Professional Documents
Culture Documents
HASIT SETH
16 October 2020
♔Remedies
♕Civil Wrongs
♞Contractual Remedies
♞Equitable Remedies
♞Constitutional Remedies
♞Statutory Remedies
♕Criminal Wrongs
♞Imprisonment
♞Fines
♞Other punishments
♔Damages
♔Equitable Remedies
♕Specific Relief
♕Injunction
♔Restitution
♕Quantum Merut
[T]he proper rule in such a case as the present is this:- Where two parties
have made a contract which one of them has broken, the damages which
the other party ought to receive in respect of such breach of contract
should be such as may fairly and reasonably be considered either arising
naturally, ie, according to the usual course of things, from such breach of
contract itself, or such as may reasonably be supposed to have been in the
contemplation of both parties, at the time they made the contract, as the
probable result of the breach of it. (emphasis supplied)
♕The arbitrators also found that, ““Breach of the DBA prevented the fulfilment
of a condition precedent to the performance of a distinct and separate
contract; it prevented the MOMA from commencing.”
♔Govt. appealed to court. Single judge upheld GWA’s contentions.
♔The Court of Appeal, reversed, rejecting damages claimed as too
remote by arguing:
♕Govt. could have got water plan built by someone else if GWA terminated
DBA for breach. And then Govt. could have given MOMA to GWA.
♕2nd – Govt. knew and intended that performance by both the parties would
lead to commencement of MOMA.
♕4th - “…there is no express term in the DBA which limits the Government’s
liability in damages to GWA’s loss of earnings under the DBA and no finding
by the arbitrators that such a term was to be implied into the DBA. “
♔Facts:
♔2 Contracts with Govt. to supply potatoes & non-veg food.
♔Maula paid ₹10,000 and ₹8,000 as performance security.
♔Govt. rescinded the contracts and forfeited the deposits for persistent
supply defaults.
♔Maula filed a suit for Rs 20,000 for performance security.
♔Supreme Court:
♔“Where the Court is unable to assess the compensation, the sum
named by the parties if it be regarded as a genuine pre-estimate may
be taken into consideration as the measure of reasonable
compensation… ”
♔“… but not if the sum named is in the nature of a penalty.
♔“…Where loss in terms of money can be determined, the party
claiming compensation must prove the loss suffered by him.”
♔Key here: Govt. led no evidence of actual loss. So trial court and later
SC decreed the suit for not proving losses suffered by Govt.
♔Alternate rates of interest if mortgage interest not paid in time are not
penalties but part of written contract.
♕Banke Behari v. Sunder Lal, 1893 SCC OnLine All 28, (Allahabad, 6 JJ)
♔Earnest money
♕Shree Hanuman v. Tata Aircraft (1969) 3 SCC 522, (3 JJ)