Professional Documents
Culture Documents
2
What Is Monitor and Control?
Monitor and control is all about
continually observing project
progress and taking corrective
action when problems arise
4
Discussion
Why is it important to measure the performance
of your project?
How do you know your project is on track with costs,
schedules or performance goals?
On what basis should you make status statements to
the Program Managers and to your clients?
What happens when you don’t use concrete facts to
support your project status reports?
6
Module Agenda
7
Key Performance Indicators (KPIs)
Two types of KPIs:
8
Say you are planning to build the
home of your dreams…
9
Base Measures
The following base measures are the metrics upon
which all others are calculated
10
Budget at Completion (BAC)
BAC is the budget determined for each task or the
total budget for the project
11
Home Project BAC
700
600
Workdays
500
400
300
BAC
200
100
0
1 2 3 4 5 6 7 8 9 10 11 12 13
Weeks
In accordance with AD Metrics, these KPI metrics
are forecasted in workdays, not dollars
12
Planned Value (PV)
PV at any given point in time is the cumulative
amount of work that was planned to be completed
by that point in time
13
Home Project PV
700
600
Workdays
500
400 BAC
300 PV
200
100
0
1 2 3 4 5 6 7 8 9 10 11 12 13
Weeks
The “flat spots” are weeks when no work is planned to be completed 14
Home Project PV, Continued
700
600
Workdays
500
Task 1: Site Preparation
400 PV = 50 workdays
BAC
300 PV
Task 3: Framing & Roof
200 PV = 150 workdays
700
600 Task 4: Rough Plumbing
& Electrical
Workdays
500 PV = 50 workdays
400 BAC
Task 6: Final Plumbing
300 & Electrical
PV = 50 workdays
PV
200
Task 5: Insulation &
100 Sheetrock
PV = 50 workdays
0
1 2 3 4 5 6 7 8 9 10 11 12 13
Weeks
16
Home Project PV, Continued
700
600 Task 7: Painting &
Trim work
Workdays
PV = 50 workdays
500
400 BAC
300 Task 8: Flooring &
Cabinets
PV
PV = 100 workdays
200
Task 9: Final Inspection
100 PV = 50 workdays
0
1 2 3 4 5 6 7 8 9 10 11 12 13
Weeks
17
Earned Value (EV)
EV is the actual budgeted value of work which was
planned to be completed by that point in time. This
represents how much work has actually been
completed on a project
According to Accenture methods, only tasks that are 100% complete are
factored into the EV of a project:
Based on contractual requirements for an engagement, tasks that are
less than 100% complete may be included in the EV calculation
Earned value for each reporting period is derived from:
The baseline budget
For each task which was actually completed in that reporting period
Note: Here “task” is used to indicate the lowest level of tracking in the
workplan, which might represent a group of deliverables, an individual
deliverable or even components of a single deliverable
18
Home Project EV
700
600 Task 1: Site Preparation
EV = 50 workdays (Week 3)
Workdays
500
BAC
400
PV
300 Task 3: Framing & Roof
EV = 150 workdays (Week 8) EV
200
100 Task 2: Foundation
EV = 100 workdays (Week 5)
0
1 2 3 4 5 6 7 8 9 10 11 12 13
Weeks
19
After Eight Weeks, What Has It Cost….
Budget Actual
Task (Workdays) (Workdays)
Task 1: Site Preparation 50 60
Task 2: Foundation 100 120
Task 3: Framing & Roof 150 190
Total 300 370
20
Actual Cost (AC)
AC is the actual amount of effort expended on the
tasks that have been completed at a given point
in time
Normal Accenture practice is that PV, EV and AC are
tracked and reported as work effort
AC for each reporting period is derived from:
The actual value
For each task which actually completed in that reporting
period
Whether on track or not, the AC gives no information
or indication on the effectiveness of the completed
work
21
Home Project AC
700
600
Week 8: Planned to complete
Workdays
200 AC
Week 8: Tasks 1-3 Completed
100 EV = 300 workdays
Project is behind schedule
0
1 2 3 4 5 6 7 8 9 10 11 12 13
Weeks
22
Remaining Base Measures
Actual to Date (ATD) – the total actual effort for all work
to date, whether work is complete or in progress
Estimate to Complete (Project ETC) – the forecast or
estimated spend required to complete each remaining
task on the project
23
Control Metrics Overview
Control Metrics are used to help project managers
identify variances and take corrective action
Control Re-forecast
Metrics Base Measures
25
Schedule Variance (SV) and Cost
Variance (CV)
SV and CV are key indicators of whether or not
your project is on track
26
Home Project SV and CV
700
600
Workdays
27
Interpreting SV and CV
Schedule
Variance Very good team,
Team is not efficient, too much
misunderstood scope
Ahead of overtime or too many
or team is cutting
Schedule resources on a task
corners
(EV > PV)
As planned, but check if estimates are accurate,
quality is as expected, deliverables are complete
On Schedule and meet specifications
(EV = PV)
Very good team;
Scope creep
however, easier
Learning curve poorly planned
deliverables are
Lack of skills
finished first and team
Behind Schedule Rework
(EV < PV) members could be
Too many reviews/sign offs
missing
31
Module Agenda
32
Identifying Risks
"OK, I have all the metrics and
collected my insights, what’s
next?”
33
Risk Management
Avoiding risks is about planning. Be proactive,
and plan for risks before they occur
Managing risks grows out of your knowledge and
experience
You use that information to predict where potential
pitfalls and obstacles might occur
Then you plan for these instances before they happen,
thereby avoiding their impact on the project
34
Risk Management Techniques
Remember these techniques
when managing risk:
Avoidance
Acceptance
Transfer
Control
Investigation
35
Issue Management
Issue management is:
36
Issue Management Process
The Project Manager is responsible for
overseeing the Issue Management Process
Facilitate
Issue
Collect Resolution
Issues from with Teams
Team Implement
Members Resolutions
Develop
Identify Track Assess Issue
Issues Issues Issues Resol-
ution
Provide Issue
Recommend-
ations to
Executive Team
37
Scope Management
Monitoring and controlling scope involves
carefully tracking your project's progress and
aggressively pursuing solutions to problems that
take your project out of scope
Ensure all assumptions regarding scope are
documented
Ensure the client knows the cost of changes to scope
early on in the process
Always revisit scope when changes occur in the
project, whether the changes are internal or external
Ensure that everyone knows what is involved when
changes occur
38
Scope Creep
Scope creep is what happens
to your project when issues
and risks are not managed
correctly
Creep occurs when changes to
scope significantly alter your
project's ability to deliver to the
business case
Scope creep can cause severe
changes to a project delivery
time and budget
39
Module Agenda
40
IBPS Approach
Generate
ideas
Analyze Structure
findings the ideas
Develop
the
research
plan
41
Solve the Problem
An Issue Tree breaks down the
Key Question into small,
logical components
42
Creating an Issue Tree
Building an Issue Tree is an
iterative process
Brainstorm
Map ideas to the issue tree
Expand the issues
43