Professional Documents
Culture Documents
• Planninginvolves identification
of a task or tasks that need to
occur
• Scheduling involves assigning
the future action needed to
accomplish a given task to occur
on a certain date and time
• it provides schedule component
names, definitions, structural
relationships & formats that
support the application of a
scheduling method
• one of the factors that influence
the sequence activities process
Program Evaluation
GANTT Chart
& Review Technique
1 2
An arrow placed in the network must satisfy two
basic questions:
wall footing
Principle No. 3
The network(arrow diagram) does not describe time
relationships but rather dependency relationships. The
length and direction of an activity arrow has no relationship
to the amount of time required to accomplish the work
presented by it. Similarly, two activities starting with the
same event do not necessarily occur at the same time.
B
3
1 A 2
C
4
Principle No. 4
That the Network(arrow diagram) is hardly ever
done by a single person because the
accomplishment of the schedule made from the
network is influenced by several number of people
who have anything to do with the project and
should be consulted when making the network.
The use of Dummy:
Dummy is an arrow on a network showing the
dependent relationship between two activities.
However, dummy activity does not represent actual
work efforts, and do not consume time.
A C A C
X Y
B D B D
Both A and B must be D depends on A and B
completed before C can start. C depends on A only.
D depends only on B not A. Y is a dummy.
X is called dummy.
1. Activity
- the work operations required to complete a
task or in short, is the actual work between
events.
Excavation
2 3
2. Events
- is a point in time signifying the beginning or
end of one or more activities.
Dummy Activity
- an arrow on a network showing the dependent
relationship between two activities. Does not
represent actual work efforts and do not consume
time. They may used to distinguish between two or
more parallel activities.
Path
- a sequence of activities that leads from the
starting node to the finishing node
Critical Path
- longest route in the network of activities
representing a project. The sum of the activities
duration along this route is the duration of the
projects.
Earliest Event
- earliest occurrence time of an event sometimes
called earliest event Time or Early Event Time. It
is the earliest time an event can happen without
delaying the Earliest start of any activity.
Earliest Start
- earliest start of an activity cannot be earlier
than the earliest event time of the event. In
other words, the Earliest Start of any activity is
always equal to the Earliest Event at the
beginning of an arrow which is sometime called i-
node. The point of an arrow is called j-node.
i-node j-node
Earliest Finish
- earliest finish of an activity is equal to its
Earliest Start plus its duration.
Latest Event Time
- is the latest time the event may occur
without delaying project completion.
Latest Finish
- latest finish of an activity cannot be later than
the latest time of its j-node.in short, all activities
with the same j-node have the same late finish
which is the same as the latest event time at
their common node.
Activity Total Float or Activity Total Slack
- span of time an activity can be delayed after its
earliest start time w/o delaying project
completion. It is numerically equal to the Total
Time for the activity minus the Activity duration.
Free Float
- refers to the amount of extra time that exists
for an activity when all activities preceding it
start at their Early Start date.
1. All events should be numbered starting from
left to right.
2
1
3 5 6
4
1. Use pencil in constructing precedence diagram
2. Activities without predecessors are placed at the
start of the network (left side)
3. Activities with multiple predecessors are located
at path intersections
4. Start with a single node and end with a single
node
5. Avoid having paths that cross with each other.
6. Number nodes from left to right.
7. Activities should go from left to right.
8. Use only arrow between any pair of nodes.
1. Use pencil in constructing precedence diagram
2. Activities without predecessors are placed at the
start of the network (left side)
3. Activities with multiple predecessors are located
at path intersections
4. Start with a single node and end with a single
node
5. Avoid having paths that cross with each other.
6. Number nodes from left to right.
7. Activities should go from left to right.
8. Use only arrow between any pair of nodes.
The method offers the solution through systematic
approach. Specific information provided by this are
enumerated as follows:
1.) PERT/CPM pinpoints the particular work
operations whose completion times are responsible
for controlling the completion date.
12
8 14 5
1 2 3 4 6
10 8
7 9 10
0
4 0
6 12
5 12 8
Computation of Early Start (ES) & Early Finish (EF)
Activities Time ES D EF
1 – 2 Demolition & Clearing 8 0 + 8 = 8
2 – 5 Underground Installations 6 8 + 6 = 14
2 – 3 Excavation 14 8 + 14 = 22
3 – 4 Foundation & Columns 5 22 + 5 = 27
4 – 5 Dummy 0 27 + 0 = 27
4 – 6 Construction of 2nd Floor 6 27 + 6 = 33
4 – 7 Roof Framing & Roofing 6 27 + 6 = 33
5 – 7 Ground Floor Slab 4 27 + 4 = 31
5 – 8 Mech. & Elect. Services 12 27 + 12 = 39
6 – 7 Const. of Interior Walls 12 33 + 12 = 45
7 – 8 Dummy 0 45 + 0 = 45
7 – 9 Const. of Interior Partitions 10 45 + 10 = 55
8 – 9 Mech. & Elect. Equip. & Fixtures 12 45 + 12 = 57
9 – 10 Painting & Finishing 8 57 + 8 = 65
Diagram showing the Early Start and Early Finish
27
6
6
12
8 14 5 39
1 2 3 4 6 47 57 65
0 27 8 22 33 10 8
7 9 10
0
45
4 0
41 12
6 12
5 8
33 45
Compute for the value of last
start(LS) and the Last Finish(LF).
This is done by working back from
node 10 to node 1 starting from
the highest value of EF=65.
Computation of Last Start (LS) & Last Finish (LF)
Activities Time LF D LS
10 – 9 Painting & Finishing 8 65 - 8 = 57
9 – 8 Mech. & Elect. Equip. & Fixtures 12 57 - 12 = 45
9 – 7 Const. of Interior Partitions 10 57 - 10 = 47
8 – 7 Dummy 0 45 - 0 = 45
8 – 5 Mech. & Elect. Services 12 45 - 12 = 27
7 – 6 Const. of Interior Walls 12 45 - 12 = 33
7 – 5 Ground Floor Slab 4 45 - 4 = 41
7 – 4 Roof Framing & Roofing 6 45 - 6 = 39
6 – 4 Construction of 2nd Floor 6 33 - 6 = 27
5 – 4 Dummy 0 33 - 0 = 33
4 – 3 Foundation & Columns 5 27 - 5 = 22
5 – 2 Underground Installations 6 33 - 6 = 27
3 – 2 Excavation 14 22 - 14 = 8
2 – 1 Demolition & Clearing 8 8 - 8 = 0
Diagram showing the Last Start and Last Finish
33
6
6
0 8 22 27 12
8 14 5
1 2 3 4 6 33 45 55 65
10 8
31 7 9 10
0 57
4 0
27 45 12
6 12
5 8
14 39
Compute for the value of float = LF - EF
Activity Time Start Finish Float
ES LS EF LF Total Free