Professional Documents
Culture Documents
04HDM 4EconomicAnalysisConcepts2008 10 22
04HDM 4EconomicAnalysisConcepts2008 10 22
3
Appraisal Framework
a) Forecasting changes
b) Evaluating those changes
4
Components of Economic Analysis (1)
5
Components of Economic Analysis (2)
8
Benefits from Road Investment
10
Primary Effects (1)
11
Primary Effects (2)
12
Secondary Effects
13
Consumers’ Surplus Approach
14
Normal and Generated Traffic Benefits
Cost +
C1 Additional benefits to
Generated traffic
C2
Demand Curve
(Price Elasticity of Demand)
T1 T2 Traffic
Normal Generated
15
Generated Traffic Benefits
16
Producers’ Surplus Approach
• Captures secondary benefits
• Advantages: Draws attention to changes in
agricultural output (key economic activity in rural
areas)
• Disadvantages: No reliable way of predicting response
- impact studies give widely different answers
- it could be based on agricultural supply price
elasticities but this is almost never done; it requires
very careful examination to use.
• For most projects benefits are just invented !
17
Producers’ Surplus
Output O1 O2
18
Coverage and Double Counting
19
Economic Comparisons
22
Benefits of Upgrading to a
Motorable Track
Headloading
C1
Track
Costs
Improved
road
C2
C3
T1 Traffic T2 T3
23
Cost Effectiveness Against
Standard of Road
24
Development Benefits
25
Estimating Benefits
Normal traffic benefits: tripsN * d1 * (VOC1- VOC2)
VOC data relates to each road section and its condition at the
time
26
Economic Decision Criteria (1)
27
Economic Decision Criteria (2)
• Payback Period
28
Economic Decision Criteria (3)
Notes:
1. check for robustness to changes in key variables (sensitivity analysis)
2. with incremental analysis
3. IRR may be indeterminate with NONE or MANY solutions.
29
Present Value Calculation
Period Flow
0 A0 PV(A0) = A0
1
2
3
4
5 A5 PV(A5) = A5 / (1 + i ) ^ 5
6
7
PV(Aj) = Aj / (1+ i ) ^ j
PV(Aj) = Present Value of Aj
Aj = Amount at year j
i = Discount rate
j = Year
30
Present Value at 12.0% Discount Rate
31
Discount Rate
34
NPV Decision Rule
35
NPV and IRR Calculation (1)
Discount Net
Rate (i) Discount Present
12.0% Rate (i) Present
36
NPV and IRR Calculation (2)
8000
4000
2000
Internal Rate
of Return
0
0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0%
-2000
-4000
Discount Rate (%)
37
NPV Versus IRR
10000
8000
NPV at 12%
Discount Rate
6000
Net Present Value (M$)
4000
Internal Rate
2000
of Return
0
0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0%
-2000
-4000
Discount Rate (%)
- The IRR and NPV will not necessarily rank the alternatives by the same order
- Always use NPV to compare project alternatives
38
Multiples Rates of Return
Net
Year Benefits Multiple Rates of Return
0 -500
1 1150
2 -660 2.00
NPV at 12% 0.64
IRR #1 10%
IRR #2 20% 0.00
0% 5% 10% 15% 20% 25% 30% 35%
Discount
-2.00
Rate NPV
Net Present Value (M$)
0% -10.0
2% -6.9
-4.00
4% -4.4
6% -2.5
8% -1.0 -6.00
10% -0.0
12% 0.6
14% 0.9 -8.00
16% 0.9
18% 0.6
20% 0.0 -10.00
22% -0.8
24% -1.8
26% -3.0 -12.00
28% -4.4 Discount Rate (%)
30% -5.9 39
No Rate of Return
Net
Year Benefits No Rate of Return
0 200
1 300
2 350 900
NPV at 12% 747
IRR #NUM! 800
700
Discount Net Present Value (M$)
Rate NPV 600
