The superstructure is generally constructed span-by-span.
Objectives for construction methodology for Metro projects:
• Accelerated construction – precast structural members • Reduced environmental pollution • Minimum disturbance to traffic • Durability of structural components • High quality of finishes and close tolerances • Aesthetic quality Metro viaducts • Elevated viaducts for metro structures are characterized by Precast Segmental Box Girder which are Epoxy Jointed and Internally Prestressed, generally supported on single piers on the central verge of the roadway.
Metro elevated viaducts Metro elevated viaducts supported on piers ,
using u- girder located on central verge of the road • Launching of segments has been carried out using overhead and underslung launching girders
• Segment sections that can be used - regular box girder section, U-shaped girder for 2 tracks ,I- girder, twin U-girder
• Advantage of this U-shaped section
- the side webs work as parapet, thereby saving of material - truncated top flange acts as emergency evacuation walkway. - At the same time, the rail level comes down, as the tracks are supported over the bottom slab, leading to economical designs. Pretensioned twin u-girder
Segmental 2 track u girder
Segmental box girder
Segmental box girder ,
extended Prestressed dry jointed
Pretension/ post – tension
I-beam with cast in – situ slab
types of sections that have been employed in India