You are on page 1of 57

Project Management:

A Managerial Approach 4/e

By Jack R. Meredith and Samuel J. Mantel, Jr.

Published by John Wiley & Sons, Inc.

Presentation prepared by RTBM WebGroup


Project Management
A Managerial Approach

Chapter 6

Resource Allocation
Critical Path Method -
Crashing a Project

CPM includes a way of relating the


project schedule to the level of physical
resources allocated to the project
This allows the project manager to
trade time for cost, or vice versa
In CPM, two activity times and two
costs are specified, if appropriate for
each activity
Chapter 9-1
Critical Path Method -
Crashing a Project

The first time/cost combination is called


normal, and the second set is referred to
as crash
Normal times are “normal” in the same
sense as the ‘m’ time estimate of the
three times used in PERT
Crash times result from an attempt to
expedite the activity by the application of
additional resources Chapter 9-2
Critical Path Method -
Crashing a Project
Careful planning is critical when
attempting to expedite (crash) a project
Expediting tends to create problems;
and the solution to one problem often
creates several more problems that
require solutions
Some organizations have more than
one level of crashing
Chapter 9-3
Fast-Tracking
Another way to expedite a project is
known as “fast-tracking”
It refers to overlapping the design and
build phases of a project
Because design is usually completed
before construction starts, overlapping
the two activities will result in shortening
the project duration
Chapter 9-4
The Resource Allocation
Problem

A shortcoming of most scheduling


procedures is that they do not address the
issues of resource utilization and availability
Scheduling procedures tend to focus on
time rather than physical resources
Time itself is always a critical resource in
project management, one that is unique
because it can neither be inventoried nor
renewed
Chapter 9-5
The Resource Allocation
Problem
Schedules should be evaluated not merely
in terms of meeting project milestones, but
also in terms of the timing and use of
scarce resources
A fundamental measure of the project
manager’s success in project management
is the skill with which the trade-offs among
performance, time, and cost are managed

Chapter 9-6
The Resource Allocation
Problem

The extreme points of the relationship


between time use and resource use are
these:
Time Limited: The project must be finished by
a certain time, using as few resources as
possible. But it is time, not resource usage, that
is critical
Resource Limited:The project must be finished
as soon as possible, but without exceeding some
specific level of resource usage or some general
resource constraint
Chapter 9-7
The Resource Allocation
Problem
If all three variables - time, cost,
specifications - are fixed, the system is
“overdetermined”
In this case, the project manager has lost all
flexibility to perform the trade-offs that are so
necessary to the successful completion of
projects
A system-constrained task requires a fixed
amount of time and known quantities of
resources
Chapter 9-8
Resource Loading

Resource loading describes the amounts of


individual resources an existing schedule
requires during specific time periods
The loads (requirements) of each resource
type are listed as a function of time period
Resource loading gives a general
understanding of the demands a project or set
of projects will make on a firm’s resources

Chapter 9-9
Resource Loading

An excellent guide for early, rough project


planning
Because the project action plan is the source
of information on activity precedences,
durations, and resources requirements, it is
the primary input for both the project
schedule and its budget
The action plan links the schedule directly to
specific demands for resources
Chapter 9-10
Resource Loading
The PERT/CPM network technique can be
modified to generate time-phased resource
requirements
The project manager must be aware of the
ebbs and flows of usage for each input
resource throughout the life of the project
It is the project manager’s responsibility to
ensure that the required resources, in the
required amounts, are available when and
where they are needed
Chapter 9-11
Resource Leveling
Resource leveling aims to minimize the period-
by-period variations in resource loading by
shifting tasks within their slack allowances
The purpose is to create a smoother distribution
of resource usage
Several advantages include:
Less hands-on management is required
May be able to use a “just-in-time” inventory policy

Chapter 9-12
Resource Leveling

When resources are leveled, the associated


costs also tend to be leveled
The project manager must be aware of the
cash flows associated with the project and of
the means of shifting them in ways that are
useful to the parent firm
Resource leveling is a procedure that can be
used for almost all projects, whether or not
resources are constrained
Chapter 9-13
Constrained Resource
Scheduling
There are two fundamental approaches to
constrained allocation problems:
Heuristic Methods
Optimization Models
Heuristic approaches employ rules of thumb that
have been found to work reasonably well in similar
situations
Optimization approaches seek the best solutions but
are far more limited in their ability to handle
complex situations and large problems
Chapter 9-14
Heuristic Methods

Heuristic approaches to constrained resource


scheduling problems are in wide, general use
for a number of reasons:
1. They are the only feasible methods of attacking
the large, nonlinear, complex problems that tend to
occur in the real world of project management
2. While the schedules that heuristics generate may
not be optimal, they are usually quite good- certainly
good enough for most purposes

Chapter 9-15
Heuristic Methods
Most heuristic solution methods start with the
PERT/CPM schedule and analyze resource
usage period by period, resource by resource
In a period when the available supply of a
resource is exceeded, the heuristic examines
the tasks in that period and allocates the
scarce resource to them sequentially, according
to some priority rule
Technological necessities always take
precedence
Chapter 9-16
Heuristic Methods
Common priority rules:
As soon as possible
As late as possible
Shortest task first
Most resources first
Minimum slack first
Most critical followers
Most successors
Arbitrary
Chapter 9-17
Heuristic Methods
 Most priority rules are simple adaptations of the heuristics
used for the traditional “job shop scheduling” problem of
production/operations management
 Most heuristics use a combination of rules: a primary rule,
and a secondary rule to break ties
 As the scheduling heuristic operates, one of two events
will result:
The routine runs out of activities before it runs out of resources
The routine runs out of resources before all activities have been
scheduled

