You are on page 1of 72

Classification of Towers based

on
1)No. of
Circuits
a. Single circuits towers

b. DC/SC towers

c. DC towers

d. MC towers
2)AOD
a) Suspension/Tangent towers <2

b) Small angle towers 2 -15

c) Medium angle towers 15 -30

d) Large Angle towers 30 -60

e) Dead end towers >60

f) Transposition towers(4Xarms)

g) Special towers JC, MC, NB, NBMC

h) Pole mounted termination towers

i) Mono poles
132 KV
SC DC/SC MC NB (B/B)
(B/B) (B/B)

A P/D(4.2) K(8) 0 (1.3)

B R(7.15) L(8.7) 30 (1.31)

C&D S(7.75) M(11.5) 60


(3.174)
Bot Xarm Bot Xarm 12.283 12.35 12.3
Ht ht

Total Height Total 27.381 38.46 27.1


height Note: All in meters
220 KV

L&T TSP M/C NB


A AV/AS X 0
B BS Y 30
C CS(8) Z(17) 60 (3.3)
D(11)
BotXarm Ht 16.85 19.085 17.45 11.79

Total Ht 33.5 38.035 51.4 29

Note: All in mesters


Special towers

NB MCNB(220KV) MCNB(132KV)

120m 250m 300m

60 0, 30 & 60 Deg 0, 30 & 60

2.2 5.4 3.936

14 13.1 12.15
Mono pole

180m

0, 30 & 60

Bot Xarm Ht 15.8


JC
For river crossing suspension towers only

Height(m) Base width Bot Wt.

(B/B) (m) Xram(m) (MT)


Full JC 88.2 12.38 69 32.5

Trunk 72.15 10.4 52.5 28.9

JC
Tower extensions:
+3m
+6m
+9m
+12m
+18m
+25m
+30m
Generally extensions are added to the tower at Bottom section .
Cage Extension is added at cage for dead end towers, the extension
Will be of 3m & 5m
SPANS:
Normal span: 320m for Panther
350m for Zebra and L&T
towers
380m for Moose and TSP
towers
950m for JC
Actual span
Wind span
Weight span: Left wt. span & Right wt.
span
Equivalent span
Negative span
Erection
a) Setting of stubs:

Templat
e
Probe setting
B/B & diagonal at Template top
B/B & diagonal at stub top Ram bus shape
Stub cleats with B&N 2 each
Extra cleats to avoid failure of foundation
due to tower falling.
Threads to bisect
LP&AP
Template height at centre point & joining
of 2 threads
b) After 14 days of curing
Built-up method:- This method consist of erection of
towers member by member. The 4 main leg members of
first section of the tower are first erected and guyed of. The
cross braces then assembled. For assembling second section
a light gin pole is placed on top of the corner legs for
raising the second section of the tower. Afterwards the gin
pole is shifted to top of second section leg to raise third
section this process is continued till complete tower is
erected.
Section method :-
Major sections of the tower are assembled on the
ground and same are erected as units.
Either mobile crane or gin pole of 10m long is
used.
Ground assembly(Proto) :-

This method consist of assembling the tower on


ground and erecting it as a complete unit. The
complete tower is assembled in line wise position
to allow Xarms to fitted. After assembly is
completed tower is picked up from ground with
the help of crane and carried to is location and
set on its foundation.
This method is not is useful when the towers
are large and heavy and the locations are
difficult.
Helicopter method :-

In this method the tower is erected in section.


