You are on page 1of 8

SECTION 8-9

QUESTIONS
1. Adjustment of contract price for construction projects may be
authorized by the following, except:
a. Minister of Public Works
b. Minister of Transportation and Communications
c. Minister of Energy
d. Minister of Building and Construction

 Answer: d
2. The adjustments of the contract price shall be made using
appropriate formulas established in accordance with the rules and
regulations to be promulgated under what section of this decree?
a. Section 8
b. Section 9
c. Section 12
d. Section 15

Answer: c
3. It may be issued only for works necessary for the completion of
the project and, therefore, shall be within the general scope of the
contract as bidded and awarded.
a. Mechanic’s Lien
b. Change Order
c. Certificate of Completion
d. Notice of Completion

Answer: b
SECTION 12-15
QUESTIONS
1. These shall jointly promulgate the rules and regulations to
implement the provisions of this decree.
a. The Minister of Public Works, Transportation, and
Communications
b. Minister of Public Transportation System
c. Director –General of the National Economic and Development
Authority
d. Minister of Energy

 Answer: b
2. This means that the decree shall take effect immediately.
a. Efficiency
b. Quality
c. Repeal
d. Effectivity

Answer: d
3. If any provision of this Decree is held unconstitutional, the other
provisions shall remain valid.
a. Separability Clause
b. Repeal Clause
c. Effectivity
d. Implementing Rules and Regulation

Answer: a

You might also like