Professional Documents
Culture Documents
• Planned Value (PV) = the budgeted amount through the current reporting period
• Earned Value (EV) = total project budget multiplied by the % of project completion
• Schedule Performance Index (SPI) calculation: SPI = EV/PV
• SPI measures progress achieved against progress planned. An SPI value <1.0 indicates
less work was completed than was planned. SPI >1.0 indicates more work was
completed than was planned.
• Cost Performance Index (CPI) calculation: CPI = EV/AC
• CPI measures the value of work completed against the actual cost. A CPI value <1.0
indicates costs were higher than budgeted. CPI >1.0 indicates costs were less than
budgeted.
• For both SPI and CPI, >1 is good, and <1 is bad. Note that if you’re in a hurry,
for both cost and schedule, you can subtract instead of dividing to get the
variance. Schedule variance = EV-PV, and cost variance = EV–AC. Subtracting
can quickly be done in your head, and for these cases, >0 is good, and <0 is
bad. But unlike SPI and CPI, variance cannot be effectively compared across
projects or over time, where the budget for a project may have changed,
because they’re relative to the size of the project.
• Because CV is positive and CPI is >1, the project is considered to be under budget.
We’re 50% of the way through the project, but our costs so far are only 45% of our
budget. If the project continues at this pace, then the total cost of the project (EAC)
will be only $90,000, as opposed to our original budget of $100,000.
REMEMBER:
• Take care not to rely solely on earned value — it represents a single objective data point.
Earned value can change quickly, and actual costs and project progress rarely occur as
budgeted. However, earned value does serve as an excellent early-warning system, and
looking at earned value trends can provide very useful data. It’s most common to report
earned value monthly, but this could be more frequent for a shorter project.
• Customer satisfaction and quality aren’t captured within earned value calculations.
• It’s important to make sure all actual costs are included in your calculations
• earned value calculations can help a project manager identify problems early and be more
proactive as opposed to “after the fact” and reactive. EV metrics are defined in a standard
manner, and the data is available to be reported regularly across the project portfolio.
Cost and Risk Control
Cost Control
Project Cost Management
• Cost is one of the key performance indicators
of the project. Involved in controlling costs are
processes centered around planning,
estimating, budgeting , financing and
managing cost so the project can be
completed within the approved budget.
A critical part of Project Management is the ability to
control costs even when uncertainty prevails. The tight
connection between cost and risk forces the Project
Manager to plan and respond decisively. Any failure to
appropriately respond to risks can make the project over
budget, behind schedule, or mired in litigation.
Project Cost Management
• It is the task of overseeing and managing project expenses
as well as preparing for potential financial risks. This job is
typically the project manager's responsibility. Cost
control involves not only managing the budget, but also
planning, and preparing for potential risks. Risks can set
projects back and sometimes even require unexpected
expenses. Preparation for these setbacks can save team
time and potentially, money.
Factors
•Cost estimating
•Cost budgeting
•Cost control
Cost Estimating
• Developing an approximation or estimate of the costs of the resources needed to
complete a project.
• Includes identifying and considering various costing alternatives.
Cost Budgeting
• Allocation of overall cost estimates to individual work item in order to establish a
cost baseline for measuring project performances
Cost Control
• Controlling changes to the project budget
• Infuencing the factors which creates changes to the budget to ensure that changes
are beneficial
• Managing the actual changes when and as they occur.
Objectives of Cost Control
• To have a knowledge of the profit and loss of the project throughout the duration of
the project.
• To have a comparison between the actual project performance and that conceived in
the original project plan
• Provides feedback data on actual project performance to future project planning.
Techniques of cost control
• Earned value management
• Forecasting
• Cost variance
• Cost performance index
Earned Value Management
• It compares the amount of work that was planned with that was actually planned
earned with what actually spent to determine if cost and schedule performance are
as planned.
Earned Value Management
• Planned Value (PV) – is the budgeted cost for the work
scheduled to be completed on an activity.
• Earned Value (EV) – is the budgeted amount for the work
actually completed on the scheduled activity
• Actual Cost (AC) – the actual cost incurred in
accomplishing worn on schedule activity
Earned Value Chart
• The chart helps visualize how the project is performing
• Example
If the project goes as planned, it will in 12 months at cost of 900,000 php
• The actual cost line is always right on or above the earned value line.
• Interpretation: this means cost are equal to or more than planned.
The planned value line is pretty close to the EV line, just slightly higher in
the last month
Interpretation: the project has been right on schedule until last month
when the project fell behind schedule.
Forecasting
• Forecasting includes making estimates or predictions of conditions
in the project’s future based on the information and
knowledgeable available at the time of the forecast. As the project
progresses, the forecast adjusted.
Cost Variance
• The cost variance at the end of the project will be the difference
between the budget at the completion and the actual amount
spent.
• Example : if a project has a earned value of £20,000 but actual costs were
£12,000.
• If the ratio has a value higher than 1 then it indicates the project is
performing well against the budget. A CPI of 1 means that the project is
performing on budget. A CPI of less than 1 means that the project is
over budget.