Bottom section is first lifted on to the stub and
then the upper section is lifted and bolted to first
section and the process is repeated till the tower
is erected. Some times complete assembled tower
is raised with the help of helicopter. This method
is adopted when approach is impossible.
MS tower parts to Galvanized tower parts
Galvanization Procedure

1 2 3 4 5 6 7 8
1. Decreasing Bath Hard HCL
2. Pickling HCL
3. Rinsing Water
4. Fluxing Ammonia and Zinc Chloride
5. Hot plate
6. Zinc batch
7. Dychromizing
8. Finishing & Filling

Galvanization :
oTower parts 86 Microns
oBolt & Nuts - 45 Microns
Tightening of B&N
The bolts & nuts are used to join the tower parts
The bolts are of 16mm diameter and 20mm diameter
The length of bolts are various from 35mm to 80mm multiple
of 5mm
17.5mm/21.5mm dia hole is provided on tower part for
fixing bolt & nut
Spring washers - 16 x 3.5 mm- to tighten the bolt&nut
Flat washers 4, 5, 6, 8, 10,20 and 25mm to fill up gaps
between the tower parts
Check for tight of B&N using torque wrench
The threads of bolts projecting out side shall be
punched at 3 positions and do half round welding to
ensure that nuts are not loosened in course of time
and avoid theft of angles.
Zinc epoxy painting is applied on welded portion to
avoid rusting.
Tower verticality :- 1 in 360
Slenderness Ratio = Effective length of members / Radius
of gyration

SR gives Resistance of any member to


bending
SR for leg members - 150
Tension members - 350
Grounding : -

pipe earthing Tower foot Resistance<15


ohm
CP earthing - 15 30 m of 7/8 or 7/9 SWG

Explain
galvanized
practice
steel of
wire
coke and salt, betonite
powder
50x6mm flat of 1.5m length is used & flat
should be buried at 0.6m below the ground
level.
Earthing pipe is of 25mm dia, 3050 meters
length GI pipe with holes.
earthing is provided for D leg only

For Railway crossing double earthing is to


be provided.

Normally earth pipe is placed vertically &


in difficult places earth pipe placed in slant
position with prior approval.

A pit of 300mm dia and 3.2m depth is


excavated to place earth pipes.
Tower Accessories: -
Danger boards

Number plate

Phase plate

Anti Climbing Device

Step bolts 16x175 mm

Antiperch / Bird guards for suspension towers

Hanger rods
i) NO TOWER SHALL BE ERECTED ON FOUNDATION BEFORE
10 DAYS AFTER CONCRETING.

ii) CHECK THE CORRECTNESS OF DIAGONAL AND LEVEL OF


THE STUB OF THE FOUNDATION.

iii) TOWERS ARE TO BE ERECTED AS PER ERECTION DRAWING

iv) ASSEMBLY OF TOWER PARTS SHALL BE MADE AS PER MARK


NUMBER WISE ENGRAVED ON THE TOWER MEMBER
CORRESPONDING TO NUMBER IN THE ERECTION DRAWING.

v) SPECIAL CARE SHALL BE TAKEN IN SELECTION OF MARK


NUMBER FOR TRANSVERSE AND LONGITUDINAL FACE OF
THE SQUARE BASE TOWER.

vi) ANY BUCKLING, DAMAGE TO STEEL MEMBER, DAMAGE TO


GALVANIZING SHALL BE AVOIDED
vii) NO MEMBER SHALL BE SUBJECTED TO UNDUE STRESS.

viii) REASON CAN BE: (i) DEFECTIVE FABRICATION.


(ii) DEFECTIVE FOUNDATION.
(iii) DEFECTIVE ERECTION METHOD.

viii) COLLECT MATERIAL FROM STORE TALLYING WITH BOM.

ix) PREFERABLY TRANSPORT COMPLETE TOWER OR


COMPLETE SECTION.

x) THE TOWER MEMBER AT LOCATION SHALL BE KEPT ON


GROUND SERIALLY ACCORDING TO THE NEED FOR
FOLLOWING UP ERECTION SEQUENCE.
DERRICK TYING ROPE

DERRICK

20mm POLY
PROPYLENE
ROPE

CROW BARS

TOWER ERECTION
i) WHILE LOADING AND UNLOADING THE TOWER PARTS,
CARE SHOULD BE TAKEN FOR STACKING
SYSTEMATICALLY.

