Professional Documents
Culture Documents
Asset Management Council 1005 Maintenance Execution and Shutdowns Best Practice
Asset Management Council 1005 Maintenance Execution and Shutdowns Best Practice
Lindsay Cameron
Planning Superintendent
Fluor Shell Maintenance
Alliance
Shell Geelong Refinery
LINDSAY CAMERON WORK
HISTORY
Lindsay Cameron is a Mechanical Engineer
with a Bachelor of Engineering degree from
Queensland Institute of Technology and a MBA
from Melbourne University
Lindsay Cameron has worked in maintenance
planning and shutdowns for Shell, BlueScope
Steel, Western Mining, QENOS, Anaconda
Nickel, & Port Kembla Copper for over 20
years.
In addition, he has worked on various SAP
implementations while working for Deloitte
Consulting (including AGL, Pasminco,
Transfield, & Telstra).
He specializes in Planning & Scheduling
systems such as SAP & Primavera.
Lindsay currently works for Fluor Operations
& Maintenance as the Planning
Superintendent for the Shell Geelong Refinery.
His interests are family, cycling, motor racing,
& the stock market/real estate investing.
AGENDA
Introduction
The Importance of Maintenance
Execution
Maintenance Execution process steps
Maintenance Workflow
Maintenance Events
Shutdowns Process
Worked Example (Risk Analysis)
Questions
THE IMPORTANCE OF
MAINTENANCE EXECUTION
GOOD MAINTENANCE IS
GOOD SAFETY
New legislative
requirements
Increased stakeholder
scrutiny of safety
performance
Risk Management
strategies
ZERO HARM
Good Safety is Good 1947 Texas City Explosion
Business 145 Shift Workers killed in
Monsanto Plant from
explosion in nearby wharf
MAINTENANCE EXECUTION
What is Maintenance Execution?
Integrated process covering:
Job Screening (including Risk & Priority)
Scoping (what to do)
Planning (how to do it)
Scheduling (when to do it)
Execution (doing it)
Close-out
JOB SCREENING
Identify the work required
CMMS system (SAP Notifications)
Can be raised by anybody
Review the Notifications
Done by somebody who understands business risk
Determine the business risk
Consequence & Probability
People, Assets, Environment, & Reputation
Convert Business Risk to Priority
Determine required End Date for work & drive
Maintenance Execution to achieve this end date
Assign to personnel to Scope & Plan work
SCOPING
What are you going to do?
Replace
Repair
Patch up
Defer work
Do nothing
Identify duplicate jobs (or similar work)
Developed by Subject Matter Experts
Cost considerations must be accounted for
Operational Constraints (production requirements,
statutory requirements, resource availability, etc)
PLANNING
How are you going to do the work?
Basic requirements:
Job Tasks, Steps, Duration, & Sequence
Resources
People
Materials
Tools
Equipment
Cost Estimate
Risk Assessment (PPA)
Safety Requirements (JSA/JHA)
SCHEDULING
When you are going to do the work?
Scheduling involves several key plant
stakeholders
Supervisors (own the labour & equipment resources)
Operations (own the plant)
Scheduler (builds the schedule)
Warehouse (owns the materials)
Someone must own the Schedule (senior
role)
Cyclic process (usually weekly)
Separate roles for Planning & Scheduling
EXECUTION
Do the work
Do the work you say you are going to do
Do it when you say you are going to do it
Like taking your car in for a service
Measure performance by KPIs
Schedule Attainment
PM Compliance
Orders completed by required end date
Ownership of KPIs is at the appropriate stakeholder
NOT the Planner (or Scheduler)
Schedule Attainment Supervisor
PM Compliance Maintenance Engineer
Orders by End Date Maintenance Engineer
CLOSE-OUT
Often forgotten part of process
Record completion of each step
Collect hours worked
Collect history (damage, cause,
activities)
Determine costs
Continuous learning
WORKFLOW
Schedule Collect
Review and Plan Allocate
Non Routine Work Authorize Prioritize Jobs Costs &
Approve Jobs and Do the =
Flow Costs Work for the Job
Requests Work
Next Period Feedback
Accommodate
Interrupt
Unplanned Jobs Schedule
Continuous
Improvement
Types of Work
PMs (Preventive Maintenance)
Corrective Work
Breakdowns
Refurbishment
Each will have a work-flow process
INITIATION
Different Work Types
SAP Notification
PM Schedule
SAP Notification
For a Corrective job
Acceptance required
Maintenance Manager,
etc.
