Professional Documents
Culture Documents
CH 09
CH 09
A Managerial Approach
Chapter 9
Resource Allocation
CRASH PROJECT
Cost
Crash
Normal
Duration
Direct Cost
Cost
Crash
Normal
Duration
Cost Slope
Cost Slope for any activity =
( crash cost normal cost ) ( crash duration normal duration ) This gives the cost per day of crashing a project.
Resource Loading
Resource loading describes the amounts of individual resources an existing schedule requires during specific time period. Resource loading gives a general understanding of the demands a project will make on a firms resources at each point in time.
Resource Loading
The action plan links the schedule directly to specific demands for resources The PERT/CPM network technique can be modified to generate time-phased resource requirements
Example
Activity A Predecessor Time 5 Resources 6
B
C D E
A
A B C,D
3
1 4 2
7
5 3 2
Resource Leveling
When there is a mismatch between what is required and what is made available, we need to give priority to some activities, postpone some activities or do the job in small lots. The ultimate objective would be to complete the project within the same cost and time constraints. For this purpose, we slip or split the activities within margin or slacks available.
Resource Leveling
Resource leveling aims to minimize the periodby-period variations in resource loading by
shifting tasks within their slack allowances without delaying the project.
The purpose is to create a smoother distribution of resource usage by shifting slack jobs.
Example
B & E activities are on the critical path. Moving them would increase the total duration beyond seven days.
Resource Splitting
Loeading
Leveling