0% 850.0
2% 830.5 500
4% 812.1
6% 794.5 400
8% 777.8
10% 762.0
300
12% 746.9
14% 732.5
200
16% 718.7
18% 705.6
20% 693.1 100
22% 681.1
24% 669.6 0
26% 658.6 0% 5% 10% 15% 20% 25% 30% 35%
28% 648.0 Discount Rate (%)
30% 637.9 40
Same Rate of Return
Net Benefits
Project Project
Year 1 2 Same Rate of Return
0 -1000 1000
1 1250 -1250 300
NPV at 12% 116 -116
IRR (%) 25% 25%
200
Discount Project Project Net Present Value (M$)
Rate 1 2
1% 238 -238 100
3% 214 -214
5% 190 -190
0
7% 168 -168 0% 5% 10% 15% 20% 25% 30% 35%
9% 147 -147
11% 126 -126 -100
13% 106 -106
15% 87 -87
17% 68 -68 -200
19% 50 -50
21% 33 -33
-300
23% 16 -16
25% 0 0 Discount Rate (%)
27% -16 16
Project 1 Project 2
29% -31 31
31% -46 46
41
Incremental Rate of Return
Alternative A - Base
Investments Profits Present
or or Net Value Present
Year Costs Benefits Benefits Factor Value
NPV = 6.3
0 8 0 -8 1.00 -8.0 IRR = 100.0%
1 0 16 16 0.89 14.3 MIRR = 100.0%
B/C = 1.79
Alternative B - Base
Investments Profits Present
or or Net Value Present
Year Costs Benefits Benefits Factor Value
NPV = 7.1
0 100 0 -100 1.0000 -100.0 IRR = 20%
1 0 120 120 0.8929 107.1 MIRR = 20%
B/C = 1.07
Alternative B - Alternative A
Investments Profits Present
or or Net Value Present
Year Costs Benefits Benefits Factor Value
NPV = 0.86
0 92 0 -92 1.0000 -92 IRR = 13%
1 0 104 104 0.8929 93 MIRR = 13%
B/C = 1.01
42
IRR Reinvestment Assumption
IRR IMPLICIT ASSUMPTION:
ALL CASH FLOW VALUES WILL EARN THE IRR INTEREST RATE
Discount
Rate (i)
12.0%
Future Value in Year 4
Investments Profits If You If You Receive
or or Net Invest at and Invest at
Year Costs Benefits Benefits 29.3% 29.3%
a b c d = c-b Interest Interest
NPV= 3508
Total 27940
IRR= 29.3%
43
Modified Internal Rate of Return
Modified Internal Rate of Return Calculation
Financing Reinvestment
Rate (i) Rate (i)
12.0% 12.0%
MIRR = 20.7%
44
Benefits X Cost
120
100
Alternative B
80
Benefits
60
40
20
Alternative A
0
0 20 40 60 80 100 120
Costs
45
Net Benefits X Costs (Efficiency Frontier)
7
Alternative B
6
Net Benefits (NPV)
5
Alternative A
0
0 20 40 60 80 100 120
Costs
46
Comparison of Alternatives
• When comparing project-alternatives,
the Net Present Value (NPV) is used
to select the optimal project-alternative
(alternative with highest NPV)
• The Internal Rate of Return (IRR) or
the B/C ratio are not recommended to
compare alternatives of a given project
Alternatives NPV
Projec 0.0
Optimal
t 3.7
Alternative:
6.7
Highest NPV
5.5
47
Ranking Projects
• When comparing the economic priority
of different projects, a recommended
economic indicator is the NPV per
Investment ratio
Selected NPV/Investment
Alternative P
Project 8.4 R
s Overlay I
O
5.2 R
Reseal I
T
2.1 Y
Overlay 48
Budget Constraints Simple Methodology
Selected NPV Investme NPV per
Projects nt Investme
Alternativ nt
e 16.8
P
2.0 8.4
R
Overlay
I
15.6
O
3.0 5.2
R
Reseal
I
20.0
Available Budget T
5.0 4.0
Y
Overlay
3.0
Budget 2.0
Constraint 1.5
Cut Off
Reseal
5.049
Budget Constraints Optimization
Projects Alternatives NPV
Evaluates all possible
0.0
combinations of project-
3.7
alternatives to find the
6.7
combination that maximizes
5.5
the NPV of the overall
network for the given budget
0.0
constraint.
