Professional Documents
Culture Documents
FIDIC Document Usage: Conditions of Contract For Construction
FIDIC Document Usage: Conditions of Contract For Construction
(a) an extension of time for any such delay. if completion is or will be delayed. under Sub-
Clause 8.4 [Extension of Time for Completion]. and
(b) payment of any such Cost plus reasonable profit, which shall be included in the
Contract Price.
After receiving this further notice, the Engineer shall proceed in accordance with SubClause
3.5 [Determinations] to agree or determine these matters.
However, if and to the extent that the Engineer's failure was caused by any error or delay by
the Contractor, including an error in. or delay in the submission of, any of the Contractor's
Documents. the Contractor shall not be entitled to such extension of time, Cost or profit.
2 THE EMPLOYER
Employer : The party named in the Contract as the "FIRST PARTY" who will enter into
contract with the Contractor for the execution of the Works covered by the Contract, or
any other party authorized by the Employer to exercise the powers and obligations of
the First Party, provided that the Contractor will be informed accordingly in writing .
Provided, that the Engineer shall obtain the specific approval of the Employer, in compliance with
the terms of his appointment, and after submitting his recommendations to the Employer in
writing, in the following matters :
– Issuing variation orders;
– Deciding on the extension of Time for Completion and applying the Liquidated Damages
Clause;
– Approving the appointment of Subcontractors;
– Notifying the Contractor on suspension of Works; and any other matters as may be set
out in Part II of these conditions).
The Contractor shall give to the Engineer not less than 21 days' notice of the date after which the Contractor
will be ready to carry out each of the Tests on
Completion. Unless otherwise agreed, Tests on Completion shall be carried out
within 14 days after this date, on such day or days as the Engineer shall instruct.
In considering the results of the Tests on Completion, the Engineer shall make allowances for the effect of any
use of the Works by the Employer on the performance or other characteristics of the Works. As soon as the
Works. or a Section, have passed any Tests on Completion, the Contractor shall submit a certified report of the
results of these Tests to the Engineer.
<56d
Each of the
monthly (or
otherwise)
interim <28d
payments
19 FORCE MAJEURE
19.1 Definition of Force Majeure
19.2 Notice of Force Majeure
19.3 Duty to Minimize Delay
19.4 Consequences of Force Majeure
19.5 Force Majeure Affecting Subcontractor
19.6 Optional Termination, Payment and Release
19.7 Release from Performance
20 CLAIMS, DISPUTES AND ARBITRATION
20.1 Contractor’s Claims
20.2 Appointment of the Dispute Board
20.3 Failure to Agree on the Composition of the Dispute Board
20.4 Obtaining Dispute Board’s Decision
20.5 Amicable Settlement
20.6 Arbitration
20.7 Failure to Comply with Dispute Board’s Decision
20.8 Expiry of Dispute Board’s Appointment
Contractor’s Claim (cl. 20.1)
Contractor’s Claim (cl. 20.1)
(cont’d)