You are on page 1of 12

PI Internal

SAP PM PROJECT OPTIMISATION@ JAMBUSAR


SEP’18
PI Internal

Sr. Process Status Remarks


No.
1 Preventive Maintenance Process implemented, but master data not
updated, thus system not generating planned
orders.

2 Calibration Order Process implemented, but due to lack of


training and unavailability of proper master
data, process not being used.
3 Breakdown Maintenance Process implemented but not being used in
correct manner, thus system not able to
generate critical breakdown analysis.
PLANT MAINTENANCE CURRENT STATUS @ PI
4 Condition Monitoring Process implemented, but due to lack of
training and unavailability of proper master
data, process not being used

5 Shutdown Maintenance Process not implemented.

6 Permit Management Not being used.


Project
PI Internal: SAP Plant Maintenance

Key Milestones : Published Duration Baseline Start Baseline Finish Actual /Expected Responsible Status
Finish
SAP Plant Maintenance Process Streamlining 120 days 01-08-18 30-11-2018    To be started

SAP PM Kick OFF Meeting 10 01 08 2018 10 08 2018 25 July’18 JR Completed


Scope:
Streamlining of SAP Plant Maintenance
Level One training for Core Team process and implementation of additional
10 01 08 2018 10 08 2018 03 Aiug’18 JR Completed
members
processes which are not being used
      Business requirement document preparation 20 13 08 2018 31 08 2018 To be started currently.
      Business Blue print document Preparation
and signoff
20 01 09 2018 20 09 2018 To be started

   Master data collection (Parallel activity) 60 01 08 2018 31 09 2018    To be started


Project Team
      Realization 30 21 09 2018 20 10 2018    To be started Project sponsor   : VS
      20 % Master Data upload 10 22 10 2018 31 10 2018    To be started Project Owner     : RT
      UAT & Signoff 10 01 11 2018 09 11 2018    To be started IT Lead : JR
   Master Data upload 100 % (PRD) 10 12 11 2018 20 11 2018    To be started Project Team :
      End User training 7 21 11 2018 27 11 2018    To be started
CoreLevel
High TeamScope BRD :
Mr. Hardik Bhatt (Utility dept.)
      Go-live 3 28 11 2018 30 11 2018    To be started
Mr. Nimesh Patel (Utility dept.)
      Post Go-live support    
Mr. Pritam Patel (Electrical dept.)
Mr. Aman Joshi (Mechanical dept.)
Recent Updates Upcoming Key Activities
Mr. Chintan Anadkat (Inst. Dept.)
 Formal kick-off meeting for Plant Maintenance improvement  Session two for PM improvement project, on PM critical
Mr. Vasant Sojitra
project done. Master data.
Mr. Rohitpratap Singh
 Identification of core team and Power users done for Jambusar  Discussion with Core team and Power user’s for As-Is and To-
Mr. Amit D Saraswat
Plant. Be documentation.
Mr. Ajay Kumar Dubey <
 Session One for PM improvement project done.
 Level one training for Core team member's done.

Key Risks and Issues Required Decisions & Support


 Master data collection & Standardizations  Incorporation of Project into SLAs of Biz Owners.
 Availability of Core Team .
PI Internal SAP PM PROJECT METHODOLOGY

SAP PM Reconfiguration to meet TO-BE Process


SAP PM Core Team Fully Trained in Jambusar Unit
Standardised Master Data and Equipment BOM
Process Documentation and Training

How We are Going to reach there


(GAP ANALYSIS) How We shall know we have arrived
(Project Deliverables)

Preventive Maintainence Through SAP


Under-utilization of the system due Complete Equipment Hierarchy
to lack of Training Paperless System
Reactive Mode of Working Where we want to go Easy data Retrivation for Audit
Incomplete equipment/asset TO-BE Online permit system with auto Notification
structures
Desire for more proactive vs. reactive environment
Manual Process and Reporting Proactive Planning for Daily, Weekly. Monthly
Uptime/Availability with Improved OEE
Online Visibility on Costs/Planning Basis
Expense Monitoring
Current SAP does provide the kinds Planning & Budgeting
Complete Visibility of Maintainence Operations
of data needed to make better Failure Analysis
decisions. Reduced Downtime MTTR and MTBR through SAP
Budget and Inventory Control 5 Why and 8D Analysis through SAP
Determine where we are Improved Service to User Departments
Better Collaboration within and Outside Departments Online Legal compliance (Form No 9,10,11 IBR)
AS-IS
Online Approval of Gate Pass
Spares Inventory Control with Maint. SLOC
Online Reporting for Expenses
PM BOM with Critical Spares List
PI Internal Project : SAP Plant Maintenance

S.NO. Main Process


1 S.NO. Support Process
Breakdown Maintenance
2 1 Gate pass creation
Preventive Maintenance
3 2 Water Tanker Process
Corrective Maintenance
4 3 Reporting & MIS
Condition monitoring
5 3 Spares Inventory Management
Shutdown Maintenance
6 4 PR and PO Tracking
Calibration Process
7 5 Legal compliance (Form No 9,10,11 IBR)
Modification/CAPEX Order
6 Waste lube oil generation (life cycle)

7 Budgeting and Expenses Reporting


PI Internal

Maintenance Work Order Process Flow

10 Maintenance Required 1
Close Work Order
Cost Object

9 Settle Order Costs Create Notification 2


Scheduled
Scheduled
(Planned)
(Planned)
8 Enter Part and Work Order Maintenance Maintenance
Maintenance
Work Order
Damage Code Cycle Create Work Order 3

7 Time Confirmations
Plan Work Order 4

6 Perform Work Release Work 5


Order
PI Internal
ROOT CAUSE ANALYSIS
PI Internal
HOW THIS IS DONE IN SAP

8
PI Internal
HOW ACTIVITIES ARE ENTERED

9
PI Internal
BREAKDOWN ANALYSIS REPORT

10
PI Internal
BREAKDOWN MAINTENANCE CRITICAL REPORTS
PI Internal
COST ANALYSIS REPORT SAMPLE SNAPSHOTS

You might also like