Punch listing and Substantial Completion Procedures

Punchlisting
• Preparing a document near the end of a
construction project listing work not conforming
to contract specifications that the general
contractor must complete prior to final payment.
DPWH Procurement Manual
• Aims to put together a coherent set of clear,
complete, up-to-date, streamlined, and
simple operational rules and procedures, to
serve as common reference and guide for
DPWH and private contractors, consultants,
and suppliers in the procurement of
contracts for infrastructure, consulting
services, and goods, consistent with RA 9184
and its IRR.