PM Schedule
Automatically generated
Pre-Approved
Injected Work
Emergency & Schedule
Breakers
For Breakdowns
Immediate approval
PLANNING
Planned Job
Planned Jobs will
require an Estimate
Can then go off to be
Approved
Before detail
Breakdowns
This process shows
identified
SCHEDULE
Jobs are scheduled according
to business requirements
Schedule for all available hours
BREAKDOWNS
Breakdowns are not scheduled
Execution phase
EXECUTION
Daily & Weekly Schedule
Jobs are executed according to
by Operational Personal
Breakdowns
Breakdowns are injected into daily
schedule
Pre-identified backlog jobs are
deferred
Breakdown work orders should have
Hours recorded
ones)
Breakdowns
Reliability analysis
Is a PM required?
PMs
PM data updated
Initiation
SHUTDOWN STEERING
GROUP
Manage upwards as well as
downwards
Managing a large Program requires
input from various stakeholders
Shutdown Steering Group to set
strategic direction
Cross-section of senior management
Must have a Charter (avoid micro-
managing)
FOUR PHASES OF
SHUTDOWN MANAGEMENT
DUR Duration
Can only be done while equipment is
DIS disassembled for other shutdown work
Synergies with doing work in conjunction
SYN with other shutdown work
Jobs to be
Almost Certain High
(Over 30%)
$0 $0 $0 $0 $0
reviewed 4 Moderate
12 26
9 18 27
34
36
for their
Likely
operational 13 4 1 3 24 31 28 25
21 2 22
3 33 29 30 32
5 6 7
20
10 14
Possible 15
impact if
35 37 39
(3% to 10%) 79
not done
23 38 17
2
Unlikely
1
Moderate High
Rare Low
Probability of
$0
1
$0
2
$0
3
$0
4
$0
5
Consequenc
Event Occuring in Low Minor Moderate Major Critical
2005/06 Financial <$25k $25k - $250k $250k - $2.5m $2.5m - $25m >$25m
Year
CONSEQUENCE (BUSINESS IMPACT)
Execution
MEETING STRUCTURE
Consistent meeting Schedule Updates
times 7:00 AM Update for
10:00 AM Morning Morning Meeting
Area Meeting 3:00 PM Update for
Night Shift
3:00 PM Managers
Meeting
EARNED VALUE
Tool for tracking
progress against
schedule
Quickly shows if
you are falling
behind schedule
Forecast costs to
complete work
SHUTDOWN
COMMUNICATIONS
Email is a problem
Reply All
Mass Distribution lists
Not everyone has email access
Noticeboards not very effective
Tool-Box talks are very effective
Meetings work well
Large mass meetings do not work well
Signs work well for operators
Flashing signs work extremely well
Jury is still out on Intranet
Your audience is not homogenous
People will generally not spread rumours that they believe
are not true
FOUR PHASES OF
SHUTDOWN MANAGEMENT
Close-out
POST SHUTDOWN REVIEW
Carry out SWOT Analysis
Consolidate issues
Feed-Back into Management Plan for future shutdowns
Some issues that came out of manufacturing
site shutdown
Need two night shift managers
Need to update schedule twice per day
Supply Department was very happy
No IT issues
Site Security not up to scratch
Steering Group worked well
Site Wide Coordination worked well (forum of
regular Meeting)
Communication needs a lot of work
Fix the phones
PREVIOUSLY WORKED
EXAMPLE
SHUTDOWN PPA
WATER SUPPLY TURNED OFF
DURING SHUTDOWN
PPA PROFORMA
Potential Problems P S Likely Causes Preventive Actions Contingent Actions Triggers
QUESTIONS