Weekly Review – 09 Oct 2018

CRM Rental

PT. Astra Graphia Information Technology PT. Swadaya Harapan Nusantara

©2016 AGIT. All rights reserved. | 1


Meeting Agenda

01. Project Plan

02. Project Status

©2016 AGIT. All rights reserved. | 2


CRM Rental

1 PROJECT PLAN

©2016 AGIT. All rights reserved. | 3


5. Schedule Plan

KICK OF MEETING Development Training


13 Sept 9 Oct - 19 Nov UAT 11 Dec - 17 Dec
EDD/Blueprint Go Live Go Live Support
27 Nov -10 Dec
User Req 18 Sep - 8 Oct 18 Dec 2018 19 Dec -14 Jan
17-27 Sep SIT
21 Nov- 26 Nov

PREP / DEFINE DESIGN DEVELOP DEPLOY COMPLETE

SEPTEMBER OCTOBER NOVEMBER DECEMBER JANUARY

Delayed

We Are Here
©2016 AGIT. All rights reserved. |
CRM Sparepart Phase 2

2 PROGRESS PROJECT

©2016 AGIT. All rights reserved. | 5


Progress Proyek – 09 Oct 2018

Progress sampai dengan 09 Oct 2018


Plan : 11.99 %
Actual : 6.1 %
GAP : - 5.89% ©2016 AGIT. All rights reserved. | 6
Project Issue

No Problem - Identification Correction PIC Due Date Status

Diselesaikan dalam w2
Ureq belum diselesaikan Oct 2018 Henri 12 Oct 2018 Behind
1.
Kamis – Jumat (11 Oct – Denis
12 Oct 2018)

©2016 AGIT. All rights reserved. | 7


Next Activity

No Activity Start End

1. Ureq 12 Oct
2. EDD 12 Oct 21 Oct

3. Development 13 Oct 19 Nov

©2016 AGIT. All rights reserved. | 8


3
CRM Renta;l

APPROVAL WEEKLY REVIEW

©2016 AGIT. All rights reserved. | 9


Approval Weekly Review – 09 Oct 2018

Mengajukan Menyetujui

Henri Alia Putra Izzat Buchari


Project Manager AGIT Project Manager TN