Professional Documents
Culture Documents
EXIT
HAZARD STUDY
HAZAN
SAFETY AUDIT
DOW INDICES (HAZARD RANKING)
ACCIDENT ANALYSIS
HAZOP
HAZARD & OPERABILITY
SCENARIO DEVELOPMENT
QUANTITATIVE RISK ASSESSMENT (QRA)
EMERGENCY MANAGEMENT PLAN (EMP)
EIA
The above diagram of inter-relationships shows that there are there are four main areas of hazard study
namely : Hazard analysis (HAZA!" Hazard and Operability study (HAZOP!" #$enario development"
%uantitative &is' Assessment (%&A! and finally (mergen$y )anagement Plan (()P!* These inter-
relationships are more elaborated in the following diagram :
ADAPTED FROM GUIDELINES FOR HAZARDS EVALUATION PROCEDURES,
AMERICAN INSTITUTE OF CHEMICAL ENGINEERS, NEW YORK, 1985, P 1-9
ACCIDENT ANALYSIS
HAZARD IDENTIFICATION
SCENARIO DEVELOPMENT
SYSTEM DESCRIPTION
SAFETY AUDIT
DOW INDICES
HAZARD CHECK LIST
HAZAN
ACCIDENT PROBABILITY
ACCIDENT CONSEQUENCE
RISK DETERMINATION
RISK AND/OR HAZARD ACCEPTABILITY
BUILD AND/OR OPERATE
YES
NO
HAZOP
QRA
EMP
EIA
Persons needed:
'hairman
(cribe
Operations -epresentative+s,
.ocuments needed:
.esign /asis
P)".s
(cribe:
records proceedings,
prepares action lists after each session
Start on time
ll peers
!o "ad ideas
Safe environment
#veryone contri"utes
'requent "rea(s
Typical %&'()" @round >ules
EXIT
"upplementary @round >ules
EXIT
$iversity is good
%isten to others
6odes:+discrete location on the P+I, at which the process parameters are in'estigated
for de'iations,
&ines between ma5or pieces of e#uipment
*#uipment items +tan2s0vessels, columns, reactors,
Pac2ages +compressors, chemical in5ection,
?tilities0(ervices +Air, 6@, (team, .rains,Aents 4lare,
(ewers1!!,
9uidewords:+-imple words used to .ualify or .uantify the intention and to guide and
stimulate the process for identifying process ha/ards5
6o, 3ore, &ess, As well as, others 1
Applicable to the Parameter
.o not list the same :cause; twiceD develop it the first timeD
if a new :deviation; triggers some thoughts for additional
conse#uences of a previously developed scenario, go bac2
and revise the scenario
EXIT
Co&&on .eviations and %"eir
Causes
'low 1rong routing, "loc(age,
"lind flange left in, faulty
non-return valve, "urst
pipe, control valve,
isolation valve, pump or
vessel failure.
)artial "loc(age -filters.,
vessel or valves failing,
lea(s, loss of pump
efficiency.
!& 2ore than 3 pump
operating, reduced
delivery head, increased
suction pressure, other
routes, exchanger tu"e
lea(s.
)ressure 4pen to atmosphere. 5eneration of vacuum "y
pump drain out of
vessels, cooling or
condensation from
vapour or gas dissolving
in a liquid.
)ump&compressor
suction lines "loc(ed.
!& Surge, relief, lea(age
from 6) connection -lines
and flanges., thermal,
rate of pressurising lines.
,emperature !& 'reezing, loss of
pressure, loss of heating,
failed exchanger tu"es.
!& 'ouled cooler tu"es,
cooling water failure,
failed exchanger tu"es.
#xothermic reaction.
%evel #mpty tan(, vessel. 7ontrol valve failure,
manual error, pump out.
6igh or %ow interface
level.
7ontrol valve failure,
manual error, "loc(ed
outlet.
7omposition 8 viscosity,
density, phase
2ixing failure. dditive
-e.g. chemical in+ection.
failure.
)oor mixing, or
interruption during mixing.
)assing through
isolations, lea(ing
exchanger tu"es, phase
change, out of spec.
#xcessive additives,
mixing.
5uide 1ords
)rocess )arameters
!o, !ot, !one %ess, %ow, Short )art of 2ore, 6igh
EXIT
.evelop /Conse0uences1
wit"out /Sa2e$uards1
.esign "ntent
4perations
2aintenance
/nspection
,esting
EXIT
Priority 2or Sa2e$uards (cont.)
