Professional Documents
Culture Documents
CONSTRUCTION CLAIMS
•What are Claims
•Types of Claims
•Objectives of Claims
•Points to be considered before
proceeding
•Notices of Claims
•Interference by the Employer
•Claims against Consultants
•Construction Contracts
•Documents relating to claims
•Procedures of Claims
WHAT ARE CLAIMS?
The definition of a claim in a dictionary is
an assertion of a right to something.
PAYMENT CLAIMS
Consideration & normal, therefore excluded from this topic
TYPES OF COST CLAIMS
•Loss / expenses (Damages)
•Additional payment under
specific provisions of the contract
•Variations
•Disruption
•Prolongation
TYPES OF CLAIMS
COMMON LAW/
EX-CONTRACTUAL
CONTRACTUAL EX-GRATIA
CONTRACTUAL CLAIMS
Where the contract provides for the event or
circumstances being complained of . Clearly
this should be the first line of consideration
as it is pointless to look elsewhere and rely
upon common law rights when express
provision exists. Further, contractual matters
are usually within the powers of the
Architect/Engineer to settle. (SFBC Cl 11(6), 24
& 34(3)
EX-CONTRACTUAL /
COMMON LAW CLAIMS
• Where the contract does not make express
provision and therefore grounds outside the
contract have to be sought - i.e. in common
law.
• Such claims are usually outside the
Architect's /Engineer's power and require
specific authority from the Employer for them
to examine the claims and make appropriate
recommendations.
EX-GRATIA CLAIMS
• By definition such claims have no grounds upon
which either side could successfully sue the other
at law.
• Their only basis is that a loss has been made and
that something more tangible than sympathy is
being sought, but anything paid will be an 'act of
grace' with, at best, some possible
acknowledgement of morale obligation.
• These claims should not be resorted to if
contractual or extra-contractual claims exist.
• Ex-gratia claims are sympathy claims
CAUSES OF CLAIMS
• Late payments • Variations
• Changes in • Rejection of "or
conditions similar"
• Delay / substitutions
interference • Unclear
• Acceleration responsibilities of
• Errors / omissions the contractor /
in design / employer
document • Failure in pre-
• Suspension of the contract planning
work
OBJECTIVES OF CLAIMS
Objectives of time claims
• To extend the contract completion time
• To reduce the amount of L. D. liable to pay to the
Employer
• To prepare for the claims for the cost claims
(remember this is not automatically)
Objectives of cost claims
• To reimburse the loss & expenses incurred
• To compensate the extra preliminaries due to delay
by the faults of the Architect, etc.
Objectives of ex-gratia claims
• To ask for sympathy in compensation, which has no
contractual grounds for the claims, for the best
efforts the contractor has put.
POINTS TO BE CONSIDERED
BEFORE PROCEEDING
• Claims should be well planned at the beginning of
the contract rather than at the end of the contract
• Check the contractual grounds before claim -
contractual justification, i.e. identify the contract
condition(s)
• The event giving rise to the claim should be actually
occurred
• True cause(s) of the claim should be identified
• Surrounding circumstance relating to the claim
should be recorded
• A good claim should be well organised and
presented in a concise way
• Understand the attitude of the Employer to claims
NOTICES OF CLAIMS
A contractor MUST GIVE NOTICE of his intention to
claim extension of time or additional payment - for
whatever reason; and the notice must be given as
soon as it becomes apparent or within the time
limited set out in the contract.