ii) HANDLE THE TOWER PARTS CAREFULLY. WHILE HANDLING


THEM WEAR SUITABLE GLOVES.

iii) ESTABLISH CLEAR SIGNAL/COMMUNICATION BETWEEN


THE PERSONS WORKING ON THE TOP AND THE PEOPLE
SUPPLYING TOWER PARTS, WATCHING GUYS PULLING ETC
SPECIAL CARE SHALL BE TAKEN FOR R.C. TOWER.

iv) ALL LIFTING TOOLS AND TACKLES SHOULD BE LOAD


TESTED AS PER STANDARD.
vi) ENSURE THE DERRICK USED BEFORE TOWER ERECTION HAS
BEEN CHECKED FOR ADEQUATE STRENGTH / SIZE.

vii) KEEP WATCH ON ALL GUYS USED DURING ERECTION ANY


SLIPPAGE/FAILURE IF THE GUY CAN CAUSE ACCIDENT.

viii) POLYPROPYLENE ROPE FROM 20MM TO 25MM SIZE


SHOULD BE USED FOR GUYING & LIFTING.

ix) AFTER 5 OPERATIONS CHECK THE CONDITION OF THE


ROPE. IF WORN OUT THEN REJECT.
xi) ALL TOWER MEMBERS TO BE FITTED WITH APPROPRIATE SIZE
OF NUTS & BOLTS OF THE SECTION ERECTED BEFORE THE
ERECTION IS TAKEN UP FOR THE NEXT SECTION.

xii) AVOID ALL TOWER ERECTION IN RAINY DAY.

xiii) HEAVILY CLOUDY DAYS AVOID ALL TYPE TOWER ERECTION.


STOP TOWER ERECTION OF R.C.TOWER.

xiv) IN CASE OF HEAVY WIND OR APPROACHING STORM STOP ALL


TOWER ERECTION. EVERY ONE SHOULD BE AWAY FROM THE
TOWER.

xv) PPE LIKE HELMET, SAFETY BELT OF PROPER QUALITY IS USED.

xvi) FOR CLIMBING TOWER USE SAFETY BELT WHICH CAN BE


FITTED TO THE TOWER.
LINE MATERIALS

1.Conductors

Conductor Amps Kg/KM AL59 INVAR

Panther 489 974 734 Amp. Double 30+7/3.00


Panther
Zebra 737 1621 930 Amp. Double 54+7/3.18
Zebra
Moose 840 1998 54+7/3.53
AAAC- Less wt., more sag, & more current carrying capacity
ACSR- More wt., less sag, & less current carrying capacity

I. Total No. of wires = 3N(N+1)+1 ; Where N= No. of layers

Layer No. of wires Total


Centre 1 1
1st 6 7
2nd 12 19
3rd 18 37
II. Lay Ratio = Lay/OD ; Where OD = Outer diameter=(2N+1)d;
where d= Dia of single strand

18 wires 10 12

12 wires 12 -14

6 wires 13 -18
2.Earth wire: Shielding angle 10 30
7/3.66 7/3.15

Weight /KM 575 428 Kg/KM

3. Insulators: 70 KN, 120KN and 160 KN

Voltag Suspension Angle

e
132KV 9Nos 10Nos

220KV 13Nos 14Nos

400KV 23Nos 24Nos


1323 = 76.2 KV 80 KV 11 = 8 Nos + 1 extra = 9 Nos

2203 = 127 KV 11 = 12 Nos + 1 extra = 13 Nos

4003 = 230.95 KV 11 = 21 Nos + 1 extra = 22 Nos or Say 23

a) Porcelain Insulators :- Ball and Socket


Long rod

b) SRC Insulators :- Silicon Rubber Composite

FRP rod with sheds, fiber resin plastic rod


Insulator hoisting
Suspension insulators shall be used upto deviations of 2 degrees
on all tangent type towers on the line and strain insulators on all
angle type towers.

