Professional Documents
Culture Documents
Purpose
Illustrate how to develop a set of AsPlanned S-Curves from scheduling information and estimates developed sometime before actual construction operations begin. Review the conceptual design estimating process to the extent necessary to set the context.
Learning Objectives
Be able to construct an as-planned schedule of work and cost versus elapsed time from a typical (but simplified) construction project Gantt Chart.
Be able to plot and identify the as Planned SCurves best representing these schedules.
Assume: All labor, material and equipment cost estimates are available from the estimating process. Maximum Task overlap with a 1-day minimum delay on an early start schedule.
Daily Cost
100%
100%
100% 100%
Daily Work
Simplifying assumptions: All work is equally weighted where 1 day equals 1 unit of work. Daily work accomplished is NOT a function of daily cost.
100%
14%
21%
29%
36%
43%
50%
57%
64%
71%
79%
86%
89%
93%
96%
4%
7%
28
100%
16%
24%
32%
40%
47%
55%
63%
71%
82%
92%
96%
0%
1%
9%
693,000
54,000
54,000
54,000
54,000
54,000
54,000
54,000
54,000
54,000
75,000
75,000
25,000
25,000
1,000
4,000
1,000
1,000
For example, at the end of day 8 you plan to have completed 50% of the Work and to have spent 47% of the Budget.
Day 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Cost % Work % 0% 4% 1% 7% 9% 14% 16% 21% 24% 29% 32% 36% 40% 43% 47% 50% 55% 57% 63% 64% 71% 71% 82% 79% 92% 86% 96% 89% 100% 93% 100% 96% 100% 100%
Note: The relationship between the scales. There is a reason to make room for the As-Built S-Curves
Cummulative Cost
Schedule in Days
Cumulative Work
70%
140%
Exercise #2.4
Individually, using engineering paper, plot the S-Curves for these data, label the axes, the curves, and the plot. Turn in your work before you leave.
Day 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Cost % Work % 0% 4% 1% 7% 9% 14% 16% 21% 24% 29% 32% 36% 40% 43% 47% 50% 55% 57% 63% 64% 71% 71% 82% 79% 92% 86% 96% 89% 100% 93% 100% 96% 100% 100%