Chapter 4 Economic Dispatch
Chapter 4 Economic Dispatch
Chapter 4
ECONOMIC DISPATCH AND UNIT COMMITMENT
A two bus system is shown in fig. If 100 MW is transmitted from plant 1
to the load, a transmission loss of 10MW is incurred. Find the required
generation for each plant and the power received by load using Penalty
Factor method, when the system incremental cost is Rs 25/MW-hr. the
cost equation of the two plants are given below:
P1 P2
Load