For ensuring insulation co-ordination the suspension or tension


strings on approach and terminal towers near the station ends upto
a length of 1.5 Km shall be provided with adjustable arcing horns on
tower side and fixed arcing horns on line side, keeping the arcing
gap as may be stipulated by the Engineer at site.

Insulator strings shall be assembled on the ground. These shall be


cleaned and examined before hoisting. All accessories shall be
properly fitted.

Those having glazing defects exceeding half centimeter square


shall not be used.
For suspension towers 70 KN insulators are hoisted
with Aerial rollers. The Aerial rollers are like single
sleeve pulley .Before hoisting of insulators the M pins
should be checked thoroughly for their opening so that
the insulation will not detached during stringing.
4. SSH for conductor:- PA rods 11 14 Nos; where PA=
Preformed Armoured Rods

5. STH for conductor 6. DSH for conductor

7. DTH for conductor 8. SSH for earth wire

9. STH for earth wire

10. 4R stock bridge vibration dampers (1.2 1.3m)

11. MS joint for conductor

12. MS joint for earth wire

13. Repair sleeves


WRONG METHOD CORRECT METHODS
i) SELECT CONTINUOUS STRETCH AND STARTING TYPE OF TOWER
FOR STRINGING WITH ADEQUATE CARE.
ii) PREPARE DRUM SCHEDULE FOR CONDUCTOR WITH CARE TO
REDUCE WASTAGE.
iii) SELECT PROPERLY THE PLACEMENT SCHEDULE FOR TENSIONER
AND PULLER.
iv) SELECT THE PLACE CAREFULLY FOR PLACEMENT OF TENSIONER
AND PULLER TAKING SITE CONDITION INTO CONSIDERATION.
v) CHECK CORRECTNESS OF ERECTED TOWER AS PER DRAWING AND
SPECIFICATION FOR ALL TOWERS.
vi) CHECK COMPLETION OF EARTHING AND RECORD TOWER FOOTING
RESISTANCE OF EACH LOCATION.
vii) ALL TREES ENROUTE THE LINE SHOULD BE CLEARED AND REMOVED
FROM THE TRAVELLING PATH OF CONDUCTOR.
viii) CERTIFY AFTER VERIFICATION JOINTLY.
STRINGING
a)Paving out of conductor
b)Rough sag
c)Final tension / stringing
METHOD

SLACK OR LAY OUT METHOD.

PAYING BY TENSIONER PULLER.


T&P required :-
Tractor/Tensioner
Turn table (5T or 10T)
Conductor socks
Automatic come along clamp for conductor and earth wire
20mm and 25mm D shackles
Wooden packs
Ground rollers
Aerial rollers
Crowbars
Hacksaw blade
Cutting pliers
Screw driver
Spanners
1. Generally drum lengths are

Panther 2KM
Zebra 1KM
Moose 1KM
Earth wire 2KM

2. Place the conductor drum on TURN TABLE & unwind it.


3. Pull the end of conductor over ground rollers and
passing
through Aerial rollers at suspension towers reach the

4. Makenext cutend
up the point
of tower usingtotractor/
conductor the cut tensioner.
point tower with STH/DTH
5. Follow the same procedure for balance conductors
and earth wire
Rough sag
T&P required:-

Rough sag leads


Steel ropes 10mm, 12mm, 15mm and 16mm
Come along clamp (7 bolts)
Slings (20mm)
4 Sheave pulley
2 Sheave pulley
Single Sheave pulley
Manila ropes 12mm, 16mm, 18mm and 20mm
Single and double end socks
Turn buckle
D shakles 20 mm
Dead man 1to 1.2 m
6. By connecting the other end to LEPTY do the rough sag by
pulling with tractor/tensioner and see that conductors
are lifted In all spans by hand height.

LEPTY made with steel rope of 12mm of 200m and


400m lengths with four sheave pulleys on either end.

