Professional Documents
Culture Documents
Purpose
Illustrate how to develop a set of AsPlanned S-Curves from scheduling
information and estimates
developed sometime before actual
construction operations begin.
Review the conceptual design
estimating process to the extent
necessary to set the context.
Learning Objectives
Be able to construct an as-planned
schedule of work and cost versus
elapsed time from a typical (but
simplified) construction project Gantt
Chart.
Be able to plot and identify the as
Planned S-Curves best representing
these schedules.
Example Construction
Project
The project is to reconstruct 2-miles of
park access road conforming to Texas
FM-Road standards. This involves the
following tasks:
1.
2.
3.
4.
#2.1 on Construction
Methods.
Ask Selected Individuals or Pairs to
answer the following:
What is Base Material and what is its
purpose in the design of the road?
How is the Base built?
What is shoot and chip?
What is Pea Gravel?
What is the design profile of a FM Road?
Days
1
10
11
4
2
$$/Day
1,000
3,500
51,000
25,000
1,000
Assume:
All labor, material and equipment cost estimates
are available from the estimating process.
Maximum Task overlap with a 1-day minimum
delay on an early start schedule.
Assumed Estimating
Process
The entire project is broken into Work Packages (work
breakdown structure): build base, shoot and chip, etc.
Estimated unit quantities for each work package are
calculated from the plans and specifications at an
appropriate level of detail.
The corresponding unit prices and productivity rates are
obtained from historical data We will use the R. S.
Means manual in this class.
Work Package (or Task or Activity) durations and costs
are derived from the historical data as applied to the
estimates.
These data serve as inputs to the scheduling process
which result in Bar-Charts similar to the one on the next
slide.
10 11 12 13 14 15 16 17
S
B
S
B
S
B
S
B
S
B
S
B
S
B
S
B
B
S
B
S
100%
100%
100%
100%
28
93%
96%
100%
100%
1,000
96%
1
89%
25,000
92%
2
86%
25,000
82%
2
79%
75,000
71%
2
71%
75,000
63%
2
64%
54,000
55%
2
57%
54,000
47%
2
50%
54,000
40%
2
43%
54,000
32%
2
36%
54,000
24%
2
29%
54,000
16%
2
21%
54,000
9%
2
14%
54,000
1%
1
7%
54,000
0%
4,000
1,000
693,000
S
B
1,000
1
M
4%
Cumulative
Cost in $$'s
ES
1
2
3
12
16
Cummulativ
e Work Units
$$/Day
$ 1,000
$ 4,000
$ 50,000
$ 25,000
$ 1,000
Daily Cost
Days
1
10
11
4
2
Daily Work
Task
M
S
B
S
D
all this
Imply?
The relationship
between time and cost
and time and work.
For example, at the
end of day 8 you plan
to have completed
50% of the Work and to
have spent 47% of the
Budget.
Day
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Cost % Work %
0%
4%
1%
7%
9%
14%
16%
21%
24%
29%
32%
36%
40%
43%
47%
50%
55%
57%
63%
64%
71%
71%
82%
79%
92%
86%
96%
89%
100%
93%
100%
96%
100%
100%
Corresponding As-Planned
S-Curves
100%
200%
90%
180%
80%
160%
70%
140%
60%
120%
50%
100%
40%
80%
30%
60%
20%
40%
10%
20%
0%
0%
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Schedule in Days
Cumulative Work
Note: The
relationship
between
the scales.
There is a
reason
to make
room for
the
As-Built
S-Curves
Cummulative Cost
As Planned S-Curves
Exercise #2.4
Individually, using
engineering paper,
plot the S-Curves
for these data,
label the axes, the
curves, and the
plot.
Turn in your work
before you leave.
Day
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Cost % Work %
0%
4%
1%
7%
9%
14%
16%
21%
24%
29%
32%
36%
40%
43%
47%
50%
55%
57%
63%
64%
71%
71%
82%
79%
92%
86%
96%
89%
100%
93%
100%
96%
100%
100%
Module Assessment
Question
If you had to ask a question about
this topic, what would it be?