Chapter 9-18
Optimizing Methods
The methods to find an optimal solution to
the constrained resource scheduling
problem fall into two categories:
Mathematical programming
Enumeration
Mathematical programming can be thought
of as liner programming (LP) for the most
part
Chapter 9-19
Optimizing Methods

Linear programming is usually not feasible for


reasonably large projects where there may be
a dozen resources and thousands of activities
In the late 1960s and early 1970s, limited
enumeration techniques were applied to the
constrained resource problem
Tree search, and branch and bound methods
were devised to handle up to five resources
and 200 activities

Chapter 9-20
Multiproject Scheduling
and Resource Allocation
The most common approach to scheduling and
allocating resources to multiple projects is to treat
the several projects as if they were each elements
of a single large project
Another way of attacking the problem is to
consider all projects as completely independent
To describe such a system properly, standards are
needed by which to measure scheduling
effectiveness

Chapter 9-21
Multiproject Scheduling
and Resource Allocation
Three important parameters affected by
project scheduling are:
Schedule slippage
Resource utilization
In-process inventory
The organization (or the project manager)
must select the criterion most appropriate for
its situation
Chapter 9-22
Multiproject Scheduling
and Resource Allocation
 Schedule slippage, often considered the most
important of the criteria, is the time past a
project’s due date or delivery date when the
project is completed
 Resource utilization is of particular concern to
industrial firms because of the high cost of
making resources available
The amount of in-process inventory concerns the
amount of work waiting to be processed because
there is a shortage of some resource
Chapter 9-23
Multiproject Scheduling
and Resource Allocation
All criteria cannot be optimized at the same
time
As usual, the project manager will have to
make trade-offs among the criteria
A firm must decide which criterion to
evaluate its various scheduling and
resource allocation options

Chapter 9-24
Mathematical Programming

Mathematical programming can be used to


obtain solutions to certain types of multiproject
scheduling problems
These procedures determine when an activity
should be scheduled, given resource constraints
Mathematical programming, however, is rarely
used in project management to handle the
multiproject problem (mostly, heuristics are
used)

Chapter 9-25
Mathematical Programming

The three most common objectives of


mathematical programming are:
1. Minimum total throughput time (time in the shop) for all
projects
2. Minimum total completion time for all projects
3. Minimum total lateness or lateness penalty for all projects

These objectives are most appropriate for ‘job


shop’ type solutions to resource constraints

Chapter 9-26
Heuristic Techniques
There are scores of different heuristic-based
procedures in existence
They represent rather simple extensions of
well-known approaches to job-shop
scheduling:
Resource Scheduling Method
Minimum late finish time
Greatest resource demand
Greatest resource utilization
Most possible jobs
Chapter 9-27
Summary

The critical path method (CPM) is a network


constructed in the same manner as PERT but
considers the possibility of adding resources
to tasks to shorten their duration
The resource allocation problem is concerned
with determining the best trade-offs between
available resources, including time,
throughout the duration of the project

Chapter 9-28
Summary
Resource loading is the process of
calculating the total load from project tasks
on each resource for each time period of the
project’s duration
Resource leveling is concerned with evening
out the demand for various resources
required in a project by shifting tasks within
their slack allowances

Chapter 9-29
Summary

There are two basic approaches to addressing


the constrained resources allocation problem:
Heuristic methods
Optimizing methods
For multiproject scheduling, three important
measures of effectiveness are schedule
slippage, resource utilization, and level of in-
process inventory

Chapter 9-30
Summary

When a new project is added to a multiproject


system, the amount of slippage is directly
related to the average resource load
Mathematical programming models for
multiproject scheduling aim to either minimize
total throughput time for all projects, minimize
the completion time for all projects, or
minimize total lateness for all projects

Chapter 9-31
Resource Allocation

Questions?

Chapter 9-32
Resource Allocation

Picture Files
Resource Allocation

Figure 9-1
Resource Allocation

Figure 9-2
Resource Allocation

Figure 9-3
Resource Allocation

Figure 9-4
Resource Allocation

Figure 9-5
Resource Allocation

Figure 9-6
Resource Allocation

Figure 9-7
Resource Allocation

Figure 9-8
Resource Allocation

Figure 9-9a
Resource Allocation

Figure 9-9b
Resource Allocation

Figure 9-10
Resource Allocation

Figure 9-11
Resource Allocation

Figure 9-12
Resource Allocation

Figure 9-13
Resource Allocation

Figure 9-14
Resource Allocation

Figure 9-15
Resource Allocation

Figure 9-16
Resource Allocation

Table Files
Resource Allocation
Resource Allocation
Resource Allocation
Copyright © 2000 John Wiley & Sons, Inc. All rights
reserved. Reproduction or translation of this work
beyond that permitted in Section 117 of the 1976 United
States Copyright Act without the express written
permission of the copyright owner is unlawful. Request
for further information should be addressed to the
Permissions Department, John Wiley & Sons, Inc. The
purchaser may make back-up copies for his/her own use
only and not for distribution or resale. The Publisher
assumes no responsibility for errors, omissions, or
damages, caused by the use of these programs or from
the use of the information contained herein.

You might also like