7. Common problem is BARD CAGING


Final tension /Stringing

T&P required:-

1. Leg winch
2. Sag boards
3. 100 MT joint compressor with die sets
suitable for panther, Zebra Moose and earth
wire.
4. Earth wire flat clamps
5. D shackles 16mm/25mm
6. Binoculars
7. Tractor / Tension puller
8. Travelling speed will be 5 8 KM per hour.
9. if speed is low causes swinging of traveler and insulator
hardware and higher speed cause damage.

10. Tension load will be around 2000 2500 Kgs


11. For 3rd crossarm stringing tension will be 500 Kgs
12. For 400 KV pilot wire and tensioner is used. First pilot
wire will be passed through the entire reach with Tractor.
Conductor is winded on Tensioner. Pilot wire is knotted to
conductor. The other end of pilot wire is connected to
Puller.slowly puller load applied and tensioner is releasing
the conductor without any problem and make up at this with
STH. Once paving is completed again load Tensioner till sag
point and guyed. Then by Lepty and Tractor make marking
and cater the end.
13. Measurement of sag with equal supports use sag boards
between the two towers of sag span

14. Measurement of sag where supports are at different height


or single spans. Use Dynamo meter for tension readings

15. Sagging section length should not exceed 5KM or 15 spans

16. Physical measurement of ground clearance on roads and


important places.
DETAIL A

A A STEEL ROPE OF 20MM DIA

BACK FILLED EARTH

1100MM
150MM
300MM
100MM

1.50M LONG ISMB 200


A
DETAIL A

STEEL ROPE OF 20MM DIA

A A
BACK FILLED EARTH

1100MM

150MM
300MM
100MM

1.50M LONG ISMB 200

A
SUSPENSION TOWER SUSPENSION TOWER
TENSION TOWER

Excavated pit for Anchoring of Conductor


40m Approx.

STEEL ROPE OF 20MM DIA


TOOLS & PLANT REQUIRED PER CONDUCTOR
BACK FILLED EARTH
1. 20mm dia wire Rope Slings 40m length
1600MM - 1 No.
250MM 2. 20mm 'D' Shakles - 2
2.00M LONG ISMB 200 300MM Nos
100MM 3. Come along Clamp (Bolted Type) - 1 No.
4. 20mm Sling 10m length - 1 No.
DETAIL B
5. Deadmen wood (1000mm-1200mm long)
- 1 No.
C

STEEL ROPE OF 20MM DIA

NOTE: Sling size = 20mm. Depending upon the BACK FILLED EARTH

Tension load rope size should be selected 2100MM

which is dependent on no of conductors 250MM


300MM
type and the tension applied during the 2.00M LONG ISMB 200
100MM
sagging. Arrangement should be capable of
1.5 times of the total tension load. DETAIL C
HOOK
HOOK HOOK

STEEL ROPE STEEL ROPE

BACK FILLED BACK FILLED


EARTH EARTH

RAIL PIECE
RAIL PIECE

IMPROPER PROPER PROPER


GUYING GUYING GUYING
ARRANGEMENT ARRANGEMENT ARRANGEMENT
After stringing ensure the following
Any departures from the correct sag in any span
does not exceed 4 percent.

The sag of any conductor does not depart by


more than 3% from the mean sag of all the
conductors in the same span subject of a
maximum of 150mm.
i) BACK TENSION OF BOTH THE TENSION TOWERS OF SAG SECTION IS MOST
IMPORTANT. PROVIDE BACK TENSION BY PAID OUT CONDUCTOR OF THE NEXT
ADJACENT SECTION OF BOTH TENSION TOWERS.

ii) BACK TENSION ON THE TOWER WITH GUY WIRE SHOULD BE AVOIDED.

iii) IF REQUIRED PREPARE A SCHEME AND GOT IT APPROVED BY THE TECHNICAL CELL.

iv) GUY WIRE CAPACITY SHOULD BE 1 TIMES OF MAXIMUM TENSION OF THE


CONDUCTORS.

v) INSPECT THOROUGHLY THE CONDITION OF GUY WIRES BEFORE USED.

