Who we are

Managing materials and equipment for constructing


waterworks

Location

Nodeulro 734, Dongjak gu, Seoul

History
1989. 11. 03.

1999. 10. 01. ( )

2003. 09. 15. ( )

2007. 07. 30.

2009. 11. 09. ( )


Main business

Purchase, Supply and Storage of Materials for Waterworks

Purchase, Supply and Storage of Water meters

Installation and replace of large scale water meters (contracting-out)

Organization

3 teams : Administration, Construction materials, Water meters

Manpower : 34persons (Administrative and technical : 26, O&M : 8)


Purchase & Supply of materials
for waterworks construction

Integrated purchasing of materials for Installation and repair of water


pipe -> Security of quality of materials and supply

For Pipes, valves, Meter cases and


construction
other materials for construction

Target
materials
For
repairing Recycled asphalt pavement
roads
Material supply procedure

Construction request
Waterworks Equipment
supply
Field of
Department Management Center construction

Design, Purchase request Purchase, Test, warehousing Return remaining materials


Budget establishment data management

All materials managed by computing program in whole procedure

Restrict release materials : Amount of using in 3 days

Stock management
Stock repairing per a month
Safety training per a month
Inventory inspection per a day
Old stock : Change items (cooperation with manufacturer)
Water meter supply and demand management

Purchase in proper time and strict acceptance trials

Water meters installation status

Over
Item Total 15mm 20mm 25mm 32mm 40mm 50mm 80m
m

EA 2,034,510 1,682,454 144,003 97,069 54,837 35,757 11,111 9,279

Ratio
100 82.7 7.07 4.77 2.7 1.75 0.55 0.46
(%)
Purchase & Acceptance trials

Purchase : MAS(Multiple Award Schedule)


Testing standard : Water meter probation criteria
( 2010-247)

- Min. flow : within test error 5.0%


- Max. flow : within test error 2.0%
Purchase procedure
Testing : Error, Pressure & Exterior, Durability