PROJECT: ANCHOR GRANDSUITES

SUBJECT: SITE PHOTOS FOR DAILY CONSTRUCTION REPORT (DCR)

DATE: 01 JULY 2020

SKELETAL CREW ACTIVITIES

A. DAY SHIFT (D/S)

1. Evaluation of Fire Hazards, waterline leaks, if any, and other possible problem at site – Parking Floors
(Turning off of breakers, checking of electrical wirings)

2. Securing of power connections and supply – GF, PL1, PL2


PROJECT: ANCHOR GRANDSUITES

SUBJECT: SITE PHOTOS FOR DAILY CONSTRUCTION REPORT (DCR)

DATE: 01 JULY 2020

SKELETAL CREW ACTIVITIES

A. DAY SHIFT (D/S)

3. Checking of water supply and water tank – Ground Floor

4. Preparatory for tiling works at PL5


PROJECT: ANCHOR GRANDSUITES

SUBJECT: SITE PHOTOS FOR DAILY CONSTRUCTION REPORT (DCR)

DATE: 01 JULY 2020

SKELETAL CREW ACTIVITIES

A. DAY SHIFT (D/S)

5. Clearing works at staging area

6. Layout of TSP at Toilet and bath area (PL5 barracks)


PROJECT: ANCHOR GRANDSUITES

SUBJECT: SITE PHOTOS FOR DAILY CONSTRUCTION REPORT (DCR)

DATE: 01 JULY 2020

SKELETAL CREW ACTIVITIES

A. DAY SHIFT (D/S)

7. Installation of Waterline at 7th floor water tank for barracks water supply.

12. Installation of partition walls at T&B and Shower area (PL5 Barracks)
PROJECT: ANCHOR GRANDSUITES

SUBJECT: SITE PHOTOS FOR DAILY CONSTRUCTION REPORT (DCR)

DATE: 01 JULY 2020

SKELETAL CREW ACTIVITIES

A. DAY SHIFT (D/S)

15. Checking of DMCI materials on site c/o stockclerk

16. Monitoring of DMCI site equipment


PROJECT: ANCHOR GRANDSUITES

SUBJECT: SITE PHOTOS FOR DAILY CONSTRUCTION REPORT (DCR)

DATE: 01 JULY 2020

SKELETAL CREW ACTIVITIES

A. DAY SHIFT (D/S)

17. Monitoring of Body Temperature of Skeletal Crew

18. Visit OSM supply and stockpile to check conditions


PROJECT: ANCHOR GRANDSUITES

SUBJECT: SITE PHOTOS FOR DAILY CONSTRUCTION REPORT (DCR)

DATE: 01 JULY 2020

SKELETAL CREW ACTIVITIES

A. DAY SHIFT (D/S)

19. Visit to ODC offices to check safety.

20. Implementation of general safety to building exterior– PROJECT SITE


PROJECT: ANCHOR GRANDSUITES

SUBJECT: SITE PHOTOS FOR DAILY CONSTRUCTION REPORT (DCR)

DATE: 01 JULY 2020

SKELETAL CREW ACTIVITIES

A. NIGHT SHIFT (N/S)

1. Housekeeping/Clearing- Collection of waste and wet Garbage at parking floors.

2. Unloading of tile deliveries for temfacil at parking floors.


PROJECT: ANCHOR GRANDSUITES

SUBJECT: SITE PHOTOS FOR DAILY CONSTRUCTION REPORT (DCR)

DATE: 01 JULY 2020

SKELETAL CREW ACTIVITIES

A. NIGHT SHIFT (N/S)

4. Monitoring of DMCI equipment/vehicle at site

4. Monitoring water level at pump room (5cm deep )


PROJECT: ANCHOR GRANDSUITES

SUBJECT: SITE PHOTOS FOR DAILY CONSTRUCTION REPORT (DCR)

DATE: 01 JULY 2020

SKELETAL CREW ACTIVITIES

A. NIGHT SHIFT (N/S)

5. Monitoring of body temperature of skeletal crew

6. Roving and Inspection of Project Security forces at perimeter fences and exterior
PROJECT: ANCHOR GRANDSUITES

SUBJECT: SITE PHOTOS FOR DAILY CONSTRUCTION REPORT (DCR)

DATE: 01 JULY 2020

SKELETAL CREW ACTIVITIES

A. NIGHT SHIFT (N/S)

7. Roving and inspection of Project security forces at perimeter fences and exterior – Inspection of OSM
stockpile at site

8. Housekeeping at PL1 Offices.