vi) GUY FIXING ANGLE SHOULD BE BETWEEN 45 o TO 50 o TO THE VERTICAL.

vii) GUY BLOCKING ARRANGEMENT SHOULD BE VERY CAREFULLY DONE.

viii) RESPONSIBLE PERSONS SHOULD BE DEPLOYED DURING ENTIRE SAGGING


OPERATION.

ix) MEN ON BACK STAY SHOULD BE PROVIDED WITH APPROPRIATE WHISTLE AND
COMMUNICATION.

x) MEN ON BACK STAY SHOULD BE IN CONSTANT TOUCH WITH FINAL SAGGING


PERSON.
xi) ANY WHISTLE OR COMMUNICATION FROM THE PERSON AT BACK STAY, STRINGING
SHOULD BE STOPPED.

xii) IF NECESSARY CONDUCTOR SHOULD BE RELEASED TO DE-TENSION.

xiii) FINAL SAGGING SHOULD BE DONE AS PER APPROVED SAG TENSION CHART.

xiv) ANY CHANGES IN THE SECTION, SPAN MADE DURING THE CONSTRUCTION THE SAG
TENSION CHART SHOULD BE GOT CORRECTED.

xv) THE PERSON IN-CHARGE OF FINAL SAGGING SHOULD HAVE COPIES OF FINAL
PROFILES, SAG TENSION CHART, FINAL TOWER SCHEDULE, SAG TEMPLATE, PROPER
RECORDING REGISTER, FORMATS, ALL DRAWINGS OF HARDWARE AND ACCESSORIES.

xvi) TWO THERMOMETERS SHOULD BE CLAMPED ON THE TOWER IN ADVANCE ON THE


SAG SPAN.

xvii) TEMPERATURE SHOULD BE CONSTANTLY MONITORED.

xviii) NECESSARY CORRECTION OF SAG BOARD SHOULD BE DONE BEFORE FINAL MARKING
OF CONDUCTOR.

xix) ADEQUATE AND PROPER COMMUNICATION SHOULD BE AVAILABLE AT ALL POINTS


CONTROLLING SAG AND BACK TENSION POINT.
xi) ALL EQUIPMENT SHOULD BE LOAD TESTED BEFORE FINAL SAGGING
OPERATION PLANNED.

xii) USE SUITABLE DYNAMOMETERS TO CROSS CHECK SAG, SHORTER SPAN, HILLY
TERRAIN.

xiii) CHECK CONSTANTLY EVENNESS OF THE BUNDLE CONDUCTOR.

xiv) KEEP CONSTANT CHECK ON THE MOVEMENT OF AERIAL ROLLER TO ENSURE


INTERMEDIATE SPAN ALSO REACHED TO DESIRED SAG.

xv) IN CASE ANY CONDUCTOR IS PULLED ABOVE SAG IN THE SAG SPAN THEN
RELEASE BOTH THE CONDUCTORS TO BRING DOWN BELOW SAG AND BRING
EVENNESS AND THEN RE-SAGGED.

xvi) AVOID FINAL SAGGING IN WINDY DAYS, OTHER WISE ALLOWANCE IS TO BE


GIVEN FOR UPLIFT.

xvii) ALLOWANCE GIVING IS NOT DESIRABLE SINCE IT DEPENDS ON THE WIND AND
EXPERIENCE.

xviii) SPECIFIC CARE SHOULD BE TAKEN IN MEASURING FINALLY SAGGED


CONDUCTOR BEFORE CUTTING & COMPRESSING THE DEAD END CLAMP.
i) KEEP THE CONDUCTOR FINALLY SAGGED FOR 48HRS ON ROLLER.

ii) AGAIN CHECK THE SAG AND RE-ADJUST IT IF NECESSARY.

iii) KEEP SUSPENSION STRING ABSOLUTE VERTICAL.

iv) PLUMB MARK THE CONDUCTOR BEFORE REMOVING ROLLER BY MEANS


OF A PLUMB OR PLUMB MARKER MADE FOR SPECIFIC PURPOSE.

