Professional Documents
Culture Documents
Cost Management - IT
Cost Management - IT
ITPM PROJECT ON
COST MANAGEMENT
• Projected costs are calculated during the planning phase of a project and
must be approved before work begins.
• Once the project is completed, predicted costs vs. actual costs are
compared, providing benchmarks for future cost management plans and
project budgets.
AMITY BUSINESS SCHOOL
Features of EVA
• Earned Value Analysis is an objective method to measure project performance
in terms of scope, time and cost.
• EVA metrics are used to measure project health and project performance.
• Earned Value Analysis is a quantitative technique for assessing progress as the
software project team moves through the work tasks, allocated to the Project
Schedule.
• Total hours to complete the project are estimated and every task is given an
Earned Value, based on its estimated (%) of the total.
• Earned Value is a measure of ‘Progress’ to assess ‘Percentage of Completeness’
AMITY BUSINESS SCHOOL
• Planned Value (PV) – The approved cost baseline for the work package. It was
earlier known as Budgeted Cost of Work Scheduled (BCWS).
Planned Value = (Planned % Complete) X (BAC)
• Earned Value (EV) – The budgeted value of the completed work packages.
It used to be known as Budgeted Cost of Work Performance at a specified
point (BCWP).
Earned Value = % of completed work X BAC (Budget at Completion).
• Actual Cost (AC) – The actual cost incurred during the execution of work
packages up to a specified point in time. It was previously called Actual Cost of
Work Performed (ACWP).
• Cost Performance Index (CPI) = EV / AC
• Schedule Performance Index (SPI) = EV / PV
Example AMITY BUSINESS SCHOOL
Suppose you are managing a software development project. The project is expected to be
completed in 8 months at a cost of Rs 10,000 per month. After 2 months, you realize that the
project is 30 percent completed at a cost of Rs40,000. You need to determine whether the project
is on-time and on-budget after 2 months.
• Step 1: Calculate the Planned Value (PV) and Earned Value (EV)
From the scenario,
• Budget at Completion (BAC) = Rs10,000 * 8 = Rs 80,000
• Actual Cost (AC) = Rs 40,000
• Planned Completion = 2/8 = 25%
• Actual Completion = 30%
Therefore,
• Planned Value = Planned Completion (%) * BAC = 25% * Rs 80,000 = Rs 20,000
• Earned Value = Actual Completion (%) * BAC = 30% * Rs 80,000 = Rs 24,000
Step 2: Compute the Cost Performance Index (CPI) and Schedule Performance Index (SPI)
• Cost Performance Index (CPI) = EV / AC = Rs24,000 / Rs40,000 = 0.6
• Schedule Performance Index (SPI) = EV / PV = Rs24,000 / Rs20,000 = 1.2
Interpretation: Since Cost Performance Index (CPI) is less than one, this means the project is
over budget. For every Rupee spent we are getting 60 paisa worth of performance. Since
Schedule Performance Index (SPI) is more than one, the project is ahead of schedule. However,
this has come at a cost of going over budget. If work is continued at this rate, the project will be
delivered ahead of schedule and over budget. Therefore, corrective action should be taken.
AMITY BUSINESS SCHOOL
b) Still time to recover – In case, the project is not going as per schedule and may
get delayed, the situation is needed to be taken care of by finding out the reasons that
are causing delay and taking the required corrective action.
c)Timely request for additional funds – While there is time to recover, the need for
additional resources or funds can be escalated with an early warning.
AMITY BUSINESS SCHOOL
THANK YOU