%raining
History
*#uipment
)S=s
7ontrol instruments
EXIT
3ualitatively 4sti&atin$ ,is5
S6,
> ? ris( is an assessment of how serious and
how credi"le is each identified deviation, its
causes and consequences@ a com"ination of the
li(elihood and the severity of the predicted or
ultimate consequences
> ? S A %
S ? ,he severity of the predicted consequences
% ? ,he li(elihood of the predicted
consequences developing given the safeguards
that are currently in place
EXIT
(*A*-" %E = 4" A* PO" 6% ('H*3* 4O- (*A*-" %E &*A*&
'lass .efinition
F A High " n plant fatalityD Public fatalitiesD *tensive
property damageD environmental damageD
*tended downtime + G or B @ days ,
@ High &ost time in5 uryD Public in5 uries or public
impactD (ignificant property damageD *ceeds
3*PA standardsD .owntime + F to @ days ,
H 3edium 3inor in5 uryD 3oderate property damageD 6o
environmental impactD .owntime + I to @I
hours , D Off=spec product
I &ow 6o wor2er in5 uriesD 3inor property damageD
6o environmental impactD .owntime + J I
hours ,
K A &ow 6o wor2er in5 uriesD 6o property damageD 6o
environmental impactD -ecoverable
operational problem
&" >*&" HOO. = 4" A* PO" 6% ('H*3* 4O- &" >*&" HOO.
'lass 4re#uency of Occurrence
F A High Possible to occur + J K years ,
@ High Possible to occur + K J FK years ,
H 3edium Possible to occur under unusual circumstances
+ FK J HL years ,
I &ow Possible to occur over the lifetime of the plant
+ HL J FLL years,
K A &ow 'ould occur, however not li2ely over plant life
+ F 0 FLL years,
S"6"*%$2
1 = > ? 5
1 1 = > ? 5
= = ? @ A 8
L%4"'%+--1 > > @ A 8 9
? ? A 8 9 1B
5 5 8 9 1B 1B
-"(> -A6>"69 3A%-"M
EXIT
HA!PS Study "ethodology
In simple terms( the 1A2OP study process in'ol'es applying in a
systematic way all rele'ant eyword combinations to the plant in
.uestion in an effort to unco'er potential problems. #he results are
recorded in columnar format under the following headings:
EXIT
DEVIATION CAUSE CONSECUENCE SAFEGUARDS ACTION
I! .-!#%1"*%!0 $+" %!(-*3&$%-! $- 7" *".-*1"1 %! "&.+ -( $+"#"
.-')3!#, %$ 3&2 7" +"',()' $- $&4" &# &! ":&3,'" $+" (-''-5%!0
#%3,'" #.+"3&$%.8
HA!PS Study "ethodology
EXIT
"ote that this is purely representational, and not intended to illustrate an actual
system
M%:"*
P)3, P1
.osing
%an2 %F
S$*&%!"* S1
AF
P;
HAZOPS Study 7et"odolo$y (Contd.)
EXIT
$eviation
,he (eyword com"ination "eing applied -e.g.
'low&!o..
7ause
)otential causes which would result in the deviation
occurring. -e.g. "-trainer -3 blocage due to
impurities in ,osing #an #3" might "e a cause of
'low&!o..
7onsequence
,he consequences which would arise, "oth from the
effect of the deviation -e.g. 4"oss of dosing results in
incomplete separation in 53". and, if appropriate,
from the cause itself -e.g. 4Ca'itation in Pump P3(
with possible damage if prolonged4..
HAZOPS Study 7et"odolo$y (Contd.)
EXIT
(afeguards
ny existing protective devices which either prevent
the cause or safeguard against the adverse
consequences would "e recorded in this column. 'or
example, you may consider recording ""ocal pressure
gauge in discharge from pump might indicate problem
was arising".
!ote that safeguards need not "e restricted to hardwareB where
appropriate, credit can "e ta(en for procedural aspects such as
regular plant inspections -if you are sure that they will actually "e
carried outC..
Action
ctions fall into two groups<
3. ctions that remove the cause.
D. ctions that mitigate or eliminate the consequences.
HAZOPS Study 7et"odolo$y (Contd.)
