Professional Documents
Culture Documents
Survey Compiled
Survey Compiled
SURVEYING PROJECT
ON
VITCC Parking Lot
CLE1003
Parking: An
overview
Act of stopping and disengaging a vehicle.
A) Parallel Parking
B) Angular Parking
E) Right Angle Parking
OBJECTIVE
To establish a parking lot
in the campus for vehicles that
arrive on a
daily basis and occasional basis.
SIGNIFICANCE
LEVELLING
CHAIN AND CROSS STAFF SURVEY
Aim:
To measure horizontal distance between two points by chaining and to take
perpendicular offsets.
We used chain surveying method to find out the offsets from the center length line of
the proposed area for the parking lot.
Methodology
1. We have adopted chain surveying method for measuring the distances of the field
boundaries from the center line.
2. We get offsets of permanent and temporary obstacles which may be taken into
account while establishing the parking lot.
Instruments: Chain, Metallic Tape, Ranging rod, Ranging pole, Cross Staff,
Arrows, Pegs
Theory: Cross-Staff is the simplest instrument used for setting out perpendicular i.e.
taking offsets from a chain line. it is easier and quicker method ,but not very
accurate .
CHAIN AND CROSS STAFF SURVEY
Procedure
1. Reconnaissance
2. Collection of equipment
3. Marking stations
4. Triangulation
Two chain men are required in this process. The chain men are
called as Leader and follower. The chain man at the forward end of
the chain is called leader and chain man at the zero or rear end of the
chain is called as follower.
The follower holds one handle of the chain in contact with peg at
station A.
The leader takes the other handle of the chain, arrows and ranging
rod & walks in the forward direction dragging chain with him.
CHAIN AND CROSS STAFF SURVEY
After the chain is stretched completely along the line the
follower steps on one side of the line with the ranging rod
touching the handle.
The follower directs the leader to stand exactly in the line. The
leader puts a scratch at the position & inserts an arrow. He then
moves forward with the chain handle with the remaining arrows
and ranging rod till the follower reaches the next arrow point.
During this procedure details which are along the side of the
chain line are located by lateral measurement with the help of
offset and tape. The points located are known as perpendicular
offsets.
All the perpendicular offsets are measured till station B is
reached. All the measurements recorded in the field book.
CHAIN AND CROSS STAFF SURVEY
Objectives accomplished:
It is to be noted that first and last stations have only fore bearing
and back bearings respectively.
Take Back bearings of the first point from the last point
PLANE TABLE SURVEY
Instruments used
1. Alidade
3. Compass
4. A3 Sheets
5. Drawing board
6. Tripod
7. Ranging rods
PLANE TABLE SURVEY
Methodology
Select the position of the table where it is be set so that all the
points to be located are visible from it. Let O be the position of
such a point on the ground
Set the plane table over this point and level it. Draw the North line in
the top corner of sheet by means of trough compass at the table.
Now transfer the position of the point O on the ground to the sheet
by means of the plumbing fork. The point O will represent point o
will represent point O on the ground.
Methodology
1.Height of Instrument (H.I) = Reduced level of
Bench mark+ Back sight (B.S)
2.Reduced level of intermediate stations and
Change point = H.I I.S or H.I-F.S
3.New H.I = Reduced level of Change point +
B.S
4.Reduced level of last point = H.I last F.S
last
5.Check: B.S- F.S = Difference between the
DIFFERENTIAL LEVELLING
PROCEDURE
Setup the level at station A, such that the points whose reduced
levels need to be estimated are clearly visible.
The level should be set perfectly horizontal with the aid of the
leveling screws.
This is ensured by positioning the spherical bubble at the centre
of the bubble tube.
Once the temporary adjustments of the level are done, the
instrument is directed towards the target staff held at the Bench
mark and the staff reading is entered as back sight.
Depending on the inter-visibility of the stations, adequate
change points are selected and the leveling is carried out until
the reading corresponding to the last station is taken.
The readings entered in the level book are solved using Height
of instrument method and the difference in elevations between
the two points is estimated.
DIFFERENTIAL LEVELLING
Depending on the intervisibility of the
stations, adequate change points are selected
and the levelling is carried out until the
reading corresponding to the last station is
taken.
The readings entered in the level book are
solved using Height of instrument method
and the difference in elevations between the
two points is estimated.
OBSERVATIONS
DIFFERENTIAL LEVELLING
Objectives accomplished
Environmental
Safety
Economics
Advantages : Environmental
Savings and other benefits that come with the usage of pervious
concrete are due mostly to the following factors:
Longer service life and lower life cycle cost than asphalt
Keep in Mind...
Pervious concrete is only as good as its design and
installation.
2. Sub-base layer
This section is placed underneath the pervious
concrete layer.
It is made up of coarser aggregate (up to 1) and
serves as a storage reservoir for water passing
through the first layer.
The thickness of this layer varies based on local
conditions as well as the amount and size of average
rainfall in the given area.
In general, for the majority of projects the height of
this layer is more than 9 inches.
TYPICAL COMPOSITION OF
PERVIOUS CONCRETE
3. Sub-grade layer
This is the undisturbed soil underneath the sub-base layer.
Sub-grade layer infiltration rate determines how much water
can be absorbed within a given time.
This directly affects the size of the sub-base layer. If the
infiltration rate is too low, larger sub-base or drainage should
be considered.
If the sub-grade is too fine, it may be necessary to place geo-
textile in between the sub-base and sub-grade to minimize
the migration of fine soil particles into the sub-base.
Omitting this could lead to clogging and reduced retention
capacity.
TYPICAL COMPOSITION OF
PERVIOUS CONCRETE
4. Drainage
A drainage system is not always necessary but may be
needed when the infiltration rate of the sub-grade
layer is low and water contained in the sub-base
cannot be absorbed by soil quickly enough.
Drainage systems are very often incorporated in
projects when pervious concrete is placed on graded
sub-grade.
In this case, drainage prevents excessive migration of
water underneath the sub-base layer and reduces the
possible transport of fine soil to the lowest spot of
pavement, where clogging can occur.
Applications
Low-volume traffic pavements
Parking areas
Driveways
Tennis courts
Patios
Artificial reefs
Slope stabilization
Well linings
Foundations
Applications
Floors for greenhouses
Fish hatcheries
Zoos
Hydraulic structures
Noise barriers
concrete pavements
THANK YOU
Bibliography
www.Sciencedirect.com
www.google.com