E&I ENGINEER SUPPLY INSTALLATION COMMISSIONING ETC TANK LORRY FILLING 80% 80% 0% 15 DAYS DISPLAY BOARDS 0% 0% 0% 10 DAYS ADDITIVE DOSING SYSTEM 50% 50% 0% 7 DAY TLF HEADER LINE INSTRUMENTS 100% 100% 0% 3 DAY TANK FARM MANAGEMENT SYSTEM 70% 0% 0% 20 DAYS BLUE DYE DOSING SYSTEM 40% 40% 0% 7 DAYS CONTROL ROOM EQUIPMENTS 70% 70% 0% 20 DAYS HYDROCARBON DETECTION SYSTEM 0% 0% 0% 15 DAYS AUTOMATIC FIRE DETECTION & FIRE 96% 80% 0% 7 DAYS ALARM SYSTEM ACCESS CONTROL SYSTEM 18% 0% 0% 15 DAYS IP BASED CCTV SURVEILLANCE 40% 20% 0% 60 DAYS SYSTEM TRAY & CABLE LAYING 97.8% 50% 0% 90 DAYS EARTHING SYSTEM 100% 20% 0% 30 DAYS Average 58.6% 39.2% 0% OVERALL AUTOMATION PROGRESS STATUS
SUPPLY
39.2% ISTALLATION
58.6% COMMISSIONING AUTOMATION WORK PLAN 2018-2019 • AUTOMATIC FIRE DETECTION & FIRE ALARM SYSTEM ………JULY 2019
• TANK FARM MANAGEMENT SYSTEM -----------------------------AUG 2019
• TLF HEADER LINE INSTRUMENTS ----------------------------- JULY 2019