Professional Documents
Culture Documents
OUTLINE
PROJECT PLANNING
RISK MANAGEMENT PLAN
summary
introduction
about
about
about
about
1. RISK IDENTIFICATION
2. RISK ASSESSSMENT
3. RISK RESPONSE PLAN
introduction
summary
introduction
summary
introduction
summary
about
about
about
about
- ALAN LAKEIN
WHY DO PROJECT PLANNING ?
With well-planned project we can better
introduction
summary
potential risks.
introduction
about
life of a project and can affect project
about
about
about
deliverables.
introduction
about
management.
about
about
about
introduction
Possible Negative
about
Elements that
about
about
about
introduction
but being mindful of a few points can be helpful.
about
about
about
about
• risk identification should be focused on project
objectives
• do basic research
introduction
straightforward step in risk management.
about
about
about
about
where the identified risks are organized
according to severity of threat and to
probability of occurrence.
COMPOSITE RISK INDEX CRI
used to assign priority, with greater CRI being
higher priority.
summary
introduction
about
about
about
about
this method is simple, straightforward,
and can generate a priority list very
quickly.
FORMULA:
introduction
management.
about
about
about
about
At this point, the risk manager has at his or her
disposal a priority list of threats and the
corresponding probability, severity, event, and
source of the risk. Using this information, the risk
manager should decide on how to deal with each
risk.
RISK RESPONSE STRATEGIES FOR THREATS
ACCEPTANCE
simply accepting the risk. Accepting a risk means
dealing with any of its consequences.
summary
introduction
AVOIDANCE
about
about
about
about
removing the probability of occurrence of a risk by
avoiding an action or decision that could carry risk.
REDUCTION
sometimes called mitigation or contingency planning,
is reducing the severity of repercussions by having
some sort of contingency plan.
APPLICATION TO SENIOR PROJECT
Risk management is useful at any project scale.
For its senior design project, the Burgundy
Team has been working on a project to track the
location of devices in space in real time using RF.
summary
introduction
about
The Burgundy Team’s project, like any project,
about
about
about
has risks that must be planned for in order to
ensure the successful and timely delivery of a
complete product. By using the three-stage
process, the Burgundy Team greatly increases its
chances of success.
SOURCES EVENTS THREATS
RISK
RISK MANAGEMENT PLAN
RF traffic within
Environment Interference
frequency range
DATA AND
PROGRAMS 7.0 0.8 Unlikely 0.3 0.2
LOST
SOFTWARE
DEVELOPMENT 5.0 0.6 Unlikely 0.3 0.2
DELAYED
TESTING
5.0 0.6 Unlikely 0.3 0.2
DELAYED
TOTAL LOSS OF
0.0 0.0 Highly likely 0.8 0.0
POWER
CRI ( SEVERITY
THREATS STRATEGY DETAILS
* PROBABILITY )
introduction
about
approved risk response plan is a milestone for
about
about
about
the risk manager as completing the risk
management overall strategy. However, risk
management is dynamic and the risk manager
must reevaluate each stage the process
periodically to ensure relevance, adapt to
changes in risk and risk probability, and revamp
in response to changes in project objectives.
The project planning is commonly perceived as
creating 'Gantt Chart' alone, which is incorrect.
summary
introduction
There are several elements of project plan. One of
about
about
about
about
its element is Risk Management Plan.