Professional Documents
Culture Documents
• Longman dictionary,
‘the act of officially stopping something
from continuing for a period of time’
Reassessment Adverse
of the design weather
of the work. condition.
Contractor
unsatisfactory
performance.
PWD FORM 203A (REV. 1/2010)
Suspension and resumption of Works.
EXCEPT
If the suspension is due to a cause by the Contractor.
Payment obligation
including all cost and
expenditure incurred by the
Clause 51.1(C) (i) are
Government and the
applicable
contractor shall be
ascertained in accordance
with Clause 54
PAM 2006
• TERMINATION OF CONTRACTOR’S
OBLIGATION AT THE SITE BECAUSE OF :-
A) Default of Obligation
B) General Default
51.1. DEFAULT OF OBLIGATION
(a) EVENTS OF DEFAULT
i. Fails to commence work within 2 weeks after the date of site
possession without any reasonable cause
ii. Suspension of work wholly or substantially- there are no works
carried out on site.
iii. Fails to proceed the responsibility required consistently and
diligently.
iv. Fails to carry the work as required by the contract
v. Persistently neglect to carry out his obligation under the contract
vi. Refuses or persistently neglect to comply with a written notice from
the SO:-
- repair any defects
- replace any unsuitable material
vii. Fails to comply with clause 47 (sub contract or assignment)
viii. Fails to comply with any terms and conditions of THIS contract
(PWD 203A)
Termination procedures
Contractor Written
Contractor Termination
fails to carry notice issue
fails to notices
the work by officer
remedy the release by
according to (appendix 3
default the Officer
contract (a)(i))
14 Days
51.1 DEFAULT OF OBLIGATIONS (CONT’D)
(b) TERMINATION
Contractor fails to remedy- Officer (as
named in the appendix) give written notice
to the contractor.
51.1 DEFAULT OF OBLIGATIONS (CONT’D)
( c ) CONSEQUENCES OF TERMINATION
i. contractor shall:-
a. Stop all operations immediately.
b. Take any necessary protection works to secure the
site, equipments, good and materials against any
damage or loss and leave the site in tidy and clean
condition.
c. Remove all the workers and labour from the site.
d. -Vacate the site according to the time stipulated by
SO.
- remove all its belongings which have not been
paid by client. If contractor fails to do so, client
have right to remove and sell their belongings.
51.1 DEFAULT OF OBLIGATIONS (CONT’D)
( c ) CONSEQUENCES OF TERMINATION
(CONT’D)
f. Hand over all plans, drawings and other
documentation with no cost to Government.
g. Pay for any losses and damages as a result of
termination
h. Not be release from any of his obligation under
the contract.
51.1 DEFAULT OF OBLIGATIONS (CONT’D)
14 Days 10days
Eg. Issuance of
Issuance of
Contractor written Contractor the
persistently Notice by continue terminatio
neglect to employer with the n
comply or default Certificate
with AI Architect
CLAUSE 25.3
• (a)
- Contractor should move out from side
- All temporary works, plants and etc can
be used by other Person
- May purchase all the materials and goods
during the completion of work.
25.4 (a) –if required by the Employer
Date of Determination
21 days
Date of Determination
21
days
28
days
1/1/2011 30/1/2011
b) The national interest, national policy and
national security is set by the Government
and is ought to be firm.
Matters relating to safety of the nation is
what is clearly included in national interest.
52.2 Consequences of Termination
a) All payments incurred either by the Client
or by the Contractor are both classified as
Payments upon Termination (Clause
54.0).
b) Other clauses:-
• 51.1 (c) (i)
• 51.1 (c) (ii) (B) – Gov. repossess the site
• 51.1 (c) (ii) (C) – to complete the work by its
own or engage new contractor.
PAM – No Clauses
Clause 53.1
• Termination
(a) If the contractor or any person on behalf of contractor
gives or have intention to give any person (involved in the
contract) any gift, money or other reward: