POWER DEVELOPMENT PLAN 2008 - 2018
3. Total New Power Plant Built will be 57,442 MW, while PLN will
contributes 35,274 MW (61 %) and IPP will be 22,168 MW (39 %).
12
Projection of Electricity Demand Growth
Growth
- Indonesia 6.5 7,6 10.4 10.2 9.8 9.4
- Jawa-Bali % 5,6 6,8 10.3 10.2 9.7 9.2
- OutsideJawa-Bali 9.9 10.4 10.6 10,2 10.2 10.0
Electrification Ratio
- Indonesia % 63.1 65.1 67.6 72.6 77.9 88.7
- Jawa-Bali 67.1 69.2 71.9 77.7 83.8 96.0
- OutsideJawa-Bali 56.1 58.1 60.2 64.2 68.2 77.1
14
Source: Draft RUPTL 2009-2018
Fuel Mix
Adjustment
Goal
1,600
Interest
1,400 1,347
Depreciation
1,200
Cost of Goods Sold (Rp/kWh)
600
Fuel
400
200
Decrease COGS
JAILOLO
LUMUTBALAI
LUMUT BALAI 75 MW
(UNOCAL)
110 MW
DIENG
KARAHA
60 MW
400 MW
LAHENDONG I, II,III,IV
TAMPOMAS KAMOJANG
80 MW
50 MW 150 MW
NGEBEL
CISOLOK 120 MW
45 MW
17
DISTRIBUTION OF GEOTHERMAL IN INDONESIA
Non Volcanic
Location : 53 Schemes
Potential :1. 15 GWe
Maluku
Sulawesi
Kalimantan
Irian Jaya
Jawa Alor
Bali Flores
19
Phase II of 10.000 MW Acceleration Program
20
Locations of Phase II Acceleration Project
SUMATERA
Core Project:
HEPP : 174 MW
GeoPP : 1.770 MW
SCPP : 724 MW KALIMANTAN SULAWESI
CCPP : 66 MW Core Project: Core Project:
SCPP GeoPP : 125 MW
: 676 MW
CCPP SCPP : 298 MW
: 120 MW
PAPUA
Core Project:
SCPP : 114 MW
MALUKU
Core Project:
GeoPP : 37 MW
SCPP : 32 MW
TOTAL
JAMALI NTT Core Project:
Core Project: Core Project: HEPP : 1.174 MW
GeoPP : 1.525 MW GeoPP : 41 GeoPP : 3.528 MW
SCPP : 2.000 MW MW SCPP : 3.944 MW
CCPP : 1.200 MW SCPP : 30 CCPP : 1.386 MW
HEPP : 1.000 MW MW TOTAL : 10.032 MW
NTB
Core Project:
GeoPP :40 MW
SCPP :70 MW
21
21
PLN and IPP Project in Phase II Acceleration Program
22
22
PLN & IPP Project Schedule in Phase II Acceleration Program
24
Short Term Pipe Line for GPP
Development
1. Development of Fields under the Old Law
2. Cooperation of Existing Developers and PLN
3. Entry : Can be a Direct Appointment
4. Existing Developer already had experience in
assessing the risks
5. Potential to have new PP built 1,300 MW in
short term
6. Extension of Existing Site
7. New wells had already been drilled
8. Scheme : Selling Steam or Selling Electricity
Mid Term for GPP Development
Conclusion
1. Following-up the government policy, maximizing of
renewable energy/geothermal role has been
anticipated in the fast-track program of generating
development Phase-II by PLN and Directorate
General of Mineral, Coal and Geothermal, MEMR.