ACTIVA PROJ

Aurora Blvd cor EDSA Cubao Quezon City


SOF # 32
Project Status
Work Progress
DESCRIPTION PRESENT PREVIOUS TO DATE

SCHEDULE 1.57% 88.28 % 89.85 %

ACTUAL 0.97 % 23.05 % 24.02 %

VARIANCE -0.60% -65.29 % -65.89 %

DAYS EQUIVALENT 2.14 Delays 235.04 Delays 237.19 Delays


Latest Billing

TO DATE %
PROGRESS
%BILLED DATE SUBMITTED REMARKS

3.78 %
26.3 % 6 July 2019 For Reconciliation (Php. 243,429.14).
Progress Photos
Progress Photos