You are on page 1of 20

AZIM GROUP TELECOMMUNICATION

TOWER CONSTRUCTION AT PAHANG 2017

GROUP MEMBER : AMIRUDIN ASRAF BIN ABD AZIZ (Project Manager)


AMIR FIRDAUS BIN AMIRRUDIN
AZIM BIN ISHA MUDIN
MOHAMMAD NOR HAKIM BIN MAT SOT
MUHADDAD AZIZI BIN ABDULLAH
PANEL : Mr. MOHAMMAD NADZRI BIN HASSAN
CONTENTS

 INTRODUCTION
 PROJECT GOAL STATEMENT
 OBJECTIVE AND SCOPE
 MILESTONES
 STAKEHOLDERS, CORE TEAM MEMBER&RESPONSIBLITIES
 PROJECT KEY ACTIVITIES
 CRITICAL ASSUMMPTIONS
 TOWER DESIGN
 GANTT CHART
 BUDGET
 RISK ANALYSIS
 CONCLUSION
PROJECT GOAL STATEMENT

Proposal to design, fabricate, assemble and


commissioning a telecom tower at Pahang
in November 2017 to be economically and
important town with RM750k budget
OBJECTIVE AND SCOPE

 TO DEVELOP THREE
COMMUNICATION
TOWER ON NOVEMBER
2017
OBJECTIVE AND SCOPE

 TO DEVELOP THREE
COMMUNICATION
TOWER ON NOVEMBER
2017
 TO DELIVER AND
ASSEMBLE 3
TELECOMMUNICATION
TOWER AT PAHANG
OBJECTIVE AND SCOPE

 TO DEVELOP THREE
COMMUNICATION
TOWER ON NOVEMBER
2017
 TO DELIVER AND
ASSEMBLE 3
TELECOMMUNICATION
TOWER AT PAHANG
 THE WHOLE BUDJET IS
RM750K
MILESTONES

DESIGN COMPLETE 31 JULY 2017

FABRICATE COMPLETE 30 AUGUST 2017

TRANSFERS & LOGISTIC 15 SEPTEMBER 2017

ASSEMBLE & CONSTRUCTION 30 OCTOBER 2017

COMMISSIONING & TESTING 15 NOVEMBER 2017


STAKEHOLDERS

 Telco Company
 Tenaga Nasional Berhad (TNB)
 Oil & Gas company
 Community
 Majlis Perbandaran Pekan
 Jabatan Kerja Raya
 Jabatan Keselamatan Kesihatan Pekerja
 Lembaga Pembangunan Industri Pembinaan Malaysia (CIDB)
CORE TEAM MEMBER & RESPONSIBLITIES

DESIGNER ACAP DESIGN SDN BHD


FABRICATES & CONSTRUCT AMET ENGINEERING SDN BHD
COMMISIONING & TESTING HAKIM NDT SDN BHD
TRANSFER & LOGISTIC AZIZI SERVICE SDN BHD
DEVELOPER AZIM GROUP
PROJECT KEY ACTIVITIES

ACAP DESIGN SDN BHD


 Design Proposal
 Design Selection
 Final Drawing Selection
 Final Design Documentation

AMET ENGINEERING SDN BHD


 Confirmation Design Submitted
 Material Prepared
 Complete Fabrication
PROJECT KEY ACTIVITIES

AZIZI SERVICE SDN BHD


Site Preparation
Tower Material Delivery

AMET ENGINEERING SDN BHD


Base Construction
Middle Construction
Full Construction
CRITICAL ASSUMMPTIONS

General Assumptions
 Start project on 1 July 2017 – 30 November 2017
Cost Assumptions
 Run of budget is rm750k
 personnel costs will not change
Resource Assumptions
 The materials to complete the project will be readily
available to be utilized.
GANTT CHART

 ..\gantt chart communication tower.mpp


 ..\- gantt chart communication tower.pdf
TOWER DESIGN
Orthography view overall design
TOWER DESIGN

Assembly simulation
BUDGET PREPARATION

Bil Budget
unit rate(RM) Quantity Total(RM)
1 Preliminaries 45000
1.1 Prepare proposal
1.2 Appointment of committee members
1.3 Establish chart and delegate tasks
5 Material
5.1 Steels FE_415 250 1000 250000
5.2 Concrete M20 85 12 1020
5.3 leg / bracing IS2062 170 12 2040
6 Welding 15000
7 Antenna NB-100 Class, 2 metre long for
1.8m and 2.4m micro antenna 1000 1 1000
8 Painting 10000
9 Fabricate/assemble 50000
10 Indirect cost 320000
11 Other cost 55940
TOTAL 750000
RISK ANALYSIS

No RISK IMPACT SOLUTION

NOT SUITABLE STRUCTURE OF SOIL INVESTIGATION WITH


1 SOIL PROJECT DISRUPTED JKR

INSURANCE CLAIM, BRIEF


ACCIDENT DURING THE BAD REPUTATION OF SAFETY AND AWARENESS
2 CONSTRUCTION COMPANY OF SAFETY AND HEALTH

BAD WEATHER DURING THE TIME FRAME NOT CLASH


3 CONSTRUCTION PROJECT DELAYED WITH RAINY SEASON
MAKES A CONTRACT
SUB CONTRACTOR NOT FOLLOW AGREEMENT WITH SUB
4 SCHEDULE PROJECT DELAYED CONTRACTOR
TRUCK SERVICE ON TIME
AND DO PREVENTIVE
5 TRUCK BREAKDOWN PROJECT DELAYED MAINTENANCE
CONCLUSION REPORT

Three communication tower should be


complete on 30 November 2017 within
budget RM750k and take all the possible risk
in company’s responsibilities.
Q&A

You might also like