2.0
1.0 P = Number of projects
3.5 A = Number of alternatives
C = Number of possible
0.0 combinations
Available Budget 5.4 C=A^P
2.1
3.2
50
HDM-4 Optimization Example (1)
Section 1
Option Cost NPV
A 2 4
B 5 7
C 7 8
Section 2
Option Cost NPV
A 1 3
B 3 6
C 5 8
9
C
8
C
7
B B
6
4
A
dNPV/dCost
A
3
0
0 1 2 3 4 5 6 7 8
Cost
Section 1 Section 2
52
HDM-4 Optimization Example (3)
18
16
1-C, 2-C
14 1-B, 2-C
12
1-A, 2-C
10
8
1-A, 2-B
6
1-A, 2-A
4
0
0 2 4 6 8 10 12 14
Cost
Combination of project alternatives Network
that maximizes the NPV of the
network 53
Appraisals & Post Evaluations (1)
54
Appraisals & Post Evaluations (2)
55
Sensitivity Analysis
• Consequences of changes on inputs
• Investments Costs
• Normal Traffic
• Traffic Growth Rate
• Generate Traffic
• Investment Cost
• Road User Benefits
57
Risk Analysis
•Inputs vary at the same time Country
Project
Africa Region
Road Management Initiative
Road Road from Point A to Point B
25%
Median 11.7%
Percentile 25% 9.4%
20%
Percentile 50% 11.7%
15% Percentile 75% 14.1%
10%
Probability that IRR is less than 12% 50%
5% Probability that IRR is greater than 12% 50%
0%
0.50
0.58
0.65
0.73
0.81
0.88
0.96
1.04
1.12
1.19
1.27
1.35
1.42
1.50
1.58
1.65
1.73
1.81
1.88
1.96
Multiplier Factor Upgrade Road to Surface Treatment Standard
8%
7%
Frequency Distribution
14% 5%
12%
4%
Frequency Distribution
10%
3%
8%
2%
6%
4% 1%
2% 0%
10.1%
14.2%
15.3%
16.3%
20.4%
21.4%
12.2%
13.2%
17.3%
18.3%
19.4%
22.4%
23.5%
24.5%
6.0%
7.1%
8.1%
9.1%
5.0%
11.2%
0%
0.50
0.58
0.65
0.73
0.81
0.88
0.96
1.04
1.12
1.19
1.27
1.35
1.42
1.50
1.58
1.65
1.73
1.81
1.88
1.96
O Community
Type of Network
Rural Transport Infrastructure Trunk or Provincial Road
61
Economic & Social Benefits
• Consumers and producers surplus approaches are very
economic in orientation. Yet roads provide ‘social benefits’ –
including improved access to health and education facilities
and improved social mobility that cannot be easily translated
into conventional economic benefits. – Although they may
have important long term ‘economic’ consequences.
Improved health and education and more secure social
networks increase long term earning capabilities but so far
the economic forecasting framework does not include this.
62
Indices and Ranking
• Widely used for feeder road planning; there are many
different approaches
e.g. i) cost of improvement / population
ii) estimated trips / cost
63
Example of Two Indices
64
Community Priorities
65
Cost Effectiveness Analysis (CEA)
66
CEA Comparison of Alternatives
Alternatives Investment
Project 2.0
Optimal
3.7
Alternative:
1.7
Lower Investment
5.5
67
Projects Eligibility with CEA
150 Eligible
Not Eligible
500
68
Effectiveness Indicator Threshold
40 ?
Reasonable Non Reasonable
35
?
30 Evaluate Universe
Frequency of Projects
25
of Projects and
Available Budget
20
15
10
0
0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900 950
Investment per Population (US$/person)
69
Possible CEA Indicators
70
Options for Beneficiary Population
71
Total Beneficiary Population (1)
Main
D Population
Center
B C E F
Village
74
Multi Criteria Analysis (2)
76
Multi Criteria Analysis Example (1)