Risk Control
What is risk?
• Risk
• It is the possibility of loss or injury
• It is everywhere
• Driving a car
• Walking down the street
• Travelling, etc.
• Project Risk
• Part of any project and represents the uncertainty element in the project
• Unplanned events or conditions that can have an effect on the project.
• Can have negative or positive effect
Types of risk
• Financial risk – material cost, market demand, improper
estimation, inflation, payment delays, unmanaged cash flows and
financial incompetence of the contractor pose a huge threat
• Socio-political risk – government laws and regulations, payment
failure by the government, increase in taxes
• Environmental risk – inclement weather conditions, natural
disasters, accessibility to the site, pollution
• Construction-related risks – failure of logistics, labor disputes,
design changes, labor productivity, rush bidding, time-gap for
revision of drawings, accidents, equipment failures
Level of risk
• High risk: substantial impact on cost, technical performance ,
or schedule. Substantial action required to alleviate issue.
High-priority management attention is required
Risk management
• Project risk management is an activity undertaken to lessen the impact of
potentially adverse events on the projects.
• Risk management can help improve projects success by helping select good
projects, determining project scope, and developing realistic estimates.
• The goal of project risk management is to minimize potential negative risks while
maximizing potential positive risk
Risk management process
• It is deciding how to approach the risk
• This plan summarizes the result in risk identification, quantitative &
qualitative analysis and response method.
• It also include contingency plan which is a predefined action that a
project team will take if an identified risk event occurs.
• Contingency plans – are predefined actions that the project team will
take if an identified risk event occurs
• Fallback plans – are developed for risks that have a high impact on
meeting project objectives and are put on meeting project objectives
and are put into effect if attempts to reduce are not effective.
Risk management process
Risk identification
• It is the process of gaining understanding of the potentially unsatisfactory
outcomes that can occur to the project.
• Historical information can help identifying the areas where risk is high
• Tools and techniques
• Documentation reviews
• Quality of the plans, as well as consistency between those plans and the
project requirements and assumptions, may be indicators of risk in the
project.
• Information Gathering Techniques
• Include brainstorming, Delphi technique, interviewing, root cause analysis.
• Delphi Technique - a facilitator uses a questionnaire to solicit ideas about
important project risks. The responses are summarized and then re-
circulated to the experts
Checklist analysis
• Are developed based on historical information and knowledge that has been
accumulated from previous similar projects and from other sources of information.
Assumption analysis
• Explores the validity of assumptions as they apply to the project. It identifies risk to
the project from inaccuracy, instability, inconsistency, or incompleteness of
assumptions
SWOT Analysis
• Examines the project from each of the strengths, weakness, opportunities, and
threats (SWOT) perspectives to increase the breadth of identified risk.
Risk diagramming techniques
• Risk diagramming techniques
• Include cause and effect diagrams, process flow chats and influence
diagram.
• Process flow charts - shows how different elements of a particular
system relate with one another. It also deals with the causal
mechanisms of the risk.
• Cause and effect diagrams: This type of diagram is also called the
fishbone or Ishikawa diagram and it is used to identify the different
causes of risks.
• Influence diagram: Influence diagrams are graphical presentations of
different situations that show causal influence in time ordering
events
Risk diagram (fishbone or Ishikawa diagram )
Two methods of risk analysis
• Qualitative approach
• Quantitative approach
• Probability and impact matrix – the matrix maps out the risk, its
probability and its possible impact. The risk with higher
probability and impact are more serious treat to the project.
• Risk categorization - risk to the project can be categorized by
source of risk, or other useful categories to determine the areas
of the project most exposed to the effects
Probability and impact matrix
Quantitative Risk Analysis
• Tools & techniques
• Expected Monetary Value Analysis – it computes the expected monetary
outcome (according to different statistical criteria) pof a decision/risk
• Three Point Estimate - a technique that uses the optimistic, most likely,
and pessimistic values to determine the best estimate.
• Decision Tree Analysis - a diagram that shows the implications of choosing
one or other alternatives.
• Sensitivity analysis – a technique used to determine which risks have the
greatest impact on a project.
• Monte Carlo analysis – is a technique used to understand the impact of
risk and uncertainty in project management. by running simulations to
identify the range of possible outcomes for a number of scenarios.
Monte Carlo analysis
Expected Monetary Value Analysis
Three Point Estimate
Risk response planning
• The process of developing options and actions to enhance
opportunities and to reduce threats to project objectives.
• The key benefit of this process is that it addresses the risks by
their priority.
• Risk avoidance – trying to eliminate some or all the risk involved
• Risk acceptance – just accepting the consequences of the risk
• Risk transference – involved third parties like using insurance,
warranties
• Risk mitigation – involve reducing the impact of the risk event
by reducing the probability of occurrence.
Risk monitoring and control
• The process of implementing risk response plans, tracking identified risks,
monitoring risks, identifying new risk, and evaluating risk process
effectiveness throughout the project.
• The key benefit of this process is that it improves efficiency of the risk
approach throughout the project life cycle to continuously optimize risk
responses.