - Jumlah pekerja belum


- -4 - - - - 31 -11 terpenuhi dari rencana.

0 0 0 0 0 0 0 70
-39
0 -16 0 0 0 0 0 54

- - - - - - 31 - Tenaga kerja berkurang


- 11 - - - - 42 -9 19 Org setelah Cut Of
Tgl 18 Nov 16
- - - - - - - 31 - 48 Org dari Cut Of tgl.18
- - - - - - 31 -11 Nov 2016

0 0 0 0 0 0 0 62
-20
0 11 0 0 0 0 0 73

Jakarta, 15 Desember 2016


PT WASKITA KARYA (Persero) Tbk.

( Emanuel . S )
Koordinator M.E.P