Professional Documents
Culture Documents
Management
Submitted by Submitted to
M . Sufiyan Ar Sarala
2mb15at017
Costs and Project Management
Direct costs
• Direct costs are costs which are directly accountable to a cost object (such as a particular
project, facility, function or product).
• Some overhead costs which can be directly attributed to a project (e.g. a designated
project manager) may also be classified as a direct cost.
• Direct costs are directly attributable to the object. In construction, the costs of materials,
labor, equipment, etc., and all directly involved efforts or expenses for the cost object are
direct costs.
• In manufacturing or other non-construction industries, the portion of operating costs
which is directly assignable to a specific product or process is a direct cost.
• Direct costs are those for activities or services that benefit specific projects, for example
salaries for project staff and materials required for a particular project.
• Because these activities are easily traced to projects, their costs are usually charged to
projects on an item-by-item basis.
Cost Slope
Nt: Normal time
Nc: Crashing time
Ct: Cost of activity in Nt.
Cc: Cost of activity in Nc.
Cost Slope= Cc − Nc ��−��
Algorithm for Crashing
• Step1 Determine the normal Critical path and identify the critical activities.
• Step2 Calculate cost slope or increment cost per unit time for different activities.
• Step3 Rank activities in ascending order as per their cost slopes.
• Step4
i)Crash activities of critical path as per lowest cost slope first.
ii)Calculate the new direct cost by adding cost of crashing to the normal cost.
• Step5 Since Critical path duration is reduced so other path also become critical. Project
duration can be reduced by simultaneously crashing activities in the parallel critical
path.
• Step6 By crashing as per step4 and 5, a point is reached when either no crashing is
possible or crashing does not result in the reduction of project duration.
Important points
Least cost slope activity of the critical path must be dealt with first and so on.
• If more than one critical path is generated after crashing then duration of activities on all
these paths have to be curtailed.
• If time in critical path(say A) lowers below an alternative path (of time say X such that
X>A)after crashing then crashing is done here in such a way that time in critical path is kept
same as X, not below X.
• If crashing a low cost slope activity(say activity D) results in though lowering a single Critical
path time but project time is not lowered then o select common activities or activity
combinations o Find least cost slope among these.
• Sometimes before Critical path other path get crashed. Here the time of crashed path is the
minimum limit of crashing time. Critical paths are crashed down to this time limit.