EXIT
D& (&) !""&. ! %/!0!) 2)-(3 )& d*"&/, with two team members
conversing in low voices at the corner of the table8
E!#)*" $+&$ !"" )!2 22+0% /!0)-,-/!), "6"! $+-#" 5+- 3%0+$ (""'
)!#)*" -( $+"3#"'6"#8
R,&3(-7 !(d 0.!0d 5%$+ ,*&%#" $+" $"&3 3"37"*/# 5+- .-!$*%7)$"
$- $+" 1%#.)##%-! 5+-'"+"&*$"1'2 &!1 #"!#%7'28 However, do not allow
them to overshadow the rest of the team8
,8**I*) A HAZOP S%8.9 (Contd.)
EXIT
T+" C+&%*3&! #+-)'1 7" %!1","!1"!$ &!1 )!7%&#"1, &!1 #+-)'1 !-$ 7"
,"*."%6"1 &# .-!#$&!$'2 (&6-*%!0 -!" #".$%-! -( $+" $"&3 &# -,,-#"1 $-
&!-$+"*
T&4" &# &! ":&3,'" $+" #%$)&$%-! 5+"*" $+" .'%"!$ 5%#+"# $- +&6" &! &11%$%-!&' H-3$ L*" A"!02, 7)$ $+"
.-!$*&.$-* #$*-!0'2 1%#,)$"# %$# !"."##%$28 C-!#%1"* $+" (-''-5%!0 &.$%-!#9
GF%$ & H%0+ L"6"' A'&*3G8 I! $+" 6%"5 -( $+" .-!$*&.$-*, $+" C+&%*3&! +&# #%1"1 5%$+ $+" .'%"!$8 H" 3&2,
5*-!0'2 -* -$+"*5%#", ,"*."%6" $+%# $- 7" & 7%&#"1 1".%#%-!8
T+" &.$%-! GH)#$%(2 $+" *"/)%*"3"!$ (-* & H%0+ L"6"' A'&*3G %# &11*"##"1 $- $+" client8 T+" C+&%*3&!
(&6-*# $+" .-!$*&.$-*I# &*0)3"!$, 7)$ %# !-$ 1%#3%##%!0 &'$-0"$+"* $+" 6%"5# -( $+" .'%"!$8 B-$+ ,&*$%"# &*"
'%4"'2 $- 7" .-!$"!$ 5%$+ $+%# (-*3)'&8
T+" &.$%-! GH)#$%(2 $+" &7#"!." -( & H%0+ L"6"' A'&*3G %# &11*"##"1 $- $+" contractor. T+" C+&%*3&!
(&6-*# $+" .'%"!$I# &*0)3"!$, 7)$ %# !-$ 1%#3%##%!0 &'$-0"$+"* $+" 6%"5# -( $+" .-!$*&.$-*8 A# 7"(-*", !"%$+"*
,&*$2 5%'' +&6" .&)#" $- (""' &00*%"6"18
%"e ,eport
EXIT
The HA!P #e$ort is a key document pertaining to the safety of the plant
't is crucial that the benefit of this e,pert study is easily accessible and
comprehensible for future reference in case the need arises to alter the
plant or its operating conditions
T+" 3&E-* ,&*$ -( #).+ & *",-*$ %# $+" $rinted "inutes, %! 5+%.+ %# '%#$"1
$+" $"&3 3"37"*#, 3""$%!0 1&$"#, K"25-*1# &,,'%"1, &!1 "6"*2 1"$&%' -(
$+" #$)12 $"&3# (%!1%!0#8
H-5"6"*, 5%$+ $+%# %# %!.')1"1 & 0"!"*&' summary8 T+" .-!$"!$# -( #).+ &
#)33&*2 3%0+$ $2,%.&''2 7"9
-
A! -)$'%!" -( $+" $"*3# -( *"("*"!." &!1 $+" #.-," -( #$)12
-
A 6"*2 7*%"( 1"#.*%,$%-! -( $+" ,*-."## 5+%.+ 5&# #$)1%"1
-
T+" ,*-."1)*"# &!1 ,*-$-.-' "3,'-2"18
-
A 7*%"( 1"#.*%,$%-! -( $+" A.$%-! F%'" #+-)'1 7" %!.')1"1
-
G"!"*&' .-33"!$#
-
R"#)'$#8 Dusually states the number of recommended actionsF
-
A,,"!1%: Dmaster copies of dwgs, studied, tech data used, cals produced,
)&* charts, corr bet contractor to vendor, or client to contractor etc F
S"'".$ & N-1" S"'".$ & N-1"
E:,'&%! E:,'&%!
