PHASE 3

HANGARS PROJECT
HANGAR STRUCTURE

SCOPE OF WORK :

• STEEL STRUCTURE MATERIAL

• ROOFING MATERIAL

• STRUCTURAL DESIGN

• ENGINEERING CALCULATION
REPORT
SOIL & LANDSCAPE PREPARATION
• TOPOGRAPHY

• CUT & FILL

• SOIL COMPACTING

• CBR TEST

• COORDINATE STACK OUT

• BORING

• SOUNDIR

• FOUNDATION BORED PILE


CIVIL WORK

SCOPE OF WORK :

• ANNEX BUILDING

• HANGAR FLOORING

• APRON FLOORING

• TAXIWAY

• ACCESS ROUTE (RE-ROUTE)


UTILITY PLANT
SCOPE OF WORK :

• POWER HOUSE
- GARDU PLN
- CUBICLE
- TRAFO
- LVMDP

• AIR COMPRESSOR SYSTEM

• FIRE SUPRESSION SYSTEM

• WATER GROUND TANK (PDAM)

• WASTE (B3) GROUND TANK

• R/O WATER TREATMENT

• OVERHEAD CRANE (1 OUT OF 4


HANGAR)
MECHANICAL/ELECTRICAL & PLUMBING

SCOPE OF WORK :

• PANEL PP • AIR CONDITIONING & DEHUMIDIFIER

• SINGLE PHASE ELECTRICAL LINE • AIRCRAFT GROUNDING

• THREE PHASE ELECTRICAL LINE • ELECTRICAL TREATMENT SYSTEM

• PNEUMATIC PIPELINE • LIGHTNING PROTECTION SYSTEM

• WATER PIPELINE • LIGHTING SYSTEM (LED)

• WATER WASTE PLUMBING


IT
INFRASTRUCTURE
SCOPE OF WORK :

• FIBER OPTIC LINING

• DATA SERVER

• NETWORKING DRAWING (WIFI/LAN)

• VoIP