Professional Documents
Culture Documents
5 MRP
5 MRP
Planning
Dr. Everette S. Gardner, Jr.
End item
R
Time
LT LT
Component
R
Time
LT
Raw material
Time
LT
Time
Component
Time
Raw material
Time
MRP 3
The simultaneous probability
problem
When components are ordered independently with an order
point system, the probability that all will be in stock at the
same time is much lower than the probabilities for individual
components
Computation:
Let Pn = Prob. that n components are
in stock simultaneously
Si = Prob. of stockout on one
order cycle for component i
Then
Pn = S 1 x S 2 x S 3 S n
MRP 4
The simultaneous probability
problem (cont.)
Example:
End Item
1 2 3
S1 = .9 S2 = .9 S3 = .9
P3 = .9 x .9 x .9 =.729
Aggregate
Product planning/
design master Inventory
changes scheduling transactions
Detailed
Purchasing
scheduling
dept.
system
A Level 0
MRP 8
Product tree vs. indented parts
list (cont.)
Indented parts list
A
B(2)
D(1)
E(3)
C(4)
D(2)
F(1)
G(3)
MRP 9
Week
Lead
1 2 3 4 5 6 7 8 9 time
Gross Rqmts.
A 1
Planned order rls.
Gross Rqmts.
B Planned order rls. 2
Gross Rqmts.
C 3
Planned order rls.
Gross Rqmts.
3
D Planned order rls.
Gross Rqmts.
2
E Planned order rls.
Gross Rqmts.
3
F Planned order rls.
Gross Rqmts.
4
G Planned order rls.
Product structure
Multilevel items
MRP 11
Product structure
MRP 12
Product structure (cont.)
Example:
Level Inventory O.H.
Truck 0 0
A. Transmission (1) 1 2
B. Gearbox (1) 2 15
C. Gear (1) 3 7
MRP 14
Multilevel items
The same item may appear at different levels on one or more
BOMs result is multiple retrievals of same record to update
system.
Examples:
X Y Z
1
A A
2
A
3
A
4
MRP 15
Multilevel items (cont.)
Solution: Low-level coding. Lowest level an item appears is
coded on inv. record. Processing delayed until that level
reached.
X Y Z
1
3
A A A A
MRP 16
Rescheduling open orders
Tests for open order misalignment:
1. Are open orders scheduled for periods following the
period in which a net requirement appears?
3. Is lead-time sufficient?
MRP 17
Rescheduling open orders
(cont.)
Example:
Week
1 2 3 4 5 6
Gross 30 5 10 10 10
requirements
Scheduled receipts 20 20
On hand 27 -3 12 12 22 12 2
MRP 18
Tactical questions in MRP
Lot sizing
Safety stocks
MRP 19
Regeneration vs. net change
Regeneration
Complete replanning of requirements and update of
inventory status for all items
Net change
Daily update based on inventory transactions
Example:
Lot size Lot size
Pd. Demand Rule 1 Rule 2
1 5 5 20
2 15 15 0
3 15 15 20
4 5 5 0
(Assume 1 unit requires 1 machine hour.)
MRP 21
Lot sizing implications in MRP
(cont.)
20 20
Machine hrs.
15 15
10 10
5 5
0 0
1 2 3 4 1 2 3 4
MRP 22
Lot sizing techniques used in
MRP systems
MRP 23
Lot-for-lot (L4L) example
Period 1 2 3 4 5 6 7 8 9 Total
Net rqmts. 35 10 40 20 5 10 30 150
Planned order 35 10 40 20 5 10 30 150
(Assume LT)
MRP
MRP1.xls 24
EOQ example
Setup cost, S = $100
Unit price, C = $50
Holding costs, HR = .24 per annum
HP = .02 per period
Annual demand, D = 200
Q = (2DS / CHR)1/2 = 58
Period 1 2 3 4 5 6 7 8 9 10
Net rqmts. 35 10 40 20 5 10 30
Planned orders 58 58 58
Remnants 23 13 13 31 31 11 6 54 24 24
MRP 25
Period order quantity example
Technique:
1. Compute EOQ to determine number of orders per year
EOQ = 58
Number of periods in one year = 12
D = 200
200 / 58 = 3.4 (orders per year)
12 / 3.4 = 3.5 (ordering interval)
Period 1 2 3 4 5 6 7 8 9 Total
Net rqmts. 35 1 40 20 5 1 3 150
0 0 0
Planned orders 85 35 3
0
MRP 26
Safety stocks in MRP systems
Need for safety stocks:
Variations in demand due to end-item forecast errors
and inventory errors
Variations in supply both lead-times and quantities
MRP 27
Safety stocks in MRP systems
(cont.)
Fixed quantity buffer stocks
Good rule of thumb: Set buffer = max. demand likely in a
single period
Never generate order solely to replenish buffer stocks