1"#%0! %!$"!$ 1"#%0! %!$"!$
S"'".$ P*-."## S"'".$ P*-."##
P&*&3"$"* P&*&3"$"*
A,,'2 A,,'2
G)%1"5-*1# G)%1"5-*1#
I1"!$%(2 I1"!$%(2
.*"1%7'" .*"1%7'"
D"6%&$%-!# D"6%&$%-!#
I1"!$%(2 I1"!$%(2
.*"1%7'" .*"1%7'"
C&)#"# C&)#"#
E:&3%!" E:&3%!"
C-!#"/)"!."# C-!#"/)"!."#
I1"!$%(2 I1"!$%(2
":%#$%!0 ":%#$%!0
S&("0)&*1# S&("0)&*1#
A##"## R%#4 A##"## R%#4
D"6"'-, D"6"'-,
R".-33"!1"1 R".-33"!1"1
A.$%-!# A.$%-!#
R","&$ (-* &'' R","&$ (-* &''
G)%1"5-*1# G)%1"5-*1#
R","&$ (-* &'' R","&$ (-* &''
P&*&3"$"*# P&*&3"$"*#
R","&$ (-* &'' R","&$ (-* &''
N-1"# N-1"#
HAZOP 3ethod 4low 'hart
HAZOP 3ethod 4low 'hart
EXIT
HAZOP : .*%A"&*. (*N?*6'* O4 *MA3"6A%"O6 HAZOP : .*%A"&*. (*N?*6'* O4 *MA3"6A%"O6
21(3>T"EB? 1hemical Industry "afety and %ealth 1ouncil, +,CC/D5 21(3>T"EB? 1hemical Industry "afety and %ealth 1ouncil, +,CC/D5
Mark vessel as
completed
Repeat 1-22 for all vessels
on flow sheet
1
Beginning
Select a vessel
2
3
4
5
6
!
"
#$plain the general intention of the
vessel and its lines
Select a line
#$plain the intention of the
line
%ppl& the first g'ide words
(evelop a meaningf'l deviation
#$amine )ossi*le ca'ses
#$amine +onse,'ences
(etect -a.ards
1/ Make s'ita*le record
11
Repeat 6-1/ for all meaningf'l deviations
derived from the first g'ide words
12
13
14
15
16
1
1!
1"
Repeat 5-11 for all the g'ide words
Repeat 3013 for each line
Select an a'$iliar& 1e2g2
heating s&stem3
#$plain the intention of the
a'$iliar&
Repeat 5-12 for a'$iliar&
Mark a'$iliar& as having
e$amined
Repeat 5-1! for all
a'$iliaries
2/
#$plain intention of the vessel
Mark line as having *een e$amined
11
Repeat 5-12
12
13
14
15
Mark flow sheet as
completed
Repeat 1-24 for
all flow sheets
#nd
EXIT
HA!P Procedure: %low diagram
EXIT
S"'".$ & #".$%-! -( $+" P'&!$
H&6" &'' $+" *"'"6&!$ P*%3&*2 K"25-*1# (-* $+%# ,'&!$ #".$%-! 7""! .-!#%1"*"1 J
S"'".$ & P*%3&*2 K"25-*1 !-$ ,*"6%-)#'2 .-!#%1"*"18 D"808 ,*"##)*"F
H&6" &'' $+" *"'"6&!$ S".-!1&*2 K"25-*1# (-* $+%# P*%3&*2 K"25-*1 7""! .-!#%1"*"1 J
S"'".$ & S".-!1&*2 K"25-*1 !-$ ,*"6%-)#'2 .-!#%1"*"18 D"808 M-*"F
A*" $+"*" &!2 .&)#"# (-* $+%# 1"6%&$%-!# !-$ ,*"6%-)#'2
1%#.)##"1 &!1 *".-*1"1 J
N-
N-
N-
Y"#
Y"#
Y"#
R".-*1 $+%# !"5 .&)#"8
A*" &##-.%&$"1 .-!#"/)"!." -( &!2 #%0!%(%.&!."J
N-
Y"#
R".-*1 $+" .-!#"/)"!."/#
R".-*1 &!2 S&("0)&*1# %1"!$%(%"18
H&6%!0 *"0&*1 $- $+" C-!#"/)"!."# &!1 S&("0)&*1#, %# &! &.$%-! !"."##&*2J
R".-*1 $+" &0*""1 &.$%-!
Y"#
N-
&he reasons 'or such wides$read use o'
HA!PS
<hough no statistics are available to verify the
claim, it is believed that the %&'() methodology
is perhaps the most *idely used aid to loss
prevention$ The reason for this can most probably
be summarized as follo*s?
It is easy to learn$