Project Management Slide
Project Management Slide
INTRODUCTION
PROJECT GOAL STATEMENT
OBJECTIVE AND SCOPE
MILESTONES
STAKEHOLDERS, CORE TEAM MEMBER&RESPONSIBLITIES
PROJECT KEY ACTIVITIES
CRITICAL ASSUMMPTIONS
TOWER DESIGN
GANTT CHART
BUDGET
RISK ANALYSIS
CONCLUSION
PROJECT GOAL STATEMENT
TO DEVELOP THREE
COMMUNICATION
TOWER ON NOVEMBER
2017
OBJECTIVE AND SCOPE
TO DEVELOP THREE
COMMUNICATION
TOWER ON NOVEMBER
2017
TO DELIVER AND
ASSEMBLE 3
TELECOMMUNICATION
TOWER AT PAHANG
OBJECTIVE AND SCOPE
TO DEVELOP THREE
COMMUNICATION
TOWER ON NOVEMBER
2017
TO DELIVER AND
ASSEMBLE 3
TELECOMMUNICATION
TOWER AT PAHANG
THE WHOLE BUDJET IS
RM750K
MILESTONES
Telco Company
Tenaga Nasional Berhad (TNB)
Oil & Gas company
Community
Majlis Perbandaran Pekan
Jabatan Kerja Raya
Jabatan Keselamatan Kesihatan Pekerja
Lembaga Pembangunan Industri Pembinaan Malaysia (CIDB)
CORE TEAM MEMBER & RESPONSIBLITIES
General Assumptions
Start project on 1 July 2017 – 30 November 2017
Cost Assumptions
Run of budget is rm750k
personnel costs will not change
Resource Assumptions
The materials to complete the project will be readily
available to be utilized.
GANTT CHART
Assembly simulation
BUDGET PREPARATION
Bil Budget
unit rate(RM) Quantity Total(RM)
1 Preliminaries 45000
1.1 Prepare proposal
1.2 Appointment of committee members
1.3 Establish chart and delegate tasks
5 Material
5.1 Steels FE_415 250 1000 250000
5.2 Concrete M20 85 12 1020
5.3 leg / bracing IS2062 170 12 2040
6 Welding 15000
7 Antenna NB-100 Class, 2 metre long for
1.8m and 2.4m micro antenna 1000 1 1000
8 Painting 10000
9 Fabricate/assemble 50000
10 Indirect cost 320000
11 Other cost 55940
TOTAL 750000
RISK ANALYSIS