You are on page 1of 6

Provision of Bus section in present

scheme of 33KV Bay extension work in


form of indoor GIS Bay
Introduction
• Construction of 33KV line bays in form of indoor GIS system
were carried out in 11 Grids under Transmission Circle, Patna
against ICB No. 30/Package J-1/ BSPTCL/ADB/2016.
• General Arrangement and schematic drawing of Bus section
has already been approved for construction of 33KV Line bays
using indoor GIS system.
• However, provision of Bus section was not considered due to
paucity of loan amount under ADB loan scheme.
• Later, it has been felt necessary to provide Bus section in
order to ensure uninterrupted power supply.
Technical requirement of Bus
sectionalizer
• Without bus section, in case of failure/ or maintenance
work of any of the incoming feeder all outgoing feeder of
that section will be out of order.
• If bus section is provided in system it will improve power
availability and stability in the system as power can be
extended from any one of the incomer.
• Also, any maintenance work on one incomer can be
easily carried out without interrupting power supply to
other outgoing feeder.
Space availability for installation of Bus
section :-
• During construction of 33KV line bays in form of GIS
System, required space for installation of Bus section
panel have already been considered.
• As such there is space available at all the Grids having
33KV line bays in form of GIS system.
• 33KV Line Bays in form of indoor GIS system have been taken up only
in 11 Grids under Patna(East) and Patna(West) circle. List of such
Grids are as below:-
S.no Name of Grids No. of 33KV Outgoing
feeder
1 Fatuha 5
2 Jakkanpur 5
3 Masaurhi 5
4 Bihta 5
5 Barh 7
6 Meethapur 7
7 Katra 7
8 Khagaul 10
9 Gaighat 10
10 Digha 10
11 Sipara 10
• Provision of supply of bus section may only be considered in only
these Grids.
Estimated Cost
• As per the budgetary offer obtained from M/s Schneider, Transmission Zone,
Patna has submitted estimate amounting to Rs. 7,28,84,002 (Rs. Seven Crore
Twenty Eight Lacs Eighty Four Thousand and two) including GST.
• The breakup of estimate has been detailed below:
S.no. Description Unit Qty Unit Price Total Price

1 Supply of 33KV Bus section Panel(2500A) Nos. 11 45,00,000 4,95,00,000


Cable for remote operation from Console
2 Panel
2.a. Control Cable 14CX 2.5 sqmm (Cu) km 5 3,49,376 17,46,880
2.b. Power Cable 4C X 16 sqmm (Al) km 2 1,28,148 2,56,296
Total Price of supply
5,15,03,176
Freight & Insurance Charges20,60,127.04
Total Price for erection and commissioning 85,17,057.00
1,08,03,641.9
GST @ 18% 4
7,28,84,001.9
Total Price for complete Work 8