Professional Documents
Culture Documents
Presentation Plan
Site Selection Grading of Sites Development of Site Arrangement FEASIBILITY STUDY
21 December 2013
PMI Revision 00
Defining types and sizes of power plant: depends on type of fuel and its delivery method, capacity anticipated in next 5-7 years, area for fuel storage, cooling towers, switchyards, space needs for store yards, workshops etc, other factors to be considered are : Geology Water for Power Stations Coal for Power Station Transport Disposal of Effluents Transmission Climatic Conditions Proximity of Airfields Fisheries and Marine Life Personnel Requirement 21 December 2013 PMI Revision 00 3 Amenities
Site Selection
Site Selection
Defining the area from which site is to be selected; load center/ co-generation/green-field project etc. Charaterizing the siting area; for identifying water/road ways, existing transmission routes, fuel sources etc Defining exclusion area; based on national territory / parks, monuments etc Narrowing down the choice by reviewing the maps, photographs, hydrology data, vegetation, transportation access, transmission corridor, topography, geology, work force availability, waste disposal, environmental impact, etc.
21 December 2013
PMI Revision 00
21 December 2013
PMI Revision 00
21 December 2013
PMI Revision 00
21 December 2013
PMI Revision 00
21 December 2013
PMI Revision 00
COST COMPARISON
Major Utilities Comparative Installed entering/existing CPC Unit Cost Plant Access Road Rs X per m Railroad track road Rs X per m Natural gas pipe line Rs X per m Plant make up water pipeline Rs X per m Electrical Transmission line Rs 2.5 X per m Circulating water pipeline Rs 7.0 X per m Coal conveyer on ground Rs 10 X per m Coal conveyer overhead Rs 20 X per m
PMI Revision 00 9
21 December 2013
RADIAL CONCEPT
Electricity
Fuel
Water
21 December 2013
PMI Revision 00
10
SITE ARRANGEMENTS
Central Power Complex is centrally located. It offers optimum space for other main areas. It creates buffer space between CP and adjoining area. Cooling Tower position. Drift must not reach switchyard, coal storage area and should not reach CPC. Length should be minimum to cut costs. It should be minimum 350 m from switchyard and 250 m from CPC.
21 December 2013 PMI Revision 00 11
SITE ARRANGEMENTS
Coal storage It occupies large and level space. It should have 15-120 days of stored coal. Not to be far off from CPC to cut costs on account of costly conveyers. Appropriate rail delivery system, curves, gradients, length of train affects unloading point in / and storage area. Coal dust is not blown onto CPC or nearby property. Space around Coal storage area for a run-off pond.
21 December 2013 PMI Revision 00 12
SITE ARRANGEMENTS
Combustion Waste Sizing for life span for Bottom ash, fly ash, FGD wastes It occupies 10-20 % of total site area. If possible, return the ash to coal mine/land filling. Ground area must be lined to avoid seepage Run-off Pond to catch ash near storage space. Water storage It has to have 3-7 days water requirement.
21 December 2013 PMI Revision 00 13
21 December 2013
PMI Revision 00
14
INPUTS
Defined Capacity
Selected location
Type of Plant
Fuel availability
21 December 2013
PMI Revision 00
15
OUTPUTS
An optimised solution for Site Arrangement Configuration Selection of Engg. Equipment systems Manpower requirement Profit /loss Operating pattern
PMI Revision 00 16
21 December 2013
Feasibility study-Objectives
Feasibility study is not an end in itself;
It doesn't leads to an end ; It helps for reaching a conclusion that is a sound proposition.
21 December 2013
PMI Revision 00
17
VARIOUS ASPECTS
It considers all the activities that must take place for power generation, including Auxiliary operations. Storage of inputs including fuel, material etc Storage of outputs including waste material, byproducts etc. Housing for employees Training need Recreational facility Support facility
21 December 2013 PMI Revision 00 18
OEM Past experience from similar units Published data Consultants Development banks
These data must not be applied before proper conversion.
21 December 2013
PMI Revision 00
19
21 December 2013
PMI Revision 00
20
THANK YOU
21 December 2013
PMI Revision 00
21