DEPARTMENT NAME

Q4 Business Plan 2018-19 review


HIGHLIGHTS

1.External Inspection of 30 nos. of Equipment's as


per Inspection Schedule Completed in CDU-VDU.

2.LPG Vapourizer 22-EE-00-103A/B: Failure analysis


of tubes Completed.
The following were the Conclusion &
Recommendation for the same:
Conclusion: Stagnant LP Steam Condensate or the
stagnant cooling water of Hydrotest is suspected to be the
cause of formation of pits resulting in Pinhole. This is a type
of under deposit corrosion due to stagnant condensate
resulting in oxygen pitting and it has resulted in carbonic
acid corrosion in one of the tubes indicated by channeling
effect at 6 o clock position.
HIGHLIGHTS

Recommendation: 1. Flow of LP steam shall be maintained in


all the tubes to ensure that all condensate is drained properly.
2. After major shutdown proper operational procedure such as
Nitrogen Purging shall be followed to prevent stagnation of
water and to keep the Tubes free from water corrosion.

3. CBD Line: Stage-wise Inspection for the Fabrication &


Erection of Section-2 of CBD header alonwith connecting
lines is under progress. Loop2 & 3 Mechanical piping &
Wrapping coating jobs completed. Hydrotest carried out
at 20 Kg/cm2 and was found satisfactory.
4.Thermography: Thermography of of CDU Heater
(11-FF-00-101) and VDU Heater (12-FF-00-101)
Thermography was carried out for CDU and VDU
heaters: At few locations specially at the Corner and
Arch section of Heater casing outside temperature
was found slightly on higher side.
Max. Temp. summary:

Sr. No. Location Max. Temp (°C)


1 CDU Heater first floor, west cabin, south Side 268.5

CDU Heater Third Floor, Arch section at Corners 228

2
VDU Heater Second Floor, west cabin, north side at corner 180

4 VDU Heater Third Floor, Arch Section 213


STATUS OF JOBS wrt BP

Sr. Activity/Milestone Status


No
1 Thermography of all Heaters Completed
(CDU-VDU)
2 RTA 2018 Documentation & Completed
Report