You are on page 1of 37

Managing Geotechnical Risk

Are we learning from the failures


The Use of Instrumentation and Monitoring to Verify

Design and Control Construction of Deep


Excavations (modified)
Andy Pickles
of
GCG (Asia) Ltd.

As

Overview of Presentation
Presentation relates to deep excavation for major
infrastructure projects

Risk in design and role of instrumentation

Typical scope and cost of instrumentation

Obtaining added value (reducing risk) from instrumentation

Interpretation of instrumentation

As

Risk in Design of Deep Excavations


Instrumentation is associated with the management of
risk (i.e. uncertainties). These include:

Soil stratigraphy

Geotechnical design parameters

Construction related factors


As

Uncertainty of Soil Stratigraphy


Variation of Continuity of Sand Layer
Discontinuous Layer

As

Continuous Layer

Uncertainty in Design Parameters - 1


Deep Excavation in Clay

4
0

FIL
L

0
-4

-4

Soft CLAY

-8

-12
-16
-20

40

75

-24

Stiff CLAY

Clayey SAND

-28
-32

As

-36

Reduced level (m)_

Reduced level (m)_

-8

-12
-16
-20

Final exc

Bend Mom
2800 kNm

5000 kNm

-24
-28

Strength_1
Strength_2

Hard CLAY

Strength_1
Strength_2

-32
-36

0.240

0.200

80 100 120 140 160

0.160

60

0.120

40

0.080

20

0.000

0.040

Wall horizontal disp. (m)

Undrained shear strength, cu (kPa)

Uncertainties in Design Parameters 2


Variation of Rate of Softening
Low Permeability

As

High Permeability

Construction Related Uncertainties -1


Performance of Grout Cut-off

CLAY

As

Construction Related Uncertainties - 2

Ground settlement on wall installation

Effectiveness and extent of dewatering

Properties of jet grout layers

Effectiveness of ground treatment

Effects of previous construction work

Interaction with adjacent structures

As

Instrumentation to deal with these risks

All design approaches

Routine design approach

Observational approach (progressive modification)

Design parameters from previous experience


Determined from instrumentation results

Offset risk by using conservative assumptions


Verify design using instrumentation results (AAA)

Manage risk through engineering input


Less conservative assumptions
Continuous improvement of design based on instrumentation results
As knowledge improves design improves and risk remains constant.

As

Trigger Levels in Routine Design

Trigger levels are used as part of the AAA system

Important to distinguish between trigger levels set using the design


predictions, on the basis of additional calculation and based on engineering
judgement

Design predictions are unreliable and AAA value requires a design review, if
appropriate AAA values can be updated

Additional calculation is based on actual serviceability and AAA values


should not be exceeded

Engineering judgement are often guesses or best practice and more detailed
analysis is then required and AAA values can be revised

As

10

Managing Risk and Obtaining Value

If the major role of instrumentation is to manage risk how


can we make it more effective?

Alternatively, how can we get more value out of


instrumentation?

As

11

The Role of Instrumentation

Routine design and construction

0%

To verify an already conservative design

Observational approach
Use data to continually improve design
Reduce construction costs
Save construction time

Long term perspective


Full interpretation published with all background
information allows future designs to be improved
Benefits accrued by major clients

As

10%
12

I
N
C
R
E
A
S
I
N
G

V
A
L
U
E

Typical Scope of Standard Instrumentation


Standard instrument
type

1 km cut and cover


with station in
Singapore

1 km cut and cover


with station in
Hong Kong

Inclinometers in walls

120

50

Strut load monitoring

400

200

Piezometers
(VW and standpipe)

50

120

Settlement points

800

500

Extensometers

10

15

As

13

Scope of Data Collection

Typically 1000 to 2000 separate instruments

Readings required daily during excavation and strut


removal stages and weekly at other times

Typically of the order of 200 readings per instrument

400,000 separate sets of readings

1,000,000 or more data points

As

14

Typical cost of instrumentation


Cost of instrumentation and
monitoring

1.5% to 2% of contract value

Management cost (engineering


support, meetings etc.)

0.5% to 1% of contract value

Total cost

2% to 3% of contract value

Cost includes
Instrumentation
Monitoring teams (instrumentation and survey)
Engineering support to coordinate work
Development and maintenance of database
Daily, weekly and monthly reporting with associated meeting costs

As

15

Cost of Instrumentation Routine Design

Total cost for routine instrumentation of a deep excavation contract is S$ 5


to 10 million

Primary use is to verify the design of the excavation works

Cost is of similar order to the original design costs (i.e. pay as much to verify
as to design)

Instrumentation is often seen as an onerous contract requirement

No added value obtained from instrumentation

Designer is often not closely involved with construction

As

16

How to Add Value to Instrumentation

Adding value is reducing risk and reducing cost

Involve designer in the construction work

Prepare good quality instrumentation interpretative reports


(comprehensive rather than instrument specific)

Carry out back analyses to determine actual performance parameters

Encourage value engineering through observational approach

Publish results and improve standards and codes of practice

As

17

Cost of Adding Value to Instrumentation

Additional cost for proper interpretation of results and


associated report is S$ 0.1 million

Additional cost for back analysis in order to obtain useful


design data for future work is S$ 0.1 to 0.2 million

Large savings in Contract costs and times are achievable


by making better use of monitoring data

Additional costs can usually be offset by better control of


day to day monitoring (i.e. cut down frequency)

As

18

Examples of Excessive Monitoring


Manual Settlement Readings
Jan 00

Nov 01
-5

-15
0

As

-120

19

Groundwater Level mPD

Examples of Excessive Monitoring


Manual Piezometer Readings

As

18 Months with 500 Measurements


20

Examples of Excessive Monitoring


Datalog Piezometer Readings
Tide Gauge

Groundwater Level mPD

1 Day

Piezometer

As

21

Examples of Excessive Monitoring


Datalogged Piezometer Readings
Jan 00

Nov 01
-5

-15
2.5

-1.5

As

22

Monitoring Frequency, Value and Risk

My experience approximately 50% of monitoring is unnecessary.

