REKAPITULASI KEGIATAN WO & WS

TALANGJIMAR – REGION SUMATRA

SUMUR WORK OVER


&

WORK SERVICE
STRUKTUR TALANG JIMAR HAL: 01 / 07

SMR.
RENCANA AWAL RENCANA AKHIR
PRODUKSI
BIAYA BIAYA
No No.SMR KEGIATAN KEGIATAN KETERANGAN
($) ($)
1 TLJ.033 WO 402,500 WS 389,027
PROBLEM TEKNIS,
2 TLJ.046 WO 432,528 WS ---- ADA IKAN

3 TLJ.058 WO 405,000 WS 385,116


4 TLJ.063 WO 410,000 WS 406,728
5 TLJ.064 WO 400,000 WS 386,030
6 TLJ.075 WO 410,000 WS 378,146
7 TLJ.082 WO 380,000 WS 340,418
8 TLJ.182 WO 445,000 WO 433,265

SUB TOTAL 1: SMR PRODUKSI 2,718,730


STRUKTUR TALANG JIMAR HAL: 02 / 07

SMR.
RENCANA AWAL RENCANA AKHIR
PRODUKSI
BIAYA KEGIATA BIAYA
No No.SMR KEGIATAN KETERANGAN
($) N ($)
9 TLJ.193 WO 439,000 WS 324,202
10 TLJ.228 WO 460,000 WO 375,925
11 TLJ.055 WO 430,000 WS 391,344
12 TLJ.073 WS 390,000 WS 389,742
13 TLJ.203 WS 400,000 WS 352,054

SUB TOTAL 2: SMR PRODUKSI 1,833,267

SUB TOTAL 1: SMR PRODUKSI 2,718,730

TOTAL SUMUR PRODUKSI : 4,551,997 TAHUN 2011


STRUKTUR TALANG JIMAR HAL: 03 / 07

SMR. PRODUKSI RENCANA AKHIR

BIAYA
No No.SMR KEGIATAN KETERANGAN
($)

1 TLJ.182 WO 433,265
2 TLJ.228 WO 375,925

TOTAL WO SUMUR RODUKSI : 809,190 TAHUN 2011


STRUKTUR TALANG JIMAR HAL: 04 / 07

SMR. PRODUKSI RENCANA AKHIR

BIAYA
No No.SMR KEGIATAN KETERANGAN
($)
1 TLJ.033 WS 389,027
2 TLJ.058 WS 385,116
3 TLJ.063 WS 406,728
4 TLJ.064 WS 386,030
5 TLJ.075 WS 378,146
6 TLJ.082 WS 340,418

7 TLJ.193 WS 324,202

8 TLJ.055 WS 391,344

SUB TOTAL 1: WS SMR PRODUKSI 3,001,011


STRUKTUR TALANG JIMAR HAL: 05 / 07

SMR. PRODUKSI RENCANA AKHIR

BIAYA
No No.SMR KEGIATAN KETERANGAN
($)
9 TLJ.073 WS 389,742
10 TLJ.203 WS 352,054

SUB TOTAL 2: WS SMR PRODUKSI : 741,796

SUB TOTAL 1, WS SMR PRODUKSI : 3,001,011

TOTAL WS SUMUR PRODUKSI : 3,742,807

TOTAL WO SUMUR RODUKSI : 809,190

GRAND TOTAL WO & WS


4,551,997 TAHUN 2011
SUMUR PRODUKSI :
STRUKTUR TALANG JIMAR HAL: 07 / 07

SMR. PRODUKSI RENCANA KEGIATAN 2011


BIAYA
No No.SMR KEGIATAN KETERANGAN
($)
1 TLJ.075 WS 378,146 Tubing 1300m + Beam pump + SRP

2 TLJ.193 WS 324,202 Tubing 1300m + Beam pump + SRP

Ganti WH, Tubing 1300m + Beam pump +


3 TLJ.182 WO 433,265 Rods

4 TLJ.228 WO 375,925 Tubing 1300m + Beam pump + SRP

TOTAL 4 SUMUR TLJ TH.2011 : 1,511,538


REKAPITULASI RENCANA KEGIATAN
WO & WS
TALANGJIMAR – REGION SUMATRA

SUMUR INJEKSI
STRUKTUR TALANG JIMAR HAL: 06 / 07

SMR. INJEKSI RENCANA AWAL RENCANA AKHIR

BIAYA BIAYA
No No.SMR KEGIATAN KEGIATAN KETERANGAN
($) ($)
1 TLJ.005 WO 376,860 WS 325,104

2 TLJ.007 WO 329,000 WS 212,582


3 TLJ.039 WO 300,000 WS 224,870
PROBLEM TEKNIS,
4 TLJ.042 WO 325,000 WS ---- WATER CRATER

5 TLJ.088 WO 300,000 WS 205,621


6 TLJ.096 WO 315,000 WS 226,100
SDH DIOPERASIKAN
7 TLJ.199 WO 235,000 WS ---- REGION

8 TLJ.208 WO 270,000 WS 219,146

TOTAL BIAYA SUMUR INJEKSI: 1.413.423 TAHUN 2011


REKAPITULASI RENCANA
KEGIATAN WS
LEDOK – REGION JAWA

SUMUR
WORK SERVICE
2011
STRUKTUR LEDOK HAL: 01 / 06

SMR. PRODUKSI RENCANA KEGIATAN 2011


BIAYA
No No.SMR KEGIATAN KETERANGAN
($)
1 LDK.128 WS 181,252
2 LDK.126 WS 265,000
3 LDK.151 WS 237,613
4 LDK.164 WS 249,269
5 LDK.076 WS 257,173
6 LDK.173 WS 210,913

7 LDK.201 WS 271,118

8 LDK.149 WS 263,533

SUB TOTAL 1: 1,936,143


STRUKTUR LEDOK HAL: 02 / 06

SMR. PRODUKSI RENCANA KEGIATAN 2011


BIAYA
No No.SMR KEGIATAN KETERANGAN
($)
9 LDK.085 WS 175,150
10 LDK.055 WS 175,740
11 LDK.136 WS 248,000

SUB TOTAL 2: 598,890

SUB TOTAL 1: 1,936,143

TOTAL 11 SMR PRODUKSI LDK: 2,535,033


STRUKTUR LEDOK HAL: 03 / 06

SMR. INJEKSI RENCANA KEGIATAN 2011


BIAYA
No No.SMR KEGIATAN KETERANGAN
($)
1 LDK.231 WI 138,326
2 LDK.223 WI 161,397
3 LDK.194 WI 138,506
TOTAL 3 SMR INJEKSI LDK: 438,229

TOTAL 11 SMR PROD & 3 SMR


2,986,537
INJEKSI LDK:
STRUKTUR LEDOK HAL: 04 / 06

SMR. PRODUKSI RENCANA KEGIATAN 2012


BIAYA
No No.SMR KEGIATAN KETERANGAN
($)
1 LDK.104 WS 165,466
2 LDK.057 WS 175,740
3 LDK.009 WS 181,108
4 LDK.045 WS 295,943
5 LDK.199 WS 224,704
6 LDK.003 WS 176,201

TOTAL 6 SMR PRODUKSI LDK: 1,219,162 TAHUN 2012


TATA -WAKTU KEGIATAN WORK OVER TLJ-075
TATA -WAKTU KEGIATAN WORK OVER TLJ-075
TATA -WAKTU KEGIATAN WORK OVER TLJ-075