Professional Documents
Culture Documents
Part 4
Part 4
As
Overview of Presentation
Presentation relates to deep excavation for major
infrastructure projects
Interpretation of instrumentation
As
Soil stratigraphy
As
Continuous Layer
4
0
FIL
L
0
-4
-4
Soft CLAY
-8
-12
-16
-20
40
75
-24
Stiff CLAY
Clayey SAND
-28
-32
As
-36
-8
-12
-16
-20
Final exc
Bend Mom
2800 kNm
5000 kNm
-24
-28
Strength_1
Strength_2
Hard CLAY
Strength_1
Strength_2
-32
-36
0.240
0.200
0.160
60
0.120
40
0.080
20
0.000
0.040
As
High Permeability
CLAY
As
As
As
Design predictions are unreliable and AAA value requires a design review, if
appropriate AAA values can be updated
Engineering judgement are often guesses or best practice and more detailed
analysis is then required and AAA values can be revised
As
10
As
11
0%
Observational approach
Use data to continually improve design
Reduce construction costs
Save construction time
As
10%
12
I
N
C
R
E
A
S
I
N
G
V
A
L
U
E
Inclinometers in walls
120
50
400
200
Piezometers
(VW and standpipe)
50
120
Settlement points
800
500
Extensometers
10
15
As
13
As
14
Total cost
2% to 3% of contract value
Cost includes
Instrumentation
Monitoring teams (instrumentation and survey)
Engineering support to coordinate work
Development and maintenance of database
Daily, weekly and monthly reporting with associated meeting costs
As
15
Cost is of similar order to the original design costs (i.e. pay as much to verify
as to design)
As
16
As
17
As
18
Nov 01
-5
-15
0
As
-120
19
As
1 Day
Piezometer
As
21
Nov 01
-5
-15
2.5
-1.5
As
22
As
23
As
24
25
X
Maximum
Allowable
Water
Drawdown
Is 1m
Movement of
Viaduct Structure
40 m
As
Alert = 10 mm
Action = 15 mm
Alarm = 20 mm
26
X-dir
Feb 01
40 mm
-30
20
JunJuly
00 00
Oct 01
Y-dir
18 mm
As
27
X-dir
40 mm
-30
20
JunJuly
00 00
July Oct
01 01
Y-dir
18 mm
As
28
Jan 00
0
As
July 00
Jan 01
July 01
29
Inclination
Drilling
Start Date
Drilling
Completion
Date
Casing Top
Level (for
R.H.)
Length of
Casing
(mPD)
(mPD)
(m)
MP33A-1
14-Jul-05
14-Jul-05
6.800
7.060
21.66
MP33A-2
26-Jul-05
26-Jul-05
6.800
7.119
21.60
MP33A-3
03-Aug-05
04-Aug-05
6.800
7.030
21.54
MP33A-4
22-Aug-05
23-Aug-05
6.800
7.000
20.13
MP33A-5
05-Sep-05
06-Sep-05
6.800
7.037
20.45
MP33A-6
18-Jul-05
19-Jul-05
6.800
6.942
20.53
09-Aug-05
17-Aug-05
6.800
6.892
20.15
27-Jul-05
27-Jul-05
6.800
7.104
20.97
MP33A-9
02-Aug-05
03-Aug-05
6.800
7.151
20.94
MP33A-10
16-Jul-05
16-Jul-05
6.800
6.989
20.94
MP33A-11
05-Sep-05
05-Sep-05
6.800
7.051
19.9
MP33A-12
15-Jul-05
15-Jul-05
6.800
7.028
20.32
MP33A-13
08-Aug-05
09-Aug-05
6.800
7.015
20.21
MP33A-14
29-Aug-05
30-Aug-05
6.800
6.884
MP33A-7
MP33A-8
As
Cap Mark
Ground
Level
MP33A
30
19.78
As
31
As
32
3 March 2002
As
33
Nov 01
-5
-15
0
Settlement (mm)
-120
50
Inclinometer (mm)
+2.5
Piezometer (mPD)
As
-1.5
34
+2
Rainfall Control
Start Dewatering
Stop Dewatering
+1
0
Complete Dwall
-1
-2
As
Jan 00
July 00
Jan 01
July 01
35
Summary
Reduced costs and reduced risk (i.e. added value) can be obtained by better
use of instrumentation
As
36
End of Presentation
Thank you
As
37