Weather & Material Status

Date : 11 March 2020

Weather
1. Weather : Clear

CIVIL MATERIAL REPORT


1. Cement : 130.20 Ton (In : 0 T, Out : 20.00 T)
2. Crushed Stone : 450.30 M3 (In : 0 M3, Out : 27.00 M3)
3. Sand : 137.40 M3 (In : 0 M3, Out : 30.00 M3)
4. Reinforcing Bar : 20.00 Ton (In : 20.00 T, Out : 5.00 T)

CIVIL ACTIVITIES
1. Pouring Concrete, Total : 33.00 m3
a. Plant Road – Second layer : 33.00 m3

2. Rebar Fabrication : 5.00 Ton, Installation : 5.00 Ton


3. Formwork Fabrication : 10.00 m2, Installation : 10.00 m2

Note : -