Obtained because nobody is reviewing the data.

Extra value can be obtained without additional cost by better control


of instrumentation

Better value is associated with reduced risk

Additional value can be obtained through


Use of Observational Approach (Progressive Modification)
Adoption of updated design codes (e.g. CIRIA C580)
Feeding back information to future contracts

As

23

Proposal for Increasing Value of Instrumentation

Use of Observational Method can achieve substantial cost savings


and more importantly time savings (e.g. Powderham, Nicolson)

Adoption of CIRIA C580 which makes more use of instrumentation


and can reduce cost of Dwalls by approximately 5% (Sze and Chan
2005)

Scope for reducing factor of safety or load factor by 10%

Paper to ICDE 2006 proposes adoption of C580 with improved


instrumentation as an interim measure. Better use of
instrumentation, involvement of designer and more widespread
adoption of Observational Approach.

As

24

Comment on Interpretation of Instrumentation


The 4 Basic Steps

1. Baseline readings and background trends must be


established (daily rainfall, seasonal rainfall, tide,
temperature etc.)

2. Construction records are critical to data interpretation


3. Instrumentation results must be correlated against
baseline trends and construction history

4. Analysis and presentation of data must consider cause


and effect
As

25

Establish Baseline Trend

X
Maximum
Allowable
Water
Drawdown
Is 1m

Movement of
Viaduct Structure

40 m

As

Alert = 10 mm
Action = 15 mm
Alarm = 20 mm

26

Establish Baseline Trend 1


Movement of Bypass Pier Head
50

X-dir

Feb 01
40 mm

-30
20

JunJuly
00 00

Oct 01

Y-dir

18 mm

As

27

Establish Baseline Trend 1


Movement of Bypass
50

X-dir

40 mm

-30
20

JunJuly
00 00

July Oct
01 01

Y-dir

18 mm

As

28

Establish Baseline Trend 2


Variation of Groundwater Level

Groundwater Level mPD

Jan 00
0

As

July 00

Jan 01

July 01

29

Construction Records Tabulated Data


Pile No.

Inclination

Drilling
Start Date

Drilling
Completion
Date

Casing Top
Level (for
R.H.)

Length of
Casing

(mPD)

(mPD)

(m)

MP33A-1

14-Jul-05

14-Jul-05

6.800

7.060

21.66

MP33A-2

26-Jul-05

26-Jul-05

6.800

7.119

21.60

MP33A-3

03-Aug-05

04-Aug-05

6.800

7.030

21.54

MP33A-4

22-Aug-05

23-Aug-05

6.800

7.000

20.13

MP33A-5

05-Sep-05

06-Sep-05

6.800

7.037

20.45

MP33A-6

18-Jul-05

19-Jul-05

6.800

6.942

20.53

09-Aug-05

17-Aug-05

6.800

6.892

20.15

27-Jul-05

27-Jul-05

6.800

7.104

20.97

MP33A-9

02-Aug-05

03-Aug-05

6.800

7.151

20.94

MP33A-10

16-Jul-05

16-Jul-05

6.800

6.989

20.94

MP33A-11

05-Sep-05

05-Sep-05

6.800

7.051

19.9

MP33A-12

15-Jul-05

15-Jul-05

6.800

7.028

20.32

MP33A-13

08-Aug-05

09-Aug-05

6.800

7.015

20.21

MP33A-14

29-Aug-05

30-Aug-05

6.800

6.884

MP33A-7
MP33A-8

As

Cap Mark

Ground
Level

MP33A

30

19.78

Construction Records - Environmental

As

31

Construction Records Progress Summaries

As

32

Construction Records - Photographs

3 March 2002

As

33

Correlate Response to Construction Activities


Cause and Effect Plots
Jan 00
Excavation level (mPD)

Nov 01

-5

-15
0

Settlement (mm)
-120
50

Inclinometer (mm)
+2.5

Piezometer (mPD)

As

-1.5

34

Correlate Response to Construction Activities


and Baseline Trends
Tidal Response

Groundwater Level mPD

+2

Rainfall Control
Start Dewatering
Stop Dewatering

+1

0
Complete Dwall

-1

-2

As

Jan 00

July 00

Jan 01

July 01

35

Summary

The primary purpose of instrumentation is to manage risk

Risk arises due to uncertainties in ground engineering

Designer is aware of uncertainties so should be involved in construction (i.e.


continuity) but is often excluded

Much instrumentation is wasted, not enough engineering input

Reduced costs and reduced risk (i.e. added value) can be obtained by better
use of instrumentation

Requires good quality interpretation of data and reporting to manage the


risks

As

36

End of Presentation
Thank you

As

37

You might also like