Professional Documents
Culture Documents
EIS POM Controlling
EIS POM Controlling
IN SOCIETY:
PROJECT & OPERATION
MANAGEMENT
LECTURE :
PROJECT CONTROL AND
TERMINATION
1
Recap from Previous
Lecture…
Control
2
Lecture outline
Control definition
Control mechanisms at various stage of
project life
Control During Construction : Time Control
Control During Construction: Cost Control
Earn Value and S-curve
Resource Leveling
Control for Project Termination
Control for Completion and Handing Over
3
Control Definition
Measuring what is actually achieved in a project
with regard to the OBJECTIVES (t, c, q),
comparing it with a “baseline” (referenced/original)
performance and monitoring and taking corrective
measures should there be unacceptable deviation
from the baseline
4
3.1 Control systems
throughout the project
Control systems / mechanisms must be
provided at each stage of the project
5
3.1 Control systems
throughout the project (cont.)
Execution (Construction / production) stage
- To ensure all ‘Plans” are being executed and strictly
followed (Schedule Plan, Cost Plan, Quality Plan)
Delivering stage
- To check the efficiency or quality of the product
delivered
- Mechanism e.g : Hand-over Document, Defects List,
Defects Liability/ Guarantee Period, Performance
Bond, As-built Drawings
6
3.2 Control During
Construction/Production
7
3.2.1 Time or Schedule Control
8
3.2.1 Time or Schedule Control (cont.)
Main Inputs Tools & Techniques Main Outputs
1. Original Schedule - 1. Schedule 1. Updated Schedule
Schedule as planned, comparison bar -updates to changes in
acts as basis for charts start and finish dates
comparison -Displays two bars for
each activity, one 2. Recommended
2. Approved shows current /actual corrective actions
schedule changes status, the other the -Anything done to
original schedule bring future project
- Information on
schedule in line with
approved schedule 2. Performance the approved original
changes measurement project schedule
3.Performance – measure variations in baseline.
reports project schedule
that may occur
- information on time eg using S-curve.
performance such as
the actual progress; 3. Project Mgmt
which planned dates software
have been met and -Track actual progress
which have not etc. dates vs planned
dates and forecast
3. effect of changes
9
3.2.1 Time or Schedule Control:
Progress Monitoring Using
Comparison Bar Charts
Assume the progress of the activity as a direct
linear function of the elapsed time
Example: Road construction
10
3.2.2 Cost Control
11
3.2.2 Cost Control (cont.)
13
3.3.3 Earn Value and S-Curve
14
Important Terms
• Time-now is the date when progress is measured
• Budget at Completion (BAC) is the original cost estimate
indicating the funds required to complete work
• Percentage Complete (PC) (planned) is the planned
work progress up to time-now
• Percentage Complete (PC) (actual) is the actual work
progress up to time-now
• Earned Value (EV) is the budgeted cost of work actually
completed on that point of time (based on budgeted rates).
EV = PC(actual) x BAC eg 25% x RM 2,500,000 =RM 625,000
Schedule Variance
= EV – PV = $5,000 – $7,500 = - $2,500
Schedule Performance Index (SPI)
= EV/PV = $5,000 / $7,500 = .66
Cost Variance
= EV – AC = $5,000 - $9,000 = - $4,000
Cost Performance Index (CPI)
= EV/AC = $5,000 / $9,000 = .55
Overspend
Budget At Completion (BAC)
100%
AC Schedule
PV Variance
(total actual
cost) (planned wk
done wrt
budget)
EV Cost
(actual wk Variance
done wrt
budget)
Time-now Slippage
Time
Time of completion
22
S CURVE
Completion
100%
Planned / scheduled
Unachieved
Work
Job
Start Actual /
(Earned
0%
Time-now Time
Q. Why “S” shape ?
24
3.4 Resource Allocation and
Leveling (cont.)
STEPS:
25
3.5 Control in Project
Termination
The Project Manager will continuously monitor,
control and manage the project to ensure the good
progress.
26
3.6 Control in Project
Completion and Handing Over
If then project has been successfully completed,
then PM must certify this
28
End of Lecture
Thank you
29