AUTOMATION PROJECT STATUS 2018-2019

Prepared By: Md Aminul Islam


E&I ENGINEER
SUPPLY INSTALLATION COMMISSIONING ETC
TANK LORRY FILLING 80% 80% 0% 15 DAYS
DISPLAY BOARDS 0% 0% 0% 10 DAYS
ADDITIVE DOSING SYSTEM 50% 50% 0% 7 DAY
TLF HEADER LINE INSTRUMENTS 100% 100% 0% 3 DAY
TANK FARM MANAGEMENT SYSTEM 70% 0% 0% 20 DAYS
BLUE DYE DOSING SYSTEM 40% 40% 0% 7 DAYS
CONTROL ROOM EQUIPMENTS 70% 70% 0% 20 DAYS
HYDROCARBON DETECTION SYSTEM 0% 0% 0% 15 DAYS
AUTOMATIC FIRE DETECTION & FIRE 96% 80% 0% 7 DAYS
ALARM SYSTEM
ACCESS CONTROL SYSTEM 18% 0% 0% 15 DAYS
IP BASED CCTV SURVEILLANCE 40% 20% 0% 60 DAYS
SYSTEM
TRAY & CABLE LAYING 97.8% 50% 0% 90 DAYS
EARTHING SYSTEM 100% 20% 0% 30 DAYS
Average 58.6% 39.2% 0%
OVERALL AUTOMATION PROGRESS
STATUS

SUPPLY

39.2%
ISTALLATION

58.6%
COMMISSIONING
AUTOMATION WORK PLAN 2018-2019
• AUTOMATIC FIRE DETECTION & FIRE ALARM SYSTEM ………JULY 2019

• TANK FARM MANAGEMENT SYSTEM -----------------------------AUG 2019

• TLF HEADER LINE INSTRUMENTS ----------------------------- JULY 2019

• TRAY & CABLE LAYING ----------------------------------------------SEPT 2019

• EARTHING SYSTEM -------------------------------------------AUG 2019

• IP BASED CCTV SURVEILLANCE SYSTEM ---------------- SEPT 2019

• ACCESS CONTROL SYSTEM --------------------------------- AUG 2019