v) THEN THE CONDUCTOR SHOULD BE LIFTED BY MEANS OF A SUITABLE


LIFTING DEVICE.

vi) LIFTING DEVICE MAY CONSIST OF ONE OR TWO HOOKS DEPENDING


UPON NUMBER OF CONDUCTORS.

vii) AFTER LIFTING THE CONDUCTOR FIX PREFORMED ARMOUR RODS.

viii) TAKE 2 OR 3 RODS ON EACH SIDE OF THE CENTRE MARK SUCH THAT
THE HAND WILL NOT BE MORE THAN ONE OR TWO PITCH LENGTHS
AWAY FROM THE CENTRE MARK.
ix) THE CENTRE MARK OF THE RODS SHOULD BE LOCATED AT THE CENTRE
MARK OF THE CONDUCTOR SUPPORT.

x) APPLY THE RODS BY ROTATING ABOUT CONDUCTOR CONTINUING FROM 1


OR 2 PITCH LENGTH OF EITHER SIDE OF THE CENTRE.

xi) FIX ARMOUR ROD APPLYING SPIRAL MOTION OF THE HANDS UNTIL THEIR
ENDS ARE SNAPPED INTO POSITION.

xii) FIX SUSPENSION STRING OVER ARMOUR ROD THEN RELEASE THE LOAD.

xiii) CHECK THE INSULATOR ASSEMBLY IS IN PLUMB.

xiv) INSTALL VIBRATOR DAMPERS OR SPACER DAMPERS AS PER DRAWING at 1.2


to 1.3 m

xv) IF VIBRATION DAMPERS ARE USED THEN FIX THE LINE SPACER
IMMEDIATELY THERE AFTER.
i) ALLOW THE FINALLY SAGGED CONDUCTOR FOR 48HRS TO TAKE CARE THE
CREEPAGE OR MINOR SAG ERROR DUE TO MOVEMENT OF AERIAL ROLLER.

ii) LIFTING DEVICE SHOULD BE FIXED IN SUCH A MANNER SO THAT LIFTING


LOAD IS TRANSFERRED TO TOWER BODY.

iii) AVOID POINTED LIFTING LOAD ON THE TIP OF CROSS ARM.

iv) LIFTING HOOK SHOULD HAVE A RUBBER OR NEOPRENE LINING.

v) MATCH THE CENTRE OF THE ARMOUR ROD WITH CENTRE MARK OF THE
SUSPENSION POINT.

vi) FIX VIBRATION DAMPERS OR SPACER DAMPER IMMEDIATELY SINCE THE


CONDUCTOR AT FULL LOAD / CRITICAL TENSION.

vii) FIX LINE SPACER IMMEDIATELY FOR BUNDLE CONDUCTOR TO AVOID


CLASHING OF CONDUCTOR.
i) MEASURE THE EXACT JUMPER LENGTH REQUIRED FOR EACH
TENSION TOWER.

ii) CHECK THE JUMPER DEPTH, ANGLE AS GIVEN IN THE


ELECTRICAL CLEARANCE DIAGRAM.

iii) PRESS THE JUMPER CONE AND FIX ON THE TOWER.

iv) WHILE FIXING JUMPER THE CONDUCTOR SHOULD BE


EARTHED PREFERABLY ON BOTH THE SIDES.

v) IN CASE OF BUNDLE CONDUCTOR RIGID SPACER SHOULD


BE FIXED AS PER THE RECOMMENDATIONS OF
MANUFACTURER.
Statutory Inspection points:
S. No. Conductor

Location No. Earth wire

Type of tower Earth wire bonds

Chimney Number plates

Coping Danger boards

Missing bolt & nuts Phase plates

HR weld Step bolt & nuts

Insulators Protection wall

Arcing horns Ground clearance

Jumper bolt & nuts Tree clearance

Jumpers Other remarks